HomeMy WebLinkAboutStaff Report 3.E 12/07/2015DATE: December 7, 2015
Agenda Item #3.E
TO: Honorable Mayor and Members of the City Council through City Manager
FROM: Dan t. o , RASCE — Director, Public Works & Utilities
Larry immer, P.E. — Deputy Director, Public Works & Utilities
SUBJECT: Resolution Accepting Completion of the East Washington Park Multi -Use
Pathway Project
RECOMMENDATION
It is recommended that the City Council adopt the attached Resolution Accepting Completion of
the East Washington Park Multi -Use Pathway Project.
BACKGROUND
The environmental document for the Petaluma Community Sports Fields identified the need to
construct a new pathway to connect the existing sidewalk on East Washington located west of
the airport at Sky Ranch Drive, to the pathway at the new Petaluma Community Sports Fields.
The project includes an 8 to 10 -foot wide concrete pathway, Americans with Disability Act
(ADA) compliant curb ramps, street lighting, pavement replacement, and pavement striping and
markings. The project location is shown on Attachment 2. The project included new split rail
fencing along the existing pathway at Petaluma Community Sports Fields that had previously
been eliminated from the East Washington Park — Phase 1 project.
The City was awarded Transportation Development Act — Article 3 (TDA -3) funding from the
Metropolitan Transportation Commission (MTC) in the sum of $306,623. The TDA -3 grant was
accepted by the City Council on April 7, 2014, and committed to this project. Bids were opened
on June 17, 2015. On July 20, 2015, the City Council awarded the construction contract to Team
Ghilotti, Inc. of Petaluma, CA, in the amount of $337,833.25. Construction began August 2015.
The proposed action meets Council Goal: "Plan for and implement priority capital projects as
funding permits ". .
DISCUSSION
The final construction contract cost for this project is $349,590.58, which includes three change
orders totaling $3,544.38. There were also some increases in the initial quantity estimates that
contributed to the increase in construction costs above the bid amount.
The first change order was to raise four utility boxes and for installation of quarry fines in the
two foot buffer between the roadway and the pathway. The change order also deducted 158
lineal feet of curb and gutter from the contract that was found to be unnecessary. The total cost
of the change was $1,139.00
The second change order covered the costs to remobilize and properly conform an ADA curb
ramp to an existing sidewalk. It included additional traffic control as well as installation of the
split rail fence along the pathway. The total cost of this change was $6,279.33
The third change order removed additional concrete as part of the conformation of the ADA
ramp and removed thick asphalt sections to allow the subcontractor to drill fence posts for the
split rail fence. The change order also deducted a backflow preventer protective enclosure
deemed unnecessary during construction. The total cost of this change order is a decrease in
contract amount of $3,873.95.
There are no outstanding claims or issues with the project and the contractor performed the work
satisfactorily.
FINANCIAL IMPACTS
Council previously approved a total budget of $486,623, comprised of $180,000 of Parkland
Impact Fees and $306,000 from the aforementioned TDA -3 Grant. With the construction
contract, final quantities, contingency, construction management and inspection, the total cost for
the project was $406,393, as shown in the following project breakdown.
Uses
Contract
Award
Actual Total
Pro ect Cost
Design
$
22,000
$
19,196
Planning/Environmental
$
-
$
-
Land & Easements
$
-
$
-
Construction Contracts
$
337,900
$
349,591
Construction Management
$
50,000
$
29,505
CIP Overhead 2.4%
$
8,100
$
8,100
Administration
$
5,000
-
Pro'ect Contingency
$
63,000
-
TOTAL
$
486,000
$
406,393
Funding Sources
Parkland hn act Fees
$
180,000
$
99,770
Public Works Grant TDA -3
$
306,000
$
306,623
TOTAL
$
486,000
$
406,393
At project closeout, all remaining funds will be returned to the Parkland Impact Fees Fund to be
used on future projects.
2
Following the acceptance of the project, the City Clerk will file a Notice of Completion with the
Sonoma County Recorder and the Finance Department will release the contract retention account
to the contractor within 60 days.
ATTACHMENTS
1. Resolution
2. Location map
Attachment 1
RESOLUTION ACCEPTING COMPLETION OF THE
EAST WASHINGTON PARK MULTI -USE PATHWAY PROJECT
PROJECT NO. C14501403
WHEREAS, in accordance with Section 68 of Article X of the City of Petaluma Charter,
Section 20162 of the California Public Contract Code and other applicable law, the City of
Petaluma solicited bids for the East Washington Park Multi -Use Pathway Project ( "Project "),
and
WHEREAS, bids for the Project were opened on June 17, 2015, in accordance with
California Public Contract Code Section 4104.5 and other applicable law; and
WHEREAS, the apparent low bid for the Project was Team Ghilotti, Inc., in the amount
of $337,833.25; and
WHEREAS, by Resolution No. 2015 -113, adopted on July 20, 2015, the City Council
found the bid of $337,833.25 for the Project to be the lowest responsive bid, awarded the Project
to Team Ghilotti, Inc., in the amount of $337,833.25, conditioned on Team Ghilotti, Inc. timely
executing the Project contract and submitting all required documents and authorized and directed
the City Manager to sign the Project contract on behalf of the City, upon such timely submission
and to execute on behalf of the City any amendments to the Project contract that are necessary to
effectively complete the project and /or to realize the Project and /or cost benefits for the City; and
WHEREAS, the following contract change orders (CCO) affecting the Project amount
have been approved:
Order Number
CC0#1 Additional Labor, Raising Utilities, and Installing
Quarry Fines, Deduct Curb and Gutter
CCO #2 Extra work on ADA curb ramp, Additional
Traffic Control, and Additional Fence
CCO #3 ( Extra Work on ADA curb ramp, asphalt removal,
and Deduction of Backflow Preventer Enclosure
Total Change Orders
Amount
$1,139.00
$6,279.33
($3,873.95)
$3,544.38; and
WHEREAS, the final contract amount, as amended, including all change orders,
overruns and underruns is $349,590.58; and
WHEREAS, the estimated total cost of the Project is $406,393, and was within the
approved Project budget; and
L,
WHEREAS, City staff have inspected the Project and determined that it has been
completed in accordance with the contract requirements, and the Contractor's continuing
warranty and other obligations pursuant to the contract; and
WHEREAS, based on the foregoing, staff recommends acceptance of the Project on
behalf of the City.
NOW, THEREFORE, BE IT RESOLVED by the City Council as follows:
1. The contract entitled East Washington Park Multi -Use Pathway Project, Project No.
C14501403, with the final contract amount of $349,590.58, is accepted as complete,
subject to the Contractor's continuing warranty and other obligations pursuant to the
contract.
2. The City Clerk is hereby authorized and directed to file a Notice of Completion
concerning the Project with the Sonoma County Clerk's Office within 10 days of the
date of this Resolution.
3. Staff are hereby authorized and directed to release all undisputed retention not subject
to pending change orders within 60 days of the date of this Resolution and in
accordance with the terms of the Project contract, California Public Contract Code
Section 7107 and applicable law.
EAST WASHINGTON PARK MULTI -USE
PATHWAY PROJECT
PROJECT NO. C14501403
LOCATION MAP
l
°o� °sT
AO
/i �
I
PROJECT SITE
4-
Attachment 2
p '9s
C°< °cTF� c oti
MUNICIPAL
AIRPORT _
Date :DECEMBER 7, 2015
City of Petaluma
Public Works and Utilities
Department
f
9
0