HomeMy WebLinkAboutStaff Report 3.D 8/4/2014DATE: August 4, 2014
TO: Honorable Mayor and Members of the City Council through City Manager
n' C Director, Public Works &Utilities
FROM: Dan St. 410�
Larry Zimmer, IE. — Capital Improvements Division Manager
SUBJECT: Resolution Accepting Completion of the Swim Center Energy Efficiency and
Renewable Energy Project and Modify CIP Budget
RECOMMENDATION
It is recommended that the City Council adopt the attached resolution accepting completion of
the construction contract for the Swim Center Energy Efficiency and Renewable Energy Project
and modify the CIP budget.
BACKGROUND
The Swim Center and Energy Efficiency and Renewable Energy Project consists of the
mechanical improvements to the Swim Center plus lighting retrofits at various locations
throughout the City. The Swim Center project included the replacement of the swimming pool
filters, heaters and pumps. The project also included the construction of a shade trellis and solar
hot water heating system. The lighting retrofits were completed as a separate project in
December 2012 and are not related to this recommended construction contract acceptance. This
work continues the City's efforts to retrofit equipment to reduce energy use, costs, and
greenhouse gas emissions.
Bids were opened on January 24, 2013, and on February 4, 2013, the City Council approved the
project budget and awarded the construction contract to Tricon Aquatics in the amount of
$479,369.00. Construction was successfully completed on April 9, 2014. The Community
Facilities Impact Fee Fund provided interim financing for the project and will be reimbursed in
full by Pacific Gas and Electric's (PG&E) On -Bill Financing Loan (OBF) Program once the
project is accepted and final documents are completed.
The proposed action meets Council Goal: "Plan for and implement priority capital projects as
funding permits".
Agenda Review:
City Attornev Finance Director
City Manager_
DISCUSSION
The final construction contract cost is $502,023.28 including change orders totaling $22,654.28
which is 4.7% of the base bid. The approved project budget established a change order
contingency of $31,000 for unforeseen conditions. Change orders included: trellis deck material,
lead paint abatement, removal and replacement of the entry doors to place filters, training pool
auto -fill and bypass, extra flange connection, pump technician assistance, gas line connection,
and a unistrut cage to support pipes.
The Swim Center facility was originally constructed in 1965 and many elements of the
mechanical room had not been updated since then. During construction, issues arose that needed
immediate attention for successful completion of the project including the replacement of the gas
regulator, corroded electrical wires and breakers, chemical probes and chlorinator for the small
pool, as well as hiring a diver to plug main drain lines. Additionally, the County of Sonoma
Environmental Health Department required bringing the facility to current health code which
added project expenditures for replacing main drain covers, water line tiles, and patching and
cleaning plaster.
Construction of the shade trellis and solar system began in March of 2013 and was completed
prior to the 2013 swim season. The filtration equipment and pumps did not arrive in time for a
successful installation prior to the 2013 swim season so staff placed this project on hold until the
swim season finished. Work resumed in October 2013 and was completed prior to the 2014
swim season.
The East Washington Place developer, Regency Centers, replaced the old, defunct solar hot
water heating system as a condition of development. Staff incorporated Regency's solar hot
water design into the City's Swim Center Energy Efficiency project to allow for seamless
installation by the City's contractor. The City has received payment from Regency to cover the
installation of the solar system including the supporting trellis and related inspection and project
management costs. Regency paid the City's consultant directly for the design for the solar
portion of the project.
The project was permitted and inspected by the City's Building Division and the County of
Sonoma Environmental Health Services Division and has received its final approval for use.
There are no disputed claims and the project was completed without any significant incidents.
FINANCIAL IMPACTS
PG&E has committed $594,244 fiom the On -Bill Financing Program (OBF) for the Swim Center
improvements and the lighting retrofits. The payment received from Regency is $87,626.86.
The total available funding is $681,870.86. However, the unforeseen facility replacements and
the staff time associated with these activities increased the project to $16,409.04 over the total
available funding as summarized in the table below:
Project Funding Sources
PG&E OBF Loan
2013-2014 CIP
Project
87,627 1
Budget
Expenditures
Lighting Retrofit
0
53,366
Design
25,000
25,000
Construction Contract
479,369
502,023
Contingency
31,000
0
Construction Mgmt. &
15,000
83,625
Inspection
CIP Overhead/Salaries
39,000
34,266
CIP BUDGET
589,369
698,280
TOTAL
Project Funding Sources
PG&E OBF Loan
594,244
Regency Payment
87,627 1
CIP Budget Adjustment
(based on this action)
16,409
Total Funding Available
698,280
The Finance Department has indicated that the additional funds to augment the CIP budget will
come from the unexpended budget for the FYI General Fund budget.
The PG&E OBF loan funds will be received at project completion and acceptance in order to pay
back the interfund loan with interest. The PG&E loan debt will be paid back using energy
savings resulting from the project. The City expects to save $26,272 annually on its gas and
electric bill for the swim center and an additional $30,142 for the lighting retrofits. These
savings will be used to pay off the improvements over approximately the next ten (10) years.
ATTACHMENTS
1. Resolution
443
Attachment 1
RESOLUTION ACCEPTING COMPLETION OF THE
CONSTRUCTION CONTRACT FOR THE SWIM CENTER ENERGY EFFICIENCY
AND RENEWABLE ENERGY PROJECT
PROJECT NO. C14501001
WHEREAS, in accordance with Section 68 of Article X of the City of Petaluma Charter,
Section 20162 of the California Public Contract Code and other applicable law, the City of
Petaluma solicited bids for the Petaluma Swim Center Energy Efficiency and Renewable Energy
Project ("Project'); and
WHEREAS, bids for the Project were opened on January 24, 2013, in accordance with
California Public Contract Code Section 4104.5 and other applicable law; and
WHEREAS, the apparent low bid for the Project was Tricon Aquatics in the amount of
$479,369.00; and
WHEREAS, by Resolution No. 2013-013, adopted on February 4, 2013, the City Council found
the bid of $479,369.00 for the Project to be the lowest responsive bid, and awarded the Project to
Tricon Aquatics; and
WHEREAS, the following contract change orders (CCO) affecting the Project amount have
been approved; and
Chance Order
Number
Descriotion
Amount
CCO#1
Expanded metal for shade structure
$ 2,976.24
CCO #2
Lead paint abatement prior to demolition
$ 8,013.20
CCO #3
Remove and replace double doors to install filter
$ 1,715.00
CCO #4
Auto -fill mechanism and bypass pipe for training pool
$ 1,658.00
CCO #5
Extra flange connection
S 1,812.00
CCO #6
Pump Technician
$ 406.00
CCO #7
Pit slab and waterproofing removed from contract
($4,500.00)
CCO #8
Install gas new line
$ 997.00
CCO #9
Heater flue through roof
$ 576.84
CCO #10
Final Closeout Resolution of All Disputed Issues (including
but not
limited to) pipe support with unistrut cage
$ 9,000.00
Total change orders:
$22,654.28
4
WHEREAS, the final contract amount, as amended, including all change orders, is $502,023.28;
and
WHEREAS, the estimated total cost of the Project is $698,279.80, is $16,409.04 over the
available funding; and
WHEREAS, the City is responsible for initial cost of implementation of efficiency measures
until funds from PG&E Loan are received; and
WHEREAS, the General Fund has unexpended funds from Fiscal Year 2013-2014 to pay the
cost overage; and
WHEREAS, PG&E has entered into agreement for City use of the On -Bill Financing Loan
Program and will fully fund eligible project costs upon successful project completion, to be paid
back monthly within City -related utility billing; and
WHEREAS, City staff, including Building Division inspectors, have inspected the Project and
determined that it has been completed in accordance with the contract requirements, subject to
completion of the punch list work, and the Contractor's continuing warranty and other
obligations pursuant to the contract; and
WHEREAS, based on the foregoing, staff recommends acceptance of the Project on behalf of
the City.
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City hereby:
1. The contract entitled Petaluma Swim Center Energy Efficiency and Renewable Energy
Project, Project No. 014501001, with the final contract amount of $502,023.28, is
accepted as complete, subject to the Contractor completing the punch list work prior to
the release of the retention, and the Contractor's continuing warranty and other
obligations pursuant to the contract.
2. The City Cleric is hereby authorized and directed to file a Notice of Completion
concerning the Project with the Sonoma County Clerk's Office within ten (10) days of
the date of this Resolution.
3. Staff are hereby authorized and directed to release all undisputed retention not subject to
pending change orders within sixty (60) days of the date of this Resolution and in
accordance with the terms of the Project contract, California Public Contract Code
Section 7107 and applicable law.
4. Authorizes $16,409.04 from the General Fund undesignated fund balance 1100.14700.