HomeMy WebLinkAboutStaff Report 3.D 01/26/2009CITY OF PETALUMA, CALIFORNIA
AGENDA BILL
Agenda Title: Resolution Approving the Project Budget
and Authorizing Award of Contract for the
Fox Hollow Park Project No. C00400305.
&D
January 26, 2009
Meeting Date: Jan. 26, 2009
Meeting Time: ❑ 3:00 PM
® 7:00 PM
Category: ❑ Presentation ® Consent Calendar ❑ Public Hearing ❑ Unfinished Business ❑ New Business
Department:
Public Works
Cost of Proposal:
Director:
Vinde Marengo
L'4
Contact Person:
Scott Brodhun
Larry Zimmer
Amount Budgeted: Total Project Budget: $301,000
Phone Number:
776-3674
Name of Fund:
Account Number:
C00400305-30600-54151
Recommendation: It is recommended that the City Council take the following action:
Adopt the resolution authorizing award of contract.
Summary Statement:
The Fox Hollow Park Project, as approved in the FY 08/09 CIP Budget, generally includes new concrete
pavement, concrete turf header, concrete curb and gutter, metal edge, removable bollards, picnic tables, benches,
trash receptacles, solar lights, planting and automatic irrigation, associated grading and drainage, earthwork,
water, electrical and utilities work, and other work specified in these special provisions and as shown on the plans
for Fox Hollow Park, dated October, 2008. Staff is recommending the project also include alternates 1 and 2 to
create the areas for play structures, which entail earthwork, storm drainage, concrete play curb, play area
accessible ramp, and safety surfacing.
Attachments to Agenda Packet Item:
Resolution approving the project budget and authorizing award of contract.
2. Location map
(Reviewed by Admin. Svcs. Dir:
�a� //// (.
Rev. # Date st`okevtsed:
"'VL„
Reviewed by City Attornev:
Date: 0
Approved by Citv Manager:
it \
Date: /� Y
File:
S:\Cu' Division%Projects\Fox Hollow Park C400305t13esignl330
PCDC-City CounciltAWard of Contract\2009.01.26 Award of Fox
Hollow Park (2).doc
CITY OF PETALUMA, CALIFORNIA
JANUARY 26, 2009
AGENDA REPORT
FOR
RESOLUTION APPROVING THE PROJECT BUDGET AND AUTHORIZING
AWARD OF CONTRACT FOR THE Fox HOLLOW PARK PROJECT NO. C00400305
RECOMMENDATION:
Adopt the resolution authorizing award of contract
2. BACKGROUND:
A design contract was awarded for the Fox Hollow Park Project in 2006; however was not
executed. The estimated cost to complete the project ($829,000), as conceptualized, exceeded
funds available ($301,000). In order to fulfill a longstanding commitment and move the
project forward, the concept and design were revised and narrowed in scope, and final design
was initiated in February 2008. A Public Works consultant prepared the plans and
specifications for the Project and the Notice Inviting Bids was issued on November 25, 2008.
On December 18, 2008, a total of ten (10) bids were received, of which nine (9) were
considered responsive. One (1) bid was considered non-responsive; therefore, it was not read
and was rejected due to failure to respond according to specifications. Bids were received and
opened as follows:
I Name of Bidder
Base Bid
Bid Alt 1
Bid Alt 2
Bid Total f
INESSCO Construction, Inc. of Santa Rosa
$163,318.40
$ 13,39020
$ 13,249.60
$189,95820 -
IFedco Construction of Santa Rosa
$193,087.00
$ 12,980.50
$ 13,202.50
$219,270.00
IC. Hardy General Engineering of Petaluma
$191,315.05
$ 16,166.00
$ 16,460.50
$223,941.55 `
IMaxistone dba Maxicrete, Inc. of Fairfield
$205,481.00
$ 10,115.30
$ 10,138.40
$225,734.70 I
Hanford ARC of Sonoma
1 $194,199.73
$ 26,542.68
$ 14,280.03
$235,022.44
(North Bay Construction, Inc. of Petaluma
( $222,777.30
$ 15,093.30
$ 15,337.40
$253,208.00
Kaze Ltd. dba Wildcat Underground and
Engineering of Petaluma
$256,524.95
$ 13,886.40
$ 14,052.20
$284,463.55
(valentine Corporation of San Rafael
$316,982.00
$ 18,723.00
$ 18,970.00
$354,675.00 *
(JA. Gonsalves and Son of Napa
$299,174.00
$ 35,788.00
$ 36,068.00
$371,030.00
(*) Denotes corrected bid total. These bid results
differed from
the December
l8 bid opening
amounts due to
mathematical errors on either bid summation and/or
bid line item
extensions.
The engineer's base bid estimate for construction is $196,000.
NESSCO Construction Inc. was the apparent low bidder with a total bid of $189,958.20,
which includes base bid and bid alternates 1 and 2. NESSCO has satisfactorily performed
similar projects for other cities in Northern California. Staff verified that NESSCO possesses
a valid Class A California contractor's license No. 765763, which qualifies them to perform
the work.
SXlP Dig ision\Projects\Fox Hollow Park C4003050csign\330 PCDC-CiqCouncihAward of ContrncPC009 01 26 Atsiud of Fox
I lollmt P.vlc(2).doc
3. DISCUSSION:
Staff recommends authorizing City Manager to enter into contract with the low bidder,
NESSCO Construction, Inc., to construct Fox Hollow Park and to include both bid alternates.
If not awarded at this time, the City will still be accountable for building the park in the
future.
4. FINANCIAL IMPACTS:
The following is a breakdown of the estimated costs
The estimated total project cost, including design, legal counsel, construction contracts,
overhead and contingency is $278,650. $301,000 was previously allocated to the 4 -acre Fox
Hollow Park from Parkland Acquisition and Development Fees, collected specifically from
subdivisions surrounding Fox Hollow Park. $22,350 was previously spent on tree trimming
and thinning a very old grove of Eucalyptus trees for safety reasons in anticipation of
developing the property as a park site. In addition to the Parkland Acquisition and
Development Fees funding, a Fox Hollow Park neighborhood group was formed, and in
collaboration with Parks and Recreation staff, has been collecting donations in order to
purchase play equipment. To date, this group has raised $13,649, which is likely sufficient for
the installation of one play structure. Funds remaining at the completion of the project will be
utilized toward purchase and installation of additional play equipment.
C:\Documents and Settings\kcrump\Local Settings\"Pemporiry Internet Files\Content.OuLlook\4ViP44E4\2009 Ill 26 Award of Fox
I-tollow Park (2).doc 3
Approved CIP
Projected CIP
Uses
Budget 08/09
Costs
IDesign
$
70,000
$
54,190
1Legal Counsel
$
1,1731
1Plan ninq/Environmental
$
6,000
$
-I
lConstruction Contracts
$
210,000
$
189,9581
1Previous Contract Work (Trees)
$
22,3501
ICIP Overhead
$
15,000
$
14,3331
1 Proiect Continqencv
$
-
$
18,9961
Estimated Total Project Cost
$
301,000
$
301,0001
IFundinq Sources
I
IParkland Acquisition Impact Fees
$
301,000
$
301,0001
(TOTAL
$
301,000
$
301,0001
The estimated total project cost, including design, legal counsel, construction contracts,
overhead and contingency is $278,650. $301,000 was previously allocated to the 4 -acre Fox
Hollow Park from Parkland Acquisition and Development Fees, collected specifically from
subdivisions surrounding Fox Hollow Park. $22,350 was previously spent on tree trimming
and thinning a very old grove of Eucalyptus trees for safety reasons in anticipation of
developing the property as a park site. In addition to the Parkland Acquisition and
Development Fees funding, a Fox Hollow Park neighborhood group was formed, and in
collaboration with Parks and Recreation staff, has been collecting donations in order to
purchase play equipment. To date, this group has raised $13,649, which is likely sufficient for
the installation of one play structure. Funds remaining at the completion of the project will be
utilized toward purchase and installation of additional play equipment.
C:\Documents and Settings\kcrump\Local Settings\"Pemporiry Internet Files\Content.OuLlook\4ViP44E4\2009 Ill 26 Award of Fox
I-tollow Park (2).doc 3
RESOLUTION APPROVING THE PROJECT BUDGET AND AUTHORIZING AWARD OF
CONTRACT FOR FOX HOLLOW PARK PROJECT NO. C00400305
TO NESSCO CONSTRUCTION, INC.
WHEREAS, through a design consultant, City staff has prepared construction bid documents
and advertised for construction of this Project; and
WHEREAS, in accordance with the City of Petaluma Charter and Municipal Code, California
Public Contract Code Section 20162 and other applicable law, City staff solicited bids for the Project;
and
WHEREAS, the project was bid on December 18, 2008, and nine (9) responsive bids were
received and opened in accordance with applicable law; and
WHEREAS, the lowest bid for the Project was from NESSCO Construction, Inc. for
$189,958.20; and
WHEREAS, the CIP budget, which included a total budget for Project No. C00400305 of
$301,000, was approved; and
WHEREAS, staff has determined that NESSCO Construction, Ine.'s bid satisfies the bidding
requirements for the Project; and
WHEREAS, staff has verified that NESSCO Construction, Inc. possesses a valid California
Contractor's License, Class A, number 765763, that qualifies NESSCO Construction, Inc. to perform the
Project; and
WHEREAS, the Project was included in a Mitigated Negative Declaration (Willow Glen
Planned Unit Development) that was adopted by the City on April 7, 1997 pursuant to the California
Environmental Quality Act ("CEQA"); and
NOW, THEREFORE, BE IT RESOLVED that the Petaluma City Council hereby:
I. In accordance with the City of Petaluma Charter and Municipal Code, California Public Contract
Code Section 20162 and other applicable law, waives any and all non-confomiance in the bid of
NESSCO Construction, Inc. for the Fox Hollow Park Project, finds the bid of $189,958.20 to be
the lowest responsive bid and further finds that NESSCO Construction, Inc. is the lowest
responsible bidder.
2. Directs staff to issue a notice of award to NESSCO Construction, Inc.
3. Authorizes and directs the City Manager to execute the project contract on behalf of the City of
Petaluma upon timely submission by NESSCO Construction, Inc. of the signed project contract
and all other required documents, including but not limited to, executed bonds, certificates of
insurance, and endorsements, in accordance with the project bid documents.
SX1P Dieision\Projccls\Fox Hollow Park ('4003115Dcsign\330 PCDGCity Council\Award oCContract\200901 26 Ahad orPox
Hollo\t Pak (2).doc 4
ATTACHMENT 2
�J
W
J
WINDMILL LANE
50NOMA MOUNTAIN PARKWAY
SX1II Div ision\ProjeetsUbs Hollow Pad: 0400305\Design\330 PC'DC-Ciry Council\Award of C'ontravt\2(1119 01 26 Av+ard ot'Pos I lollow Park
5
f'-i.doc