HomeMy WebLinkAboutPCDC Resolution 2005-04 03/21/2005RES®LUTI®IV 2005-0
PETi4LUi1~Q- C011AMUNITY ®EVEL®PNIEIVT C®M~AISSI®N
ACCEPTING COMPLETION OF THE
MAGGIORA & GHILOTTI, INC. CONSTRUCTION
PETALUMA RIVER TRIAL ENHANCEMENT, AREA 3
PROJECT NO. C200503
WHEREAS, the Petaluma Community Development Commission (PCDC) awarded the
contract for the River Trial Enhancement, Area 3 Project, to Maggiora 8~ Ghilotti, Inc. on July 12,
2004; and,
WHEREAS, Maggiora &Ghilotti, Inc. has completed all the work at a total value of
$772,133 to the satisfaction of the Director of Economic Development and Redevelopment and
the Redevelopment inspection team.
NOW, THEREFORE, BE IT RESOLVED by the Petaluma Community Development Commission
that the City Clerk/Recording Secretary is hereby authorized to sign the Notice of Completion.
BE IT FURTHER RESOLVED that the Finance Department is hereby authorized to release the
ten (10%) to Maggiora 8~ Ghilotti, Inc. within forty five (45) days after the recordation of the
Notice of Completion provided that all stop notices have been released.
Adopted this 21 S' Day of March 2005 by the following vote:
Comrnissiaher Aye No Absent
Canevaro X
Chair Glass X
Vice Chair Harris X
Healy X
Nau X
O'Brien X
Torliatt X
David Glass, Chair
ATTEST:
Claire Cooper, Recording S cretary
APPROVED A_ S TO FORM:
~~ =~~
Richard R. Rudn~'ansky, en ral Counsel