Loading...
HomeMy WebLinkAboutResolution 2017-118 N.C.S. 08/07/2017Resolution No. 2017-118 N.C.S. of the City of Petaluma, California ACCEPTING COMPLETION OF PETALUMA BOULEVARD NORTH WATER MAIN REPLACEMENT PROJECT — LAKEVILLE STREET TO B STREET, CITY PROJECT NO. 067501304 WHEREAS, in accordance with Section 68 of Article X of the City of Petaluma Charter and Municipal Code, California Public Contract Code Section 20162 and other applicable law, City staff prepared construction bid documents and solicited bids for the project (Project); and WHEREAS, the Project was bid on March 10, 2016, and two bids were received and opened on April 6, 2016 in accordance with applicable law; and WHEREAS, the lowest responsible bid for the Project was submitted by Team Ghilotti, Inc. from Petaluma, CA for $2,895,824; and WHEREAS, by Resolution No. 2016-063 N.C.S., adopted on May 2, 2016, the City Council found the bid of $2,895,824 for the Project to be the lowest responsive bid; awarded the Project to Team Ghilotti, Inc. in the amount of $2,895,824 conditioned on Team Ghilotti, Inc.'s timely execution of the Project contract and submittal of all required documents, and authorized and directed the City Manager to sign the Project contract on behalf of the City; and WHEREAS, the following contract change orders (CCO) affecting the project amount have been approved: Change Order Number Description Amount Potholing Added bid item quantity $ 58,500.00 CC0#1 AC plug and 2" grind and overlay $140,874.00 CCO#2 Misc. T&M $ 16,503.01 CCO#3 Misc. T&M $ 11,439.26 CCO#4 Misc. T&M $ 19,707.27 CCO#5 Misc. T&M $ 10,808.88 CCO#6 Misc. T&M $ 6,458.02 CCO#7 Misc. T&M Total Change Orders $ 37,613.02 $301,923.46 ; and WHEREAS, the final contract amount, as amended, including all change orders, overruns, and underruns is $3,030,718.46 and is within the approved project budget; and WHEREAS, City staff have inspected the project and determined that it has been completed in accordance with the contract requirements, and the Contractor's continuing warranty and other obligations pursuant to the contract; and Resolution No. 2017-118 N.C.S. Page 1 WHEREAS, based on the foregoing, staff recommends acceptance of the project on behalf of the City. NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Petaluma as follows: The contract titled Petaluma Boulevard North Water Main Replacement Project - Lakeville to B Street, with the final contract amount of $3,030,718.46, is accepted as complete, subject to the Contractor's continuing warranty and other obligations pursuant to the contract. 2. The City Clerk is hereby authorized and directed to file a Notice of Completion concerning the project with the Sonoma County Clerk's Office within 10 days of the date of this Resolution. The Public Works and Utilities Director is hereby authorized and directed to release all undisputed retention not subject to pending change orders within 60 days of the date of this Resolution and in accordance with the terms of the Project contract, California Public Contract Code Section 7107 and applicable law. Under the power and authority conferred upon this Council by the Charter of said City, REFERENCE: I hereby certify the foregoing Resolution was introduced and adopted by the Approved a tc Council of the City of Petaluma at a Regular meeting on the 7`h day of August, form: 2017, by the following vote: City Attorney AYES: Albertson, Vice Mayor Barrett, Mayor Glass, Healy, Kearney, King, Miller NOES: None ABSENT: None ABSTAIN ATTEST Resolution No. 2017-118 N.C.S. Page 2