Loading...
HomeMy WebLinkAboutStaff Report 4.A 07/18/2016Agenda Item #4.A � F 1 DATE: July 18, 2016 TO: Honorable Mayor and Members of the City Council through City Manager FROM: Qanofin, RASCE — Director, Public Works and Utilities Larry Zimmer, P.E. — Deputy Director, Public Works and Utilities SUBJECT: Resolution Authorizing Award of Contract for the Denman Reach Phase 3 Improvements Project and Revising the Project Budget RECOMMENDATION It is recommended that the City Council adopt the attached Resolution Authorizing Award of Contract for the Denman Reach Phase 3 Improvements Project and Revising the Project Budget. BACKGROUND Placing flood terracing within the Petaluma Watershed in concert with the development of a river and creek trail system was envisioned in the 1996 River Access and Enhancement Plan and was adopted as a policy in the General Plan 2025 in 2008. Once completed, the three phases of Denman Reach will meet this policy and provide an opportunity to develop a stewardship program with area businesses and residents. Flood plain modeling has concluded that the completed project will lower the flood elevation for a one - hundred year storm by up to 1 foot in some areas. Phases 1 and 2 were completed in 2005 and Phase 3, the final phase, will complete the project through the Denman Reach of the Petaluma River between the Corona Road and Twin Bridges. In the fall of 2008, the City submitted a two -part grant application to the State of California for land acquisition and continuation of the flood terrace, riparian habitat enhancement, and trail improvements within the Denman Reach. The first grant application was to the California Natural Resources Agency's (NRA) River Parkways Program for land acquisition in the amount of $1,150,000, which was initially partially funded at $850,000 but later augmented with an additional $165,262 bringing the land acquisition grant to $1,015,262. The second application was to the Department of Water Resources' (DWR) Urban Streams Restoration Program for $993,375, which was fully funded for design and construction. In addition to the state funding grants, the Sonoma County Water Agency (SCWA) Zone 2A committed matching funds of approximately $512,500 as authorized by City Council Resolution No. 2015 -007 N.C.S. There are five properties affected by the construction of Denman Reach Phase 3, three of which are the vacant parcels located on the west side of Industrial Avenue directly across from the intersection of Benson Way and Industrial Avenue. Through acquisition of two parcels in fee simple and the other three parcels by temporary construction and permanent trail easements, the project can complete the flood plain terracing and add approximately 2,100 feet of trail between Corona Road and the intersection of Industrial Avenue and Petaluma Boulevard North. The proposed action meets Council Goal: "Plan for and implement priority capital projects as funding permits ". DISCUSSION On December 2, 2013, the City Council authorized the execution of a Professional Services Agreement with Questa Engineering Corporation to provide design and environmental services for the project. Staff met with adjacent parcel owners during planning and design of the project and has provided quarterly reports to the SCWA Zone 2A Committee and Department of Water Resources. Most recently, the project was presented to the Tree Advisory Committee on June 15. City staff prepared the contract documents and issued a Notice Inviting Bids on May 26, 2016. On June 22, 2016, three bids were received as follows: Name of Bidder Base Bid Total Bid Alt A Bid Alt B Bid Alt C Team Ghilotti, Inc. of Petaluma $1,234,007 $31,200 $132,272 $152,800 Argonaut Constructors of Santa $1,216,273 $80,000 $231,760 $99,750 Rosa Ghilotti Construction Company of $1,337,807 $48,000 $183,950 $92,250 Santa Rosa Engineer's Estimate $1,000,000 $40,000 $91,000 $41,000 The lowest responsible bidder, Team Ghilotti, Inc., has performed similar flood terracing and wetland enhancement projects for the City of Santa Rosa, County of Napa, and Vallejo Sanitation and Flood Control District. Staff verified that Team Ghilotti, Inc. possesses the required Class A California Contractor's License, number 895384, which expires on April 30, 2017, which is appropriate for the work. The bid broke out three additive alternate bid schedules to allow the City to maximize additional improvements if funding permitted and to provide a contingency for landscape maintenance services. The base bid schedule covers the core elements of the flood terracing projects, including a 2, 100 linear foot trail segment, wetland enhancement and creation, irrigation, and hydroseeding. Acceptance of bid alternate A would add 1,000 feet of quarry fine trail looping around the new and existing wetlands. Bid alternate B is for 833 feet of trail connecting to Petaluma Boulevard near the Industrial Avenue / Stony Point Road intersection. Bid alternate C includes post and cable fence, landscaping, and a year of landscape maintenance. The trail envisioned in bid alternate B would require three additional easements that have not been acquired. Although communications with these property owners have been favorable, permanent easements were not pursued because earlier engineering estimates indicated that the project would exceed the available budget. 2 Bid alternate C was added as a contingency in case the City's DWR grant partner, Conservation Corps North Bay (CCNB), could not be contracted to do the work. At this time, it appears that the City's partner can perform the requisite work. CCNB is a listed partner to the City on the DWR grant and has provided an estimate of $90,000 to complete the landscape installation portion of work in bid schedule C that in comparison to the low bid is a cost savings to the project. Upon completion of the landscape work, the City will install two interpretative displays along the terracing portion of the site and procure a one -year landscape maintenance contract for the project. In addition, the City will draft an amendment with Questa Engineering in the amount of $55,000 to provide additional construction and environmental services due to unforeseen changes and additional requirements of the regulatory permitting agencies. The landscape contract and contract amendment will come back to City Council for authorization at a future meeting. The additional funds have been included in the revised project budget. The project was approved concurrently with the adoption of a Mitigated Negative Declaration, through Resolution #2012 -138 N.C.S. adopted by the City Council on September 10, 2012. Construction is scheduled to begin in late August and will continue for 80 working days, weather conditions permitting. Construction management will be conducted by City staff with assistance from Questa for construction and environmental services and a consulting material testing firm. It is recommended that the City Council authorize the City Manager to execute a contract for the Denman Reach Phase 3 Improvements Project base bid and bid alternative A with the apparent low bidder, Team Ghilotti, Inc. Since the needed easements are not in place, bid alternate B is not recommended but may be added by change order if easements are acquired in time and sufficient project contingency budget remains available. Bid alternate C is not needed because a separate landscape contract with CCNB is proposed and will be scheduled for Council action at a later date. FINANCIAL IMPACTS The approved FY 16/17 CIP budget for the subject project is $2,940,000, which included past land acquisitions and right of way work. Project funding is comprised primarily of Department of Water Resources Grant with Sonoma County Water Agency Zone 2A, Sonoma County Agricultural Preservation and Open Space District, and City storm drainage impact fees for local grant match as summarized in the table that follows. However, during design, it was discovered that 40 -year old City water and sewer lines traverse the project to provide service to customers along Petaluma Boulevard North. Therefore, it is proposed that the City Waste Water and Water Capital funds be utilized to replace and relocate the old sewer and water main that bisect the project in the amount of $84,000 per fund, which represents the cost of upgrading and replacing each pipeline. Those funds, which are currently available, would be transferred as a result of the proposed action. With this revision, the amended budget would be $3,108,000 as is also summarized in the following table. The revised budget would cover the base bid and alternate bid A of $1,234,007 and allow a project contingency of $240,681 to complete the project including bid alternate B if easements 3 are acquired in time. The current project estimate includes an anticipated amendment to the Questa Engineering contract in the amount of $55,000 as addressed previously and the proposed landscape agreement with CCNB for $90,000. The following is a breakdown of the proposed FY 16/17 CIP budget and the proposed current project budget: Uses CIP Budget FY16/17 Current Estimates Design $ 186,000 $ 236,681 Legal $ 4,000 $ 4,000 Land Acquisition $ 1,045,000 $ 1,045,000 Construction Contracts $ 1,373,000 $ 1,234,007 Landscaping/Kiosks $ 136,000 Regulatory Permits $ 37,312 Construction Management $ 150,000 $ 130,000 CIP Overhead $ 44,000 $ 44,000 Administration $ 1,000 $ 1,000 Project Contingency $ 137,000 $ 240,000 TOTAL $ 2,940,000 $ 3,108,000 Funding Sources Waste Water Capital $ 84,000 Water Capital $ 84,000 Storm Impact Fees $ 370,000 $ 370,000 State Grants $ 1,015,000 $ 1,015,000 SCWA Zone 2A Assessments $ 512,000 $ 512,000 Dept of Water Resources Grant $ 993,000 $ 993,000 Sonoma Open Space Grant $ 50,000 $ 50,000 TOTAL $ 2,940,000 $ 3,108,000 Note: City staff salary and benefits costs are included in appropriate project phases for the project. It is anticipated that grant funds will be fully expended for this project and any unused local funds will be returned to the appropriate accounts for use on future projects. Budget adjustments of $84,000 to each of the Water and Wastewater Capital Funds will be brought forward during the first quarter budget adjustments in order to be reflected in the revised FY 16/17 budget ordinances. ATTACHMENTS 1: Resolution 2. Location Map Attachment 1 RESOLUTION AUTHORIZING AWARD OF CONTRACT FOR THE DENMAN REACH PHASE 3 IMPROVEMENTS PROJECT AND AMENDING THE PROJECT BUDGET WHEREAS, City staff has prepared construction bid documents and advertised for construction of the Denman Reach Phase 3 Improvements Project, Project Number 000500208, ( "the Project "); and WHEREAS, in accordance with the City of Petaluma Charter and Municipal Code, California Public Contract Code Section 20162 and other applicable law, City staff solicited bids for the Project; and WHEREAS, the Project was bid on May 26, 2016, and three bids were received and opened on June 22, 2016 in accordance with applicable law; and WHEREAS, the lowest responsible bid for the base bid and bid alternative A was submitted by Team Ghilotti, Inc. from Petaluma, CA for $1,234,007; and WHEREAS, staff recommends the construction contract be awarded for the base bid and bid alternate A for a total contract amount of $1,234,007; and WHEREAS, staff has determined that the Contractor's bid is responsive and satisfies the bidding requirements for the Project; and WHEREAS, staff has verified that Team Ghilotti, Inc. possesses a valid California Contractor's License, Class A, number 895384 that is acceptable for the Project; and WHEREAS, the project was approved concurrently with the adoption of a Mitigated Negative Declaration through Resolution #2012 -138 N.C.S. adopted by the City Council on September 10, 2012; and WHEREAS, water and sewer line improvements are included in the project with a value of $84,000 each; and WHEREAS, the estimated project cost exceeds the approved project budget; and WHEREAS, the approved funds are available are in the 2016/1017 budget and in the reserves of the Water and Wastewater Capital Funds for the value of the water and sewer line improvements included in the project. NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Petaluma hereby: 1. In accordance with the City of Petaluma Charter and Municipal Code, California Public Contract Code Section 20162 and other applicable law, waives any and all non- 5 conformance in the bid of Contractor for the Denman Reach Phase 3 Improvements Project, Project Number C00500208 and finds the bid of $1,202,807 to be the lowest, responsive bid and further finds that Team Ghilotti, Inc. is the lowest responsible bidder. 2. Awards the contract for the Denman Reach Phase 3 Improvements Project, Project Number C00500208 to Team Ghilotti, Inc. in the amount of $1,234,007, the amount of the lowest responsive base bid and bid alternate A, conditioned on Team Ghilotti, Inc. timely executing the project contract and submitting all required documents, including but not limited to, executed bonds, certificates of insurance, and endorsements, in accordance with the project bid documents. 3. Directs staff to issue a notice of award to Team Ghilotti, Inc. 4. Authorizes and directs the City Manager to execute the project contract on behalf of the City of Petaluma upon timely submission by Team Ghilotti, Inc. of the signed project contract and all other required documents, including but not limited to, executed bonds, certificates of insurance, and endorsements, in accordance with the project bid documents. 5. Approves the revised project budget of $3,108,000. 6. Directs the City Manager to include the proposed project budget augmentation in the City's first quarter budget adjustments in the amount of $168,000, one -half being funded by each of the Water and Wastewater Capital Funds. rel Attachment 2 DENMAN REACH PHASE 3 PROJECT PROJECT NO. C00500208 LOCATION MAP B� �O �oRTy Date :JULY 18, 2016 N L City of Petaluma � U, PROJECT SITE E Public Works and Utilities S Department r85, 7