Loading...
HomeMy WebLinkAboutStaff Report 3.B 03/20/2017Agenda Item #3.B ,b DATE: March 20, 2017 TO: Honorable Mayor and Members of the City Council through City Manager FROM: Da �S . i ASCE — Director, Public Works and Utilities Larry i P.E. — Deputy Director, Public Works and Utilities SUBJECT: Resolution Accepting Completion of the Denman Reach Phase 3 Improvements Project, City Project No. C00500208 RECOMMENDATION It is recommended that the City Council approve a Resolution Accepting Completion of the Denman Reach Phase 3 Improvements Project, City Project No. C00500208. BACKGROUND Placing flood terracing within the Petaluma Watershed, in concert with the development of a river and creek trail system, was envisioned in the 1996 River Access and Enhancement Plan and was adopted as a policy in the General Plan 2025 in 2008. Flood plain modeling concluded that the completed project would lower the flood elevation for a one - hundred year storm by up to 1 foot in some areas. Phases 1 and 2 were completed in 2005, and Phase 3 completes the project through the Denman Reach of the Petaluma River between the Corona Road Bridge and Twin Bridges on Petaluma Boulevard North. In the fall of 2008, the City submitted a two -part grant application to the State of California for land acquisition and continuation of the flood terrace, riparian habitat enhancement, and trail improvements within the Denman Reach. The first grant application was to the California Natural Resources Agency's (NRA) River Parkways Program for land acquisition in the amount of $1,150,000, which was initially partially funded at $850,000 but later augmented with an additional $165,262 bringing the land acquisition grant to $1,015,262. The second application was to the Department of Water Resources' (DWR) Urban Streams Restoration Program for $993,375, which was fully funded for design and construction. In addition to the state funding grants, the Sonoma County Water Agency (SCWA) Zone 2A committed matching funds of approximately $512,500 as authorized by City Council Resolution No. 2015 -007 N.C.S. There were five properties affected by the construction of Denman Reach Phase 3, three of which are the undeveloped parcels located on the west side of Industrial Avenue directly across from the intersection of Benson Way and Industrial Avenue. Through acquisition of two parcels in fee simple and the other three parcels by temporary construction and permanent trail easements, the project completed the flood plain terracing and added approximately 2,100 feet of trail between Corona Road and the intersection of Industrial Avenue and Petaluma Boulevard North. Bids were opened on June 22, 2016. On July 18, 2016, the City Council authorized the award of the construction contract for phase 3 to Team Ghilotti, Inc. of Petaluma in the amount of $1,234,007. Construction began in August 2016 and was completed in February 2017. DISCUSSION The project was managed and inspected by Public Works and Utilities engineering staff with assistance from the designer, Questa Engineering, and resulted in a final construction contract amount of $1,218,842, including six change orders and overruns and underruns in estimated bid item quantities. In all, the total cost of the change order work and bid item adjustments decreased the contract amount by $15,165.01. The first change order provided for the temporary fencing at the stock pile site, which increased the contract amount by $1,849.30. The second change order increased the contract amount by $2,833.31 to provide for labor to haul off concrete unexpectedly found at the project site to an alternate dumpsite and riprap at an outfall structure. The third change order eliminated two bid items of water and sewer main relocations that were determined to be unnecessary for a decrease in the contract amount of $100,440.92. The fourth change order allowed the removal of the original designed quarry fine pathway along with an underlayment of filter fabric. After lime treatment of the pathway area, a new and more robust pathway was re- installed. This change was necessary because the original design of the pathway was deemed inadequate after failing during the first rain event, which caused the pathway base to soften. This change order increased the contract amount by $78,612.07. The fifth change order provided for the extra labor and equipment to remove and replace a damaged storm drainpipe and provide protection around the pipe, which increased the contract by $6,188.66. The sixth and last change order added riprap in a swale to direct the flow near the new pedestrian bridge, and protect around the corners of the bridge abutments to prevent future scouring, which increased the contract by $2,826.93. The contractor performed satisfactorily and there are no outstanding claims, however in the time since the contractor completed the contract work, the project site has experienced a great amount of flooding. This flooding has caused a portion of the new pathway to be washed away and is currently in an unusable state due to an apparent flaw in the pathway design. Because the damage is not due to poor workmanship, it is not necessary to hold the Contractor responsible, and withhold their retention. The City is working with the designer on an appropriate resolution. The City will be advertising a small project under the same CIP within the existing budget to complete the pathway to a satisfactory and usable condition, including rehabilitation of roughly 800 linear feet of newly installed pathway, and of existing pathway from previous Denman Project phases that has been damaged due to the inundation. The Conservation Corps North Bay will be working under a separate contract to perform the site revegetation later this spring, which involves planting roughly 100 plants and 200 trees at the 2 project site. Similarly, the design and construction of the informational kiosks is in process and will be completed later this fall under a separate contract. The proposed action meets Council Goals: "Plan for and implement priority capital projects as funding permits." FINANCIAL IMPACTS On July 18, 2016, City Council approved a new project budget of $3,108,000, which included past land acquisitions and right of way work. Project funding is comprised primarily of Department of Water Resources Grant with Sonoma County Water Agency Zone 2A, Sonoma County Agricultural Preservation and Open Space District, and City storm drainage impact fees for local grant match as summarized in the table that follows. -uses ' CIP Budget =, FYI 6117 Approved Bud et Actual Project Costs Design $ 186,000 $ 236,681 $ 271,150 Legal $ 4,000 $ 4,000 $ 1,520 Land Acquisition $ 1,045,000 $ 1,045,000 $ 1,045,000 Construction Contracts $ 1,373,000 $ 1,234,007 $ 1,218,842 Landscaping/Kiosks $ 136,000 $ 136,000 Regulatory Permits $ 37,312 $ 37,312 Construction Management $ 150,000 $ 130,000 $ 98,400 CIP Overhead $ 44,000 $ 44,000 $ 44,000 Administration $ 1,000 $ 1,000 $ 1,385 Project Contingency $ 137,000 $ 240,000 $ - Pathway Rehabilitation Work $ - $ - $ 254,391 TOTAL $ 2,940,000 $ 3,108,000 $ 3,108,000 Funding Sources Waste Water Capital $ 84,000 $ 84,000 Water Capital $ 84,000 $ 84,000 Storm Impact Fees $ 370,000 $ 370,000 $ 370,000 State Grants $ 1,015,000 $ 1,015,000 $ 1,015,000 SCWA Zone 2A Assessments $ 512,000 $ 512,000 $ 512,000 Dept of Water Resources Grant $ 993,000 $ 993,000 $ 993,000 Sonoma Open Space Grant $ 50,000 $ 50,000 $ 50,000 TOTAL $ 2,940,000 1 $ 3,108,000 $ 3,108,000 Note: City staff salary and benefits costs are included in appropriate project phases for the project. The grant funds will be fully expended upon the acceptance of the project. The remaining project budget of $254,391 will be used to complete the rehabilitation of the damaged pathway, and the $136,000 will be used for the landscaping and kiosk installation. 3 ATTACHMENTS 1. Resolution 2. Location Map Attachment 1 RESOLUTION ACCEPTING COMPLETION OF THE DENMAN REACH PHASE 3 IMPROVEMENTS PROJECT, CITY PROJECT NO. C00500208 WHEREAS, City staff prepared construction bid documents and advertised for construction of the Denman Reach Phase 3 Improvements Project, Project Number C00500208, ( "the Project "); and WHEREAS, in accordance with the City of Petaluma Charter and Municipal Code, California Public Contract Code Section 20162 and other applicable law, City staff solicited bids for the Project; and WHEREAS, the Project was bid on May 26, 2016, and three bids were received and opened on June 22, 2016 in accordance with applicable law; and WHEREAS, the lowest responsible bid for the base bid and bid alternative A was submitted by Team Ghilotti, Inc. from Petaluma, CA for $1,234,007; and WHEREAS, by Resolution No. 2016 -116, adopted on July 18, 2016, the City Council found the bid of $1,234,007 for the Project to be the lowest responsive bid, awarded the Project to Team Ghilotti, Inc., in the amount of $1,234,007, conditioned on Team Ghilotti, Inc. timely executing the Project contract and submitting all required documents and authorized and directed the City Manager to sign the Project contract on behalf of the City; and WHEREAS, the following contract change orders (CCO) affecting the project amount have been approved: Change Order Number Description Amount CCO #1 Additional subcontractor costs to provide $1,849.30 temporary fencing at the project dumpsite at the Petaluma Community Sports Fields CCO #2 Additional labor to remove excess concrete $2,833.31 found at project site to alternate dump site and provide rip rap at an outfall structure CCO #3 Elimination of bid items to relocate the water ($100,440.92) and sewer main, as well as, the associated labor to provide rip rap protection around the existing structures. CCO #4 Removal of the previously installed filter $78,612.07 fabric and pathway, lime treatment of the subgrade, and install and compact 4" of quarry fine pathway 5 CCO #5 Additional labor and material costs to install $6,188.66 85 linear feet of storm drain pipe and additional rip rap protection of the pipe CCO #6 Additional labor and equipment costs to install rip rap protection at each coiner of the pedestrian bridge abutments and nearby swale Total Change Orders ; and $2,826.93 ($8,130.65) WHEREAS, the final contract amount, as amended, including all change orders, overruns, and underruns is $1,218,841.99 and is within the approved project budget; and WHEREAS, City staff have inspected the project and determined that it has been completed in accordance with the contract requirements, and the Contractor's continuing warranty and other obligations pursuant to the contract; and WHEREAS, based on the foregoing, staff recommends acceptance of the project on behalf of the City. NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Petaluma hereby: 1. The contract titled Denman Reach Phase 3 Improvement Project, with the final contract amount of $1,218,841.99 is accepted as complete, subject to the Contractor's continuing warranty and other obligations pursuant to the contract. 2. Staff is hereby directed to solicit bids for the rehabilitation of the damaged pathway. 3. The City Clerk is hereby authorized and directed to file a Notice of Completion concerning the project with the Sonoma County Clerk's Office within 10 days of the date of this Resolution. 4. Staff is hereby authorized and directed to release all undisputed retention not subject to pending change orders within 60 days of the date of this Resolution and in accordance with the terns of the Project contract, California Public Contract Code Section 7107 and applicable law. on DENMAN REACH PHASE 3 IMPROVEMENTS PROJECT PROJECT NO. C00500208 LOCATION MAP rA i i i ZZ �S1 IZZ Attachment 2 7