HomeMy WebLinkAboutResolution 2015-048 N.C.S. 05/04/2015Resolution No. 2015-048 N.C.S.
of the City of Petaluma, California
ACCEPTING COMPLETION OF THE CONSTRUCTION CONTRACT
FOR THE EAST WASHINGTON STREET AT EDITH STREET
LIGHTED CROSSWALK PROJECT
PROJECT NO. C16101308
WHEREAS, in accordance with Section 68 of Article X of the City of Petaluma Charter,
Section 20162 of the California Public Contract Code and other applicable law, the City of
Petaluma solicited bids for the East Washington Street at Edith Street Lighted Crosswalk Project
("Project"), and
WHEREAS, bids for the Project were opened on July 30, 2014, in accordance with
California Public Contract Code Section 4104.5 and other applicable law; and
WHEREAS, the apparent low bid for the Project was Team Ghilotti, Inc., in the amount
of $131,230; and
WHEREAS, by Resolution No. 2014-146 N.C.S., adopted on September 15, 2014, the
City Council found the bid of $131,230.00 for the Project to be the lowest responsive bid,
awarded the Project to Team Ghilotti, Inc., in the amount of $131,230.00, conditioned on Team
Ghilotti, Inc. timely executing the Project contract and submitting all required documents and
authorized and directed the City Manager to sign the Project contract on behalf of the City, upon
such timely submission and to execute on behalf of the City any amendments to the Project
contract that are necessary to effectively complete the project and/or to realize the Project and/or
cost benefits for the City; and
WHEREAS, the following contract change orders (CCO) affecting the Project amount
have been approved:
Change Order
Number Description Amount
CCO#2 Additional Striping and Pavement Grinding $1,341.55
CCO#3 Ramp Modifications $2,518.28
Total Change Orders $3,859.83
WHEREAS, the final contract amount, as amended, including all change orders,
overruns and undeiruns is $133,351.63; and
WHEREAS, the estimated total cost of the Project is $219,461, and was within the
approved Project budget; and
WHEREAS, City staff have inspected the Project and determined that it has been
completed in accordance with the contract requirements, and the Contractor's continuing
warranty and other obligations pursuant to the contract; and
Resolution No. 2015-048 N.C.S. Page 1
WHEREAS, based on the foregoing, staff recommends acceptance of the Project on
behalf of the City.
NOW, THEREFORE, BE IT RESOLVED by the City Council as follows:
1. The contract entitled East Washington Street at Edith Street Lighted Crosswalk
Project, Project No. C16101308, with the final contract amount of $219,461, is
accepted as complete, subject to the Contractor's continuing warranty and other
obligations pursuant to the contract.
2. The City Clerk is hereby authorized and directed to file a Notice of Completion
concerning the Project with the Sonoma County Clerk's Office within 10 days of the
date of this Resolution.
3. Staff are hereby authorized and directed to release all undisputed retention not subject
to pending change orders within 60 days of the date of this Resolution and in
accordance with the terms of the Project contract, California Public Contract Code
Section 7107 and applicable law.
Under the power and authority conferred upon this Council by the Charter of said City.
REFERENCE:
I hereby certify the foregoing Resolution was introduced and adopted by the
-.-Approved as to
Council of the City of Petaluma at a Regular meeting on the 4th day of May, 2015,
for,
by the following vote:
City Attornby
AYES:
Albertson, Barrett, Mayor Glass, Healy, King, Vice Mayor Miller~
NOES:
None
ABSENT:
Kearney