HomeMy WebLinkAboutStaff Report 3.D 9/8/2014 (2)(i) DATE: TO: September 8, 2014 Honorable Mayor and Members of the City Council through City Manager FROM: Dan St. j ofl } fSre — Director, Public Works & Utilities Larry Zimmer, P.E. — Capital Improvements Division Manager SUBJECT: Resolution Approving the Budget and Authorizing Award of Contract for the Western Avenue Water Main Extension (Bantam Way to Benjamin Lane) Project RECOMMENDATION It is recommended that the City Council Approve the Budget and Authorize the Award of Contract for the Western Avenue Water Main Extension (Bantam Way to Benjamin Lane) Project. BACKGROUND To maintain and improve the condition of the City's water system, the Department of Public Works and Utilities annually replaces water line mains throughout the City to add redundancy and improve reliability. To address operational issues with water distribution to the western area of the City's service area, a 12 -inch water main is required in Western Avenue between Bantam Way and Benjamin Lane. The project is needed to complete a vital service loop and avoid the consistent shutdowns within portions of the western distribution areas. This project will also add fire hydrants and connect services and reduce future maintenance costs. The project location is shown on Attachment 2. The proposed action meets Council Goal: "Plan for and implement priority capital projects as funding permits." DISCUSSION Staff prepared the project design documents and issued a Notice Inviting Bids on June 12, 2014. On July 23, 2014 seven bids were received as follows: Name of Bidder W.R. Forde Associates, Inc. Team Ghilotti Inc. ARB Argonaut Contractors Coastside Concrete Agenda Review: City Attorney Finance Director Bid Total $ 394,698 Lowest Responsible Bidder $ 479,477 $ 534,106 $ 544,754 $ 553,997 City Manager Ghilotti Bros., Inc. $ 598,789 Terracon $ 599.725 Engineer's Estimate $ 440,898 The lowest responsible bidder, W.R. Forde Associates, has performed similar projects for the City of Petaluma, Marin Municipal Water District, and the City of Burlingame. Staff verified that Contractor possesses a valid Class A California Contractor's License, license number 814744, which expires on November, 30 2014, that qualifies Contractor to perform the work. The attached formal protest letter dated June 30, 2014, was received from Team Ghilotti Inc. The basis of their protest is that W.R. Forde Associates did not list subcontractors for grinding and tack oil operations. W.R. Forde's attached response email, dated August 6, 2014, indicates that they will self -perform tack oil operations and grinding, and will not need a subcontractor. WR Forde may rent a grinder, but equipment rentals are not classifieds as subcontractors. This protest letter has been reviewed by staff and has been found not to have merit; therefore staff recommends the protest be rejected. Construction is scheduled to begin in September 2014 and to be completed in December 2014. Construction management and inspection will be conducted by City staff. The project was designed by City staff without reliance on consultants except for geotechnical, survey, and material testing specialists. FINANCIAL IMPACTS The total project budget for the Western Avenue Water Main Extension (Bantam Way to Benjamin Lane) 2014/2015 Project (C67501407) is $699,000. $642,000 is set aside and approved for 2014/2015. The following is a breakdown of the approved 2014/2015 CIP budget: It is not anticipated that the contingency will be entirely spent and the remaining contingency funds will be proportionally returned to their funding source. ATTACHMENTS 1. Resolution 2. Location Map 3. Bid Protest and Response Correspondence 2 Allnroved Revised Construction Contract (low bid) $ 450,000 $ 394,698 Design and Planning (City Staff) $ 20,000 $ 20,000 Administration $ 4,000 $ 4,000 Construction Management & Inspection $ 35,000 $ 35,000 Salaries/Benefits $ 55,000 $ 55,000 CIP Overheads $ 8,000 $ 8,000 Contingency $ 70,000 $ 125,302 TOTAL: $642.000 $ 642.000 It is not anticipated that the contingency will be entirely spent and the remaining contingency funds will be proportionally returned to their funding source. ATTACHMENTS 1. Resolution 2. Location Map 3. Bid Protest and Response Correspondence 2 Attachment 1 RESOLUTION APPROVING THE BUDGET AND AUTHORIZING AWARD OF CONTRACT FOR THE WESTERN AVENUE WATER MAIN EXTENSION (BANTAM WAY TO BENJAMIN LANE) PROJECT WHEREAS, City staff has prepared construction bid documents and advertised for construction the Western Avenue Water Main Extension Project (Bantam Way to Benjamin Lane), Project Number C67501407, ("the Project"); and WHEREAS, in accordance with the City of Petaluma Charter and Municipal Code, California Public Contract Code Section 20162 and other applicable law, City staff solicited bids for the Project; and WHEREAS, the Project was bid on June 12, 2014, and seven bids were received and opened on July 23, 2014 in accordance with applicable law; and WHEREAS, the lowest responsible bid for the Project was submitted by W.R. Forde Associates from Petaluma, CA for $394,698; and WHEREAS, staff has determined that the Contractor's bid satisfies the bidding requirements for the Project; and WHEREAS, staff has verified that W.R. Forde Associates possesses a valid California Contractor's License, Class A, number 814744 that qualifies Contractor to perform the Project; and WHEREAS, the bid protest by Team Ghilotti, Inc. is rejected. W.R. Forde Associates confirmed all work omitted from the subcontractor list shall be self -performed; and WHEREAS, the Project is categorically exempt pursuant to California Environmental Quality Act (CEQA) and Title 14, the California Code of Regulations ("CEQA" Guidelines"), Section 15302, because the Project consists of replacement and reconstruction of existing utility systems and/or facilities involving negligible or no expansion of capacity; and WHEREAS, the funds made available are in the 2014/2015 water and wastewater collection system budget. NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Petaluma hereby: 1. Approves the 2014/2015 project budget of $642,000. 2. In accordance with the City of Petaluma Charter and Municipal Code, California Public Contract Code Section 20162 and other applicable law, waives any and all non- conformance in the bid of Contractor for the Western Avenue Water Main Replacement (Bantam Way to Benjamin Lane) Project, Project Number C67501407 and finds the bid of $394,698 to be the lowest, responsive bid and further finds that W.R. Forde Associates is the lowest responsible bidder. 3. Awards the contract for the Western Avenue Water Main Replacement (Bantam Way to Benjamin Lane) Project, Project Number C67501407 to W.R. Forde Associates in the amount of $394,698, the amount of the lowest responsive bid, conditioned on W.R. Forde Associate's timely executing the project contract and submitting all required documents, including but not limited to, executed bonds, certificates of insurance, and endorsements, in accordance with the project bid documents. 4. Directs staff to issue a notice of award to W.R. Forde Associates. 5. Authorizes and directs the City Manager to execute the project contract on behalf of the City of Petaluma upon timely submission by W.R. Forde Associates of the signed project contract and all other required document, including but not limited to, executed bonds, certificates of insurance, and endorsements, in accordance with the project bid documents. 4 A acwent Mp,1N �X,�ENg1�N N �Eg AV�NUA Wo 6E JAMIN SANE WES BANiPM W G� No c67�a�q.07 PRpJE. commAcron +mmmu. June 30, 2014 City of Petaluma Department of Public Works & Utilities Attn: John C. Brown, City Manager 11 English St. Petaluma, CA 94952 Attachment 3 CrIVE- JUL 3 0 2014 CITY Reference: Western Avenue Water Main Extension Bantam Way to Benjamin Lane City Project Number C67501407 Subject: Protest of Bid Submitted by W. R. Forde Associates Dear Mr. Jolm C. Brown, In accordance with the construction documents, this letter is to notify the City of Petaluma that we are protesting the apparent low bid of W. R. Forde Associates for the project referenced above. Our protest is based on the requirements specified in the bid proposal documents "List of Subcontractors": 'In accordance with the provisions of Section 4102 and 4108, inclusive, of the Government Code of the State of California, each bidder shall list below the name and location of place of business of each subcontractor who will perform a portion of the contract work in excess of one-half of one percent of the total contract price.' Specific work that was listed by other responsive bidders was an asphalt grinding subcontractor and a tack oil subcontractor as required for the paving for bid items 5) 12" Water Alain (C-900 D218), 15) Asphalt Concrete Paving, and 16) Cold Planning/Grind AC Pavement for the above mentioned project. These bid items require a minimum of 1,210 lineal feet of trench paving that is 8 '/2' Wide and 10" thick, and a minimum of 622 Square Yards of AC Grinding. In order to perform such work, a minimum of 3 days of grinding, and the supply and spreading of tack oil is required. At one-half of one percent, W. R. Forde Associates was required to list all subcontractors whose contract value for performing such work would have exceeded $1,973.49. At the time of bid, W. R. Forde Associates listed one subcontractor, Striping Graphics, for striping under bid items 18, 19, and 20. Neither Striping Graphics or W. R. Forde Associates self perform spreading tack oil and/or grinding operations. Given the nature and scope of the work as described in the contract documents, the grinding and tack oil operations would exceed $1,973.49 for contract work performed. Attached to this letter is a quote to Team Ghilotti, Inc, received from Delta Grinding showing a minimum of $4,000 for a daily operated rate for a 67" grinder. At three days of grinding at $4,000 per day, the minimum contract value of the grinding operations would be $12,000. This value far exceeds the minimum value of $1,973.49 per W. R. Forde Associates bid. Similarly, attached to this letter is a quote from Pacific Northwest Oil for the delivery and spread of tack oil showing a 2 ton minimum of tack oil, a value of $1,300 (2 tons at $650 each), a delivery fee of $550, and a 4 hour minimum spread charge, a value of $660 (4 tons at $165 per hour), for a total minimum contract value of $2,510. Based upon the contract documents, more than 2 tons of tack oil would be required further increasing the value of the tack oil work. 2531 Petaluma Blvd South 4 Petaluma, CA 94952 # PAX: 707-763-8711 • wwwa'eamGhilotti.com STATE CONTRACTORS LICENSE il895384 CLASS: A Asphalt grinding requires a specialized grinding machine. Industry standard is to subcontract out this portion of work unless the contractor owns its own grinding machine. In the case of W. R. Forde Associates, we believe they do not own this type of equipment. In addition, it is not industry standard to rent these machines out. Due to the omission of listing a grinding and a tack oil subcontractor on the bid proposal submitted by W.R. Forde Associates, TGI respectfully requests that the agency disqualify their bid as non-responsive and award the contract to Team Ghilotti, Inc. as the low responsive bidder for this project. Sincerel , Robert E. Lee Vice President Team Ghilotti, Inc. CC: W. R. Forde Associates ARB, Inc. Jul 23 2014 11:03AM HP LASERJET FAX �O.H.199ING COMP+'ANS' INC' RECEIVED 07/23/2014 11:4b 925-778-3969 page 1 $131--Wbo 3l°.13,ph. 16chf CA 9.453.1 Estimating/o ficeF. 9025='�7$ CA License A-7869114 Fax: SZ y=71$-39043,NV License A-0076673 xatcherc 025 406-3sgf!i SBE -00U117 PRI(E QUOTATION j WORK ORDER Bid Date: July 23, 2014 Attn: Estiknating Department THE DIFFERENCE IS... _,EET SOW GARB CO'LLkNT ' p,~ PROJECT NAME Western Ave Water Main Petaluma. CA I DAILY RENTAL ( GRIND & LOAD 0" "CERTIFIED WITH THE STATE OF CALIFORNIA AS A SMALL BUSINESS OWNER" SM032117 40" grinder operated daily rental directed by customer -------------$3.0110.00 per 8 hour shift 2411 or 3611 FCSgrinder operated daily rental directed by customer -------$3,2 )0_00 per 8 hour shift 6'7"-713" grinder operated daily rental directed by customer --------54,0 )0.00 per 8 hoar shift PRICE INCLUDES MOBILIZATION FEE . ' NIGirl' PEE: 5150 (S41g) and 5200 (alis) , • i Daily shift rates include one set ofteelh per shin • Options) nigh HP +$500 Saturdays: 5250 (54ft) /5500 (Z611) Additional per shift • Sunday; S500(5cin)/ SHOD(a61t) Additional per hift Weekday OT(54ft) S25 per hr in addition to prorated hourly rate (54001h) •, Weekday OT IUD) S50 per hr In addition to prorated hourly rate (5550th) Y VpM1 undue lV n Dl r1 Vnb: • .Delta Grinding is not responsible for cannot reach includ Ing area around manholes, ma chine is doom& not to exceed total trafficcontrot,iayouq handwork, water valves, trees and other obstructions daily rental rate maximum Cleaning ofslderwaiks, building • Delta Grinding Is not responsible for maintenance • Delta Grinding not responsible for any temporary tapers, posting of"no and protection of milled areas unpotholed, unmarked, or mismarked parking" signs, temporary pavement . Delta Grinding excludes trimming shrubs ortrmas obstructions. delineation or car removal • General to provide minimum of 6' distance • General to pothole all utilities • Unless otherwise indicated, this price between bottom of grinding activities and tops of • General responsible for USA marking excludes any milli ng of concrete any utilities • enerel momracter to assume price does not include cost of a pilot Car . Delta Grinding must be notified within 7.9hrs of any responsibllity for fees, permits, water Ifrequired backcharges meter, or notifications required • Grinders are equipped with standard • Delta Grinding excludes bringing highway surface . General to supply water to grinder 6/8" tooth sparing within longitudinal& transverse slope smoothness . Additional insurance coverage or (wording PrkQ exdudes additional hand work at specs. may incur addlorwl fee dead end streets and court, removal of . Delta Grinding does not accept withholding . General contractor responsible for %.0 on gutter pan or AS ribbon along rentention on daily rental work maintaining safe passage on and vertical curb . Delta Grinding will accept back charge for grinder Brice )around milled areas • excludes araas milling machine downtime, not to exceed actual cast fortime It Is the sole responsibility of the lessee or reatertofollow the requirements of the regional notification center law punuen j.to Article 2 (Commencing with section 421611ofahapter3.l of Division S of Tlde lofthe government code. By signing this Contract, and/or permitting Delta Grinds g Company to commence or to continue to work, the lessee or renter acapts a0 Oabllrdes and responsibilities contained In the regional notification center law. Tot a extent Caused brnegrigence of Delta Grinding (Delta), Delta agrees to defend, Indemnify and hold harmless gen am] contractor and owner from all claims, damall,tees, arMmsts(Claim) relating to Delta'. work under this work order, and Its acts, errors, or omissions. Persuant to civil code 2782.05, Delm's defense and Indpmniry abligadam shall be limited to Its perregtage fault farthe claim. This work order shall superscede and confilaing Indemnity/defense provisions In the original;subcontract agreement and Constitute a moditlotan theroF. Contractor'sacceptance ofthe terms of this work ordershall be evidenced by ether (i) Contradves sighatura below, orpi) Contractor's permljting Delta Grinding Company to commence or to continue to work on the project If you )have any questans please all our of ice at (925177&3939. SignMux Dare RECEIVED 07/23/2014 10:24 7232014 1024 AM FromFadirm N.rhwes Oil Fax Number. 200-460 2506 Pape i of l !�I rid , 1 3310 E. MINER AVENUE STOCKTON, CA 95206 CALIFORNIA CONTRACTORS LICENSE 4 705296 OFFICE 2094634762 Todays Date: 23-Jn1-14 CUSTOMER: CONTACT: ESTIMATOR PROJECT NAME: WESTERN AVE LOCATION: PETALUMA CONTRACT#: • QUOTE IS FOR THE FOLLOWING: els 4 TONS OF SS -111 PRICE QUOTED: $650 PER TON DELIVERY CHARGE: $550 EACH FAX 209 463-2566 OIL QUOTE # 6533 1 :l 17U1112113AtUlll BID DATE: 7/23/2014 TAX INCLUDED • IF SPREADING IS AT NIGHT HOURLY RATE IS: $175.00 PER HOUR Comments: MINIMUM 2 TON OIL PURCHASE PER DELIVERY PLEASE CALL ERIC HICKS @ 209 463-4762 IF YOU HAVE ANY QUESTIONS DUE TO MARKET VOLATILITY THE PRODUCT QUOTED MAY BE INFLUENCED UP OR DOWN BY THE CALTRANS ASPHALT INDEX. ALL PRICES QUOTED STRAIGHT OR CUT WITH WATER. PROTECTION OF EXISTING CONCRETE AND STRIPING BY OTHERS. ALL IN ROUTE CANCELATIONS WILL BE CHARGED AT SPREAD RATE PORT TO PORT Wcdmaday, July 23, 2014 Pop 1 oft 11 10 Carothers, Kent ..,.....................— .� �... From: David Voorhis <dave@wrforde.net> Sent: Wednesday, August 06, 2014 8:16 AM To: Carothers, Kent Cc: Don Russell Subject: TGI Protest Kent: We are in receipt of Team Ghilotti's protest letter regarding our bid for the Western Avenue Water Main project. We would like to emphasize to the City of Petaluma that W.R. Forde was in no way required to list subcontractors for the work referenced in TGI's letter of protest. 1. W.R. Forde has been spreading our own tack oil since the inception of our business and will continue to do so throughout the performance of this project 2. W.R. Forde will perform the Asphalt Grinding operations with either our own equipment or rented equipment (operated or bare). TGI included in their protest a quotation from DELTA GRINDING COMPANY INC. that clearly shows three separate rates for DAILY RENTAL DIRECTED BY CUSTOMER. W.R. Forde may well be renting from Delta Grinding when it is time to perform this item of work. However W.R. Forde elects to proceed with the AC grinding operation, we will not be employing any entity to perform work in the capacity of a subcontractor, and will be spreading our own tack oil with our forces and equipment. There clearly is no requirement for WRF to have listed a subcontractor for work which we will perform ourselves or perform with rented equipment and therefore TGI's protest is completely without merit. Please contact me if you have any questions or need further information, David Voorhis Chief Estimator Office: (510) 215-9338 Fax: (510)215-9867 Cell: (415) 716-2200 W.R. Forde Associates 984 Hensley Street Richmond, CA 94801 From: Carothers, Kent Imailto:kcarothers(@ci.oetaluma.ca.usj Sent: Friday, July 25, 20148:32 AM