HomeMy WebLinkAboutStaff Report 3.A 07/18/2016DATE: July 18, 2016
Agenda Item #3.A
TO: Honorable Mayor and Members of the City Council through City Manager
FROM: Dan 09&rASjCE — Director, Public Works & Utilities
Larry Zimmer, P.E. — Deputy Director, Public Works & Utilities
SUBJECT: Resolution Accepting Completion of the Construction Contract for Water Service
Replacement 2015 -2016 Project, C67501406
RECOMMENDATION
It is recommended that the City Council adopt the attached Resolution Accepting Completion of
the Construction Contract for Water Service Replacement 2015 -2016 Project, C67501406.
BACKGROUND
The subject project is part of City's continued effort to replace defective water services that
result in frequent pipe breaks and water leaks. Many of the water services installed during the
1970's and early 80's included polybutylene "blue- tube" piping to connect the water main to the
customer's water meter. The plastic resin used to manufacture polybutylene (PB) pipes and
fittings causes the material to become brittle which in turn causes micro - fractures and pipe
failure. The water industry has since moved away from its use and many cities, including
Petaluma, are left with thousands of PB water services. Maintenance crews routinely replace
these old services as they fail.
This project was bid on May 28, 2015 and W.R. Forde Associates, from Richmond, CA was
awarded the bid of $922,000 via Resolution No. 2015 -114 N.C.S., adopted on July 20, 2015, by
the City Council.
The subject project upgraded a total of 316 1 -inch water services and water main service saddles
to current City standards. There are still 4,126 polybutylene service lines remaining to be
upgraded to high- density polyethylene in the.fature. The water service replacements will be
phased over multiple years based on available budget and priorities. The subject project also
included a new 8 -inch PVC water main on west side of Petaluma Boulevard north of the Shasta
and Sycamore intersection that replaced an existing 2 -inch water main and PB water service
lines, and added a fire hydrant as requested by the City's Fire Marshal.
DISCUSSION
The final construction cost for this project is $955,103.54, which includes three change orders
totaling $50,171.54, as follows:
• Change order 1: $31,244.00 to upgrade specified 3/4" angle stops for the domestic
service lines to 1 -inch angle stop for future fire services.
• Change order 2: $18,000 to complete extra work related to abandoning existing blow -
offs, installing new blow -offs and other miscellaneous work which were neither included
in the plans nor anticipated during bid.
• Change order 3: $2,089.11, which includes a credit of $22,850.45 to the City for City .
provided materials to repair existing damaged pipe, remove existing saddle and install
full circle clamps at various locations, install fire stub -outs for future developments on
Petaluma Boulevard, install water service line under unmarked gas main and other
miscellaneous work.
There are no outstanding claims and the project met all requirements for pressure testing,
disinfection and compaction.
FINANCIAL IMPACTS
Council previously approved a total budget of $1,164,000 from the Water Capital Funds.
With the construction contract, final quantities, change orders, construction management and
inspection, the total cost for the project was $1,089,518.59 as shown in the following project cost
breakdown:
Phase
Contract Award
Actual Total
Project Cost
Planning/Environmental
$
-
$
75.23
Design
$
60,000.00
$
10,437.86
Legal Services
$
1,000.00
$
1,000.00
Administration
$
5,000.00
$
5,000.00
Construction Contract
$
922,000.00
$
971,704.82
Construction Management
$
85,000.00
$
91,300.68
CIP Overheads
$
10,000.00
$
10,000.00
Contingency
$
81,000.00
$
-
TOTAL:
$
1,164,000.00
$
1,089,518.59
Funding Sources
Water Capital
$
1,164,000,00T$
1,089,518.59
At project closeout, all remaining funds will be returned to the Water Capital Funds.
Following the acceptance of the project, the City Clerk will file a Notice of Completion with the
Sonoma County Recorder and the Finance Department will release the contract retention account
to the contractor within 60 days.
2
ATTACHMENTS
1. Resolution
2. Location Map
Attachment 1
RESOLUTION ACCEPTING COMPLETION OF THE CONSTRUCTION CONTRACT
FOR THE WATER SERVICE REPLACEMENT 2015 -2016 PROJECT, C67501406
WHEREAS, in accordance with Section 68 of Article X of the City of Petaluma Charter
and Municipal Code, California Public Contract Code Section 20162 and other applicable law,
City staff prepared construction bid documents and solicited bids for the Project; and
WHEREAS, the project was bid on May 28, 2015, and three (3) bids were received and
opened on June 17, 2015 in accordance with applicable law; and
WHEREAS, the lowest responsible bid for the Project was submitted by W.R. Forde
Associates, from Richmond, CA for $922,000; and
WHEREAS, by Resolution No. 2015 -114 N.C.S., adopted on July 20, 2015, the City
Council found the bid of $922,000 for the project to be the lowest responsive bid, awarded the
Project to W.R. Forde Associates, in the amount of $922,000, conditioned on W.R. Forde
Associates timely executing the project contract and submitting all required documents and
authorized and directed the City Manager to sign the project contract on behalf of the City; and
WHEREAS, the following contract change orders (CCO) affecting the Project amount
have been approved:
Order Number Description Amount
CC0#1 Upgrade angle stop from %" to 1" $31,244.00
CCO #2 Remove and replace damaged blow -offs $16,838.43
CCO #3 Add fire stub -outs and credits to City $2,089.11
Total Change Orders $50,171.54
; and
WHEREAS, the final contract amount, as amended, including all change orders,
overruns, and underruns is $955,103.54 and is within the approved project budget; and
WHEREAS, City staff have inspected the project and determined that it has been
completed in accordance with the contract requirements, and the Contractor's continuing
warranty and other obligations pursuant to the contract; and
WHEREAS, based on the foregoing, staff recommends acceptance of the project on
behalf of the City.
M
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Petaluma
as follows:
The contract titled Water Service Replacement 2015 -2016 Project, project no.
067501406, with the final contract amount of $955,103.54, is accepted as complete,
subject to the Contractor's continuing warranty and other obligations pursuant to the
contract.
2. The City Clerk is hereby authorized and directed to file a Notice of Completion
concerning the project with the Sonoma County Clerk's Office within 10 days of the
date of this Resolution.
3. Staff are hereby authorized and directed to release all undisputed retention not subject
to pending change orders within 60 days of the date of this Resolution and in
accordance with the terms of the project contract, California Public Contract Code
Section 7107 and applicable law.
4
WATER SERVICE REPLACEMENT 2015 -2016
PROJECT NO. C67501406
��
LOCATION MAP
` c/T
00 \ \<
�T
\o
Y,
<V.
it
Attachment 2
A'A, RYLYN C
9
1.