HomeMy WebLinkAboutStaff Report 3.A 12/19/2016DATE: December 19, 2016 Agenda Item #3.A TO: Honorable Mayor and Members of the City Council through City Manager FROM: Dan St. John, F.ASCE — Director, Public Works and Utilities Larry Zimmer, P.E. — Deputy Director, Public Works and Utilities t , SUBJECT: Resolution Accepting Completion of the Recycled Water Main Extension — Oakmead Business Park Phase 1 Project. RECOMMENDATION It is recommended that the City Council adopt the attached Resolution Accepting Completion of the Recycled Water Main Extension — Oakmead Business Park Phase 1 Project. BACKGROUND The City of Petaluma delivers tertiary treated recycled water produced by the Ellis Creel', Water Recycling Facility ( ECWRF) to urban users within the City limits to irrigate parks, open spaces, golf courses, and schools and outside the City limits to agricultural customers. The opening of the ECWRF in 2009 allowed the City to produce tertiary recycled water, which is suitable for non - potable uses such as irrigation. In November 2015, the Urban and Agricultural Recycled Water Master Plan was presented to Council, which identified specific project alignments and phasing to expand the City's recycled water system, including the Oakmead Business Park Phase 1 project. In June of 2015, City staff met with a representative from Kaiser Permanente (Kaiser) to discuss construction of a pipeline to deliver recycled water to their campus. Since Kaiser would use approximately sixty -five percent of the amount of recycled water delivered through the pipeline, Kaiser agreed to pay for sixty -five percent of the construction cost of the pipeline. The City agreed to bear the remaining construction costs and the cost of design and construction management for the project. The approved reimbursement agreement specifies that Kaiser will reimburse the City for construction cost of the recycled water pipeline, with a not to exceed amount of $400,000. Bids for the subject project were opened on June 8, 2016. On July 11, 2016, the City Council awarded the construction contract to Team Ghilotti Inc. of Petaluma, CA in the amount of $523,553.50. Construction of the recycled water main was completed in October 2016. DISCUSSION The final construction contract cost is $543,516.15, which includes the initial low bid of $523,553.50, three change orders totaling $17,282.55, and bid item adjustments totaling $2,680.10. The change orders were related to unforeseen utility conflicts, additional construction items requested by the Operations Division, and a cross - connection investigation necessary to make the final tie -in to Kaiser's irrigation system. The bid item adjustments were caused by additional pipeline extensions required to connect to the existing recycled water main facilities. There are no outstanding claims or issues, and the contractor performed satisfactorily on the proj ect. FINANCIAL IMPACTS The approved FY 16/17 CIP budget and actual expenditures for the Recycled Water System Extension — Oakmead Business Park Phase 1 Project (C66501633) is summarized in the following table: Project Costs Approved CIP Budget Actual Costs Construction Contract $ 523,553.50 $ 543,516.15 Planning/Environmental $ 10,000.00 $ 10,000.00 Design $ 45,000.00 $ 30,000.00 Administration $ 5,000.00 $ 2000.00 Construction Management $ 70,000.00 $ 50,000.00 CIP Overheads $ 10,000.00 $ 5,000.00 Contingency $ 56,446.50 $ 0.00 TOTAL $ 720,000.00 $ 640,516.15 The project is funded through the wastewater capital fund and a private cost -share funding agreement with Kaiser Permanente, for sixty -five percent of the construction costs. The funding sources are as follows: Funding Sources Approved CIP Budget Actual Funding Wastewater Capital Fund $ 343,000 $ 287,230.65 Kaiser Permanente $ 377,000 $ 353,285.50 Total $ 720,000 $ 640,516.15 At project closeout, Kaiser will be billed for their contractual share, and all remaining funds will be returned to the Wastewater Capital fund to be used on other future projects. Following the acceptance of the project, the City Clerk will file a Notice of Completion with the Sonoma County Recorder and the Finance Department will release the contract retention account to the contractor within 60 days. 2 ATTACHMENTS 1. Resolution 2. Location Map Attachment 1 RESOLUTION ACCEPTING COMPLETION OF THE RECYCLED WATER MAIN EXTENTION — OAKMEAD BUSINESS PARK — PHASE 1 PROJECT WHEREAS, in accordance with Section 68 of Article X of the City of Petaluma Charter, Section 20162 of the California Public Contract Code and other applicable laws, the City of Petaluma solicited bids for the Recycled Water Main Extension — Oakmead Business Park Phase 1 Project ( "Project "); and WHEREAS, bids for the Project were opened on June 8, 2016 in accordance with California Public Contract Code Section 4104.5 and other applicable laws at which time the City received 5 (five) bids; and WHEREAS, by Resolution No. 2016 -109 N.C.S. adopted July 11, 2016, the City Council of the City of Petaluma found the bid of $523,553.50 for the Project to be the lowest responsive bid; awarded to Team Ghilotti Inc. in the amount of $523,553.50 conditioned on Team Ghilotti's timely executing the Project contract and submitting all required documents; and authorized and directed the City Manager to sign the Project contract on behalf of the City upon such timely submission and to execute on behalf of the City any amendments to the Project contract that were necessary to effectively complete the project and /or to realize the Project and/or cost benefits for the City; and WHEREAS, the following change orders (CO) affecting the Project amount have been approved: CO No. 1: Work around Buried Debris and SD /WS conflicts $ 8,343.27 CO No. 2: Install two additional Circle Clamps $ 1,102.09 CO No. 3: Cross Connection Investigation $ 7,837.19 Total Change Orders: $ 17,282.55; and WHEREAS, the final contract amount as amended, including final quantities, is $543,576.15; and WHEREAS, City staff has inspected the Project and determined that it has been completed in accordance with the contract requirements subject to the Contractor's continuing warranty and other obligations pursuant to the contract; and WHEREAS, based on the foregoing, staff recommends acceptance of the Project on behalf of the City. NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Petaluma as follows: 1. The contract entitled Recycled Water Main Extension — Oakmead Business Park Phase 1, City Project Number C66501633 with a final contract amount of rd $543,576.15, is accepted as complete subject to the Contractor's continuing warranty and other obligations pursuant to the contract. 2. City Clerk is hereby authorized and directed to file a Notice of Completion concerning the Project with the Sonoma County Clerk's Office within ten (10) days of the date of this Resolution. 3. Staff is hereby authorized and directed to release all undisputed retention not subject to pending change orders within sixty (60) days of the date of this Resolution and in accordance with the terms of the Project contract, the Petaluma City Charter, California Public Contract Code Section 7107 and applicable law. 5 Attachment 2 RECYCLED WATER MAIN EXTENSION - OAKMEAD BUSINESS PARK PHASE 1 LOCATION MAP �v I� PROJECT SITE o s JL Date :DECEMBER 19, 2016 N City of Petaluma PROJECT SITE W E Public Works and Utilities S Department s% f t� Lam' %3