Loading...
HomeMy WebLinkAboutStaff Report 3.C 01/26/20093.0 January 26, 2009 CITY OF PETALUMA, CALIFORNIA AGENDA BILL Agenda Title: Resolution Authorizing Award of Contract for the Airport Meeting Date: January 26, 2009 Underground Storage Tank Removal Project No. C00100208 and Approving a New Project Budget Meeting Time: ❑ 3:00 PM ® 7:00 PM Category: ❑ Presentation ® Consent Calendar ❑ Public Hearing ❑ Unfinished Business ❑ New Business Department: Public Works Cost of Proposal: Director: Vi Le Contact Person Larry Zimmer Estimated Total Project Budget $173,984 Phone Number: 776-3674 Name of Fund: Airport Fund 6100: $175,000 Amount Budgeted: Total Project Budget $197,000 Account Number: (08-09 originally approved CIP) C00100208-30600-54151 Proposed New Project Budget $175,000 Recommendation: It is recommended that the City Council take the following action: Adopt the resolution authorizing award of contract and approving a new project budget Summary Statement: The Airport Underground Storage Tank Removal Project, as approved in the FY 08/09 CIP Budget, generally includes removal and disposal of three, 12,000 -gallon underground storage fuel tanks, testing for soil contamination, site work excavation, associated electrical and utility work, and restoration of concrete and asphalt surfaces at the Petaluma Municipal Airport. Removal of the three tanks is mandatory per State regulations. Attachments to Agenda Packet Item: Resolution authorizing award of contract. Location map Revi wed by Admin. Svcs. Dir: Reviewed by City Attornev: Approved_bv—City Manager: CAat ./jJ j Date: Date: j 7 Rev. # Date 1,4 vued: File: S:\CIP Division\Projects\Airport UST Removal C10020Kl)esign\330 PCDC-City Council\2009.01.26 Award of Airport UST Itemoval.doe CITY OF PETALUMA9 CALIFORNIA JANUARY 26, 2009 SII C ' t t 1 FOR RESOLUTION AUTHORIZING AWARD OF CONTRACT FOR THE AIRPORT UNDERGROUND STORAGE TANK REMOVAL PROJECT NO. C001 00208 AND APPROVING A NEW PROJECT BUDGET RECOMMENDATION: Adopt the resolution authorizing award of contract and approving a new project budget. 2. BACKGROUND: A Public Works consultant prepared the plans and specifications for the Airport Underground Storage Tank Removal Project. The Notice Inviting Bids was issued on November 25, 2008, and bids were received and opened on December 18, 2008 as follows: NAME OF BIDDER BID AMOUNT Bay Pacific Pipeline, Inc. of Novato $83,000 Wildcat Underground of Petaluma $98,600 Zaccor Companies, Inc. of Alameda $139,035 Northwest General Engineering of Santa Rosa $140,286 Musco Excavators, Inc. of Santa Rosa $148,250 American Construction and Environmental of Brentwood $148,833 C. Hardy General Engineering of Petaluma $173,900 North Bay Construction, Inc. of Petaluma $174,735 W.R. Forde Associates of Richmond $195,000 The engineer's estimate for the construction is $100,000. With a bid of $83,000, the apparent low bidder is Bay Pacific Pipeline, Inc. of Novato, California. This contractor has satisfactorily performed similar projects for other cities in Northern California. Staff verified that Bay Pacific Pipeline, Inc. possesses a valid Class A California contractor's license No. 524020, as well as a Hazardous Substance Removal Certificate, which qualifies them to perform the work. 3. DISCUSSION: In accepting the Airport Fuel Tank Upgrade, Project on February 25, 2008, Council was informed that, to comply with the California Fire Code and California Code of Regulations Title 23, the three decommissioned underground storage fuel tanks would have to be removed within a year of being taken out of operation. The City had been given notice on November, 27, 2007 by the Fire Marshal that removal of the UST's would be required by October 9, S:\CIP Division\Projecls\Airport UST Removal C170208\Desipn\330 PCDC-C43 CounciP2009.01,26 ;beard of Airport UST Removal.doc 2 2008. However, to allow the City to complete design plans and specifications, the City Fire Marshall agreed to extend this deadline until June 2009. The specific code requiring closure and removal within 12 months of abandonment (with a possible 12 month extension) is CCR Title 23 Water, Division 3 State Water Resources Control Board and Regional Water Quality Control Boards, Chapter 16 Underground Tank Regulations, Article 7. Underground Storage Tank Closure Requirements. At this time, staff recommends authorizing City Manager to enter into contract with the low bidder, Bay Pacific Pipeline, Inc., to allow removal of the underground storage tanks. If not awarded at this time, the City will not meet State requirements and could potentially face fines. 4. FINANCIAL IMPACTS: The following is a breakdown of the estimated total project costs: Uses (Design 1Legal Counsel 1 Planning/Environmental 1Construction Contracts 1Construction Management 1CIP Overhead 1Proiect Contingency 1Estimated Total Project Cost (Funding Sources 1General Fund Loan IAirport Fund 1 TOTAL Approved CIP Proposed Projected CIE Budget 08/09 Budget Costs J $ 18,000 $ 23,795 $ 23,7951 $ 5,000 $ - $ -1 $ 22,000 $ 21,554 $ 21.5541 $ 100,000 $ 83,000 $ 83,0001 $ 27,000 $ 16,600 $ 16,6001 $ 10,000 $ 8,333 $ 8,2851 $ 15,000 $ 21,718 $ 20,7501 $ 197,000 $ 175,000 $ 173,9841 $ 97,000 $ $ 1 1 $ 100,000 $ 175,000 $ 175,000 $ 197,000 $ 175,000 $ 175,0001 The estimated total project cost, including planning, design, construction, administration, inspection, testing, and contingency is $173,984. IIowever, there is a possibility that additional excavation will be needed if soil contamination is found during the tank removal process. $197,000 was approved in the 08-09 Budget. SP.CIP Dig-ision\Projceis'Ulirport UST Removal 01002080csign1330 PCDC-City Cbuncil\2009.01.26 Award of Airport UST Removtd.doc 3 ATTACHMENT1 RESOLUTION AUTHORIZING AWARD OF CONTRACT FOR THE AIRPORT UNDERGROUND STORAGE TANK REMOVAL PROJECT NO. 000100208 TO BAY PACIFIC PIPELINE, INC. AND APPROVING A NEW PROJECT BUDGET WHEREAS, through a design consultant, City staff has prepared construction bid documents and advertised for construction of this Project; and WHEREAS, in accordance with the City of Petaluma Charter and Municipal Code, California Public Contract Code Section 20162 and other applicable law, City staff solicited bids for the Project; and WHEREAS, the project was bid on December 18, 2008, and nine (9) bids were received and opened in accordance with applicable law; and WHEREAS, the lowest bid for the Project was from Bay Pacific Pipeline, Inc. for $83,000; and WHEREAS, the CIP budget, which included a total budget for Project No. C00100208 of $197,000, was approved; and WHEREAS, staff has determined that Bay Pacific Pipeline, Inc.'s bid satisfies the bidding requirements for the Project; and WHEREAS, staff has verified that Bay Pacific Pipeline, Inc. possesses a valid California Contractor's License, Class A, number 524020, that qualifies Bay Pacific Pipeline, Inc. to perform the Project; and WHEREAS, the Project has a Categorical Exemption pursuant to the California Environmental Quality Act ("CEQA") pursuant to Article 19, Section 15301 and/or 15330 of Title 14 of the California Code of Regulations ("CEQA Guidelines"); and NOW, THEREFORE, BE IT RESOLVED that the Petaluma City Council hereby: 1. Approves the project budget in the amount of $175,000. 2. In accordance with the City of Petaluma Charter and Municipal Code, California Public Contract Code Section 20162 and other applicable law, waives any and all non-conformance in the bid of Bay Pacific Pipeline, Inc. for the Airport Underground Storage Tank Removal Project, finds the bid of $83,000 to be the lowest responsive bid and further finds that Bay Pacific Pipeline, Inc. is the lowest responsible bidder. 3. Directs staff to issue a notice of award to Bay Pacific Pipeline, Inc. 4. Authorizes and directs the City Manager to execute the project contract on behalf of the City of Petaluma upon timely submission by Bay Pacific Pipeline, Inc. of the signed project contract and all other required documents, including but not limited to, executed bonds, certificates of insurance, and endorsements, in accordance with the project bid documents. C:\Documents and Settings\kcrumptLecal Settings\Temporary lntcrnet Files\Conlent.Outlook\4V5P44E4\2009 01 26 A\Card of Airport OST Removal.doc 4 N I - Z W O 6F`f'ryi$ a mE 3 O €E@,€CBPP ,= V ` O F N L n O E 0! C p eE°t F Q 0 h o m s €iSoiPPa m cn N y U ePieai:s� kPF9ti$t: I �r E Ln 0 v LD m a v v 3 a 0