CONSTRUCTION MANAGEMENT
PRESENTATIUN
February 2, 2004
The
Covello
Group
rr
PARTICIPANTS
Owner:
City of Petaluma
Mike Ban
I 1 English Street
Director -
Petaluma, CA 94952
(707) 778-4487
Margaret Orr
Engineering Manager
(707)778-4589
Contractor:
Kiewit Pacific Co.
Clint Cole
5000 Marsh Drive
Project Manager
Concord, CA 94520
(925) 516-4600
Design Engineer:
Carollo Engineers
Tom Patten
2700 Ygnacio Valley Rd, Suite 300
Principal
Walnut Creek. CA 94598
(925) 932-1710
Doug Wing
Design Engineer
(925)299-6733
Environmental
ESA
Jim O'Toole
Management:
8950 Cal Center Drive, Bldg 3, Suite 300
Project Engineer
Sacramento, CA 95826
(707) 795-0900
Jennifer Garrison
Environmental Manager
(916)564-4500
Programmer:
ArcSine engineering
Doug McHaney
970 Executive Way
Project Manager
Redding, CA 96002
(530) 222-7204
Steve Stewart
Lead Programmer
(530)222-7204
Construction
The Covello Group
Bruce Presser
Manager:
1660 Olympic Blvd, Suite 300
Principal
Walnut Creek, CA 94596
(925) 933-2300
Ken Sinclair
Construction Manager
(925)260-2943
Ed O'Brien
Field Engineer-
(925) 382-1246
19
• ' '
* Contractor: KIEWIT PACIFIC CONSTRUCTION
Base Contract Amount (Total Project) .................................... $ 110,329,000.00
Change Orders Executed. . . ........ ...... .... — ........... ............ $ 4,141,218.00
Total Contract Cost ......................................................... $ 114,470,218.00
Contract Amount Earned ................................................... $ 111,610,539.00
Progress Payment for December 2008 (excludes retention)........... $ 693,634.00
Previous Progress Payments (excludes retention) ...................... $ 100,449,485.00
Estimated Percent Complete.. . ....... ......................... ........................ 98 °io
* Design Engineer: Carollo Engineers
Authorized Budget (Total Project) ....................................... $ 4,354,075.00
Billings to Date... . .... ..................................................... $ 4,209,090.00
* Environmental Manager: ESA
Authorized Budget (Total Project).... . ................... ..... --- $ 1,434,830.00
Billings to Date...............................................................$ 1.136,255.00
ArcSine engineering
Authorized Budget (Total Project) ....................................... $ 2.340,951.00
Billings to Date... . .......... ......................................... ...... $ 2,061028.00
* Construction Manager: The COVELLO GROUP, Inc.
Authorized Budget (Total Project).. . . ... ....... ......... ...... ..... $ 10,231,509.00
Billings to Date...............................................................$ 8,249.033.30
3
Schedule
Notice to Proceed ......................................
Base Contract Duration..... .............. ..................................
Original Completion Date ..................................................
Time Extension Authorized ...............................................
Revised Duration................................................................
Revised Completion Date ..................................................
Weather Days (included in base duration) .........................
Weather Days Expended (included in time expended)......
TimeExpended..................................................................
Percent Time Expended .....................................................
4
,..... . October 10, 2005
1278 consecutive days
April 9, 2004
........ .......... ..... 67 days
........ 1345 consecutive days
..................... June 15, 2009
...... .................. ..40 days
...............................82 days
........... I ...... I ...... 1. 1178 Days
..................................... 88%
Construction Manager's Summary
1. Schedule
The project remains on schedule for completion in June 2009.
2. Work Progress
Oxidation Ditches
Painting of equipment and piping was completed at both oxidation ditches. Operational
testing was also completed.
Grounding of light poles and electrical boxes began.
Secondary Clarifiers
The 5 day operational test was completed.
Grounding of light poles and electrical boxes began.
Main Electrical Building
Drain lines were installed for the condensation line on the evaporative cooler.
Headworks Facility
The operational testing was completed. Discharge chutes were installed on the washer
compactors and trash dumpsters were delivered to the site to collect the screenings.
Work begam on the grounding of light poles and electrical boxes at the structure.
Screw Press Building
Work continued on pulling, terminating and testing of the wiring in the building. Work
began on the steel framework for the biosolids load out slab. Coating of piping and
equipment was completed in the building.
Methane Digester
Coating of the piping and equipment continued through the month at the methane
digester equipment pad. Scaffolding was installed in the methane digester and testing of
the T -Loc liner on the interior of the digester began. Work to ground the light poles and
electrical boxes also began.
Acid Digester
Testing and repair of the T -Loc liner was completed on the interior of the structure.
Boiler Building
Pulling, terminating and testing of wire for the equipment in the building continued.
Coating and insulating of the hot water piping was completed.
Thickener Building
Pulling, terminating and testing of wire continued throughout the month.
Biofilter
Smoke testing of the biofilter gravel layers was completed. The media was then
reinstalled in the bioli ters.
Operations and Maintenance Building
Completion of punch -list activities continued.
Filter Support
Start-up of the chemical metering pumps began. Testing was also started on the polymer
equipment.
Tertiary Filters
Little work was done at this facility during the month. The structure was used in the 5
day operational test.
LTV Disinfection
Coating of the air lines was completed.
Recycled Water Pump Station
This facility has been put into operation.
Wetlands Planting
A seed mix of native and wetland plants was planted in the mitigation wetland area.
Site Landscaping
Final grading was completed in the area south of the UV structure.
Planting of trees was started along the west entry road. Planting continued around the
operations and maintenance buildings.
Polishing Wetlands
The planting of Cell D was completed and with this, all of the cells have now been
completed. The wetlands biologist will be brought out to confirm that the plantings in all
cells satisfy the Contract requirements.
Existing Chlorine Contact Basin
Punchlist and other corrective work continued in the area throughout the month.
3. Contract Changes
Six change orders were processed in December with a total value of $1.51,871.00. Three
hundred sixty one change orders have been executed to date with a combined value of
$4,141,218.00. The change orders greater than $10,000 executed this month areas
follows:
Rerouting of electrical conduits at the headworks deck. $46,510.00
Shoring costs at Junction Box No. 2 $48,500.00
Dewatering costs at Junction Box No. 2 $28,000.00
Analyzer changes and minor changes to the instrument index $23,495.00
The Contractor continues to negotiate change order pricing however, they have asked that
all change orders be issued unilaterally.
4. Field Orders
Eleven
new field orders were prepared in December. Two -hundred forty six field orders
have been prepared for the project. Of those, one hundred fourteen remain active with a
total estimated value of $899,656.00. Active field orders for general changes greater than
$10,000
are as follows:
FO
No.
Description
Amount
76
Concrete Hand Holes at Light Bases
$15,456.00
88
RWPS: Truck Fill Station
$11,354.00 A
I 106
CCB: Addition of Drain Vault Float and Clarification on Heat Trace Controller
$15,000.00
110
Handrail at Oxidation Ditch 1 and 2 North Bull nose
$10,000.00
111
Handrail Post Pockets at Headworks
$25,000.00
113
HVAC Modifications at Filter Support, Thickener & Screw Press
$10,000.00
117
Modify Solids Handling Slab
$22,000.00
134
CCB Wash down System
$50,000.00
142
Housekeeping Pads for Pump LCP's at Filter Support
$12,615.00
145
Existing CCB Piping Modifications
$30.000.00
173
Ops Bldg: Canopy Hood Single Speed Motors
$10,000.00
175
Water Meter Box Modifications — Locations and Valves
$11,641.00
177
Level Switches at RWPS Cans
$15,000.00
182
Additional Grading at RWSB — Build Up Petals
$20,000.00
183
Waste Gas Flare Modifications
$15,000.00
200
CCB Paving/Grading Modifications
$40,000.00
201
West Access Road Sidewalk Demolition
$10,000.00
202
RWPS 3W Supply Modifications
$10,000.00 I
204
Entry Road Sidewalks
$40,000.00
207
West Access Road — Entrance Conduit Protection
$12,000.00 I
216
Life Ring Cabinets
$10,000.00
221
Motor Operated Gates in Fences
$10,000.00
225
East Flood Protection Berm
$75,000.00
233
Headworks Barscreen Enclosure Gas Monitoring
$20,000.00
237
1 W/2W Pump Station Air Gap Tank Coating
$10,000.00
239
Light Pole and Enclosure Grounding
$20,000.00
240
Motor Control Wiring Modifications
$20,000.00
242
Screw Press: Power Supply for LCP-17SPRO01
$25,000.00
Total Active Field Orders < $10,000
$324,590.00
5. Testing
Pipe was pressure tested as required throughout the month.
Testing of the control systems as noted in items above were completed this month.
6. Anticipated Work for Nest Month
The process test of the liquid process is scheduled to begin on January 6. This test will
bring sewage into the plant and the headworks, oxidation ditches, secondary clarifiers and
other related equipment/facilities into service.
Strategy field-testing to confinn the operation of the control programming is scheduled to
be completed on the filter support building, tertiary filters, and UV facility.
At the screwpress building, the piping for the load out facility will be installed and
coating of the pipe will begin.
The sand for the tertiary filters is scheduled to be delivered and installed near the end of
January. Prior to this, the factory representative will be on site checking the installation
and process controls to confirm that the system has been properly constructed.
The factory representative for the UV disinfection facility will be on site to begin the
start-up process for that equipment.
Electrical work will continue at the boiler building, screw press building, ferrous chloride
and digested sludge tank.
Landscaping work will continue throughout the site.
SUBMITTAL STATUS
FIELD ORDERS
Total Cost of
Total December Active Active Orders
Field Orders Issued 246 11 114 $899,656.00
CHANGE ORDER SUMMARY
Total December
Value of Change Orders Executed in December 6 $151,871.00
Value of Change Orders Executed to Date 361 $4,141,218.00
Percent to Date of Original Contract 3.759;,
WEATHER RELATED DELAYS
Days
Base Contract Allowance 40
Weather Related Days in December 0
Weather Related Days to Date 82
9
Received
To Date
December
Returned
Pending
First Time Shop Drawing Submittals
903
0
903
0
Request for Information
1536
12
1534
2
C. M. Request for Information
262
3
261
1
FIELD ORDERS
Total Cost of
Total December Active Active Orders
Field Orders Issued 246 11 114 $899,656.00
CHANGE ORDER SUMMARY
Total December
Value of Change Orders Executed in December 6 $151,871.00
Value of Change Orders Executed to Date 361 $4,141,218.00
Percent to Date of Original Contract 3.759;,
WEATHER RELATED DELAYS
Days
Base Contract Allowance 40
Weather Related Days in December 0
Weather Related Days to Date 82
9
w
Kiewit excavated the walking trail section which runs from the berm at Polishing
Pond Cell A to Ellis Greek before placing the decomposed granite trail materials.
tw .
10
Kiewit Iron Workers performed the layout and placement of the FRP Grating supports in
the Polymer Blending area in the Filter Support Building
M iW' I
w
WW W
pp 5^otla A „� I�
One Kiewit Laborer applies the herbicide to the surface of the Biofilter
media to prevent the growth of Weeds and other plants in the structure.
Kiewit Pipe Fitters placed the 10 inch Digested Sludge Overflow
Ductile Iron piping on the south side of the steel tank.
12
Ellis Creek Water Recycling Facility
CONTRACT CHANGE ORDER TRACKING SHEET
CCO #
Description
Amount Days Status
1
Time extension for additional soil sampling
0.00 8
2
Lime treatment at Ox Ditch & Secondary Clarifiers
125,000.00
3
Board up Farmhouse
3,385.00
4
Hay Stacker Relocation
493.00
5
Terrorism Insurance and Increased Earthwork
0.00
6
Meter in Temporary Recycled Water Pipeline
3,023.00
7
Temporary Power for Pond 1 Aerators
1,270.00
8
Pavement Repair on Cypress and McDowell
419,681.00
9
Conduit Encasement Coloring Agent
{ l r'k00 001
10
Delayed Caltrans Encroachment Permit
16,723.00
11
Trench Cut -Off Walls
8,(100 000
12
Horizontal Aerators Extended Warranty Testing
0.00
13
Deletion of Prime Coat under AC Pavement
?9,100 00)
14
Replace PVC Sched. 40 with EB 20 Conduit in DB
1, 7 74 OM
15
Delete Lakeville Highway Access
40,000.00
16
Contract Time Extension for Weather Days 03-04/06
0.00 38
17
Change Valve Types
0.00
18
Replace EMT conduits by MC cable (@_ O&M Bldg
11 ii 7 W)
19
Inverter Duty Motors at Oxidation Ditch Aerators
16.466.00
20
Aerated Lagoon and Pond 1 Modifications Milestone
0.00
21
Additional Striping and Loops on McDowell
13,74200
22
Catch Basins Invert Changes
01.99' 00)
23
Oxidation Ditch Sump Modifications
750,00)
24
Change Buried Conduits PVC GRS to PVC Sch. 40
+'.t'1;? 038,t1tr)
25
Temporary Power to Existing Aerators 4 and 7
7,956.00
26
O&M Bldq: Ceiling & Wall Heights Rms
4,287.00
27
Provide Portable Generator Pads at Ponds
2,554.00
28
FS Bldq: Extend Conduit Stub -ups Beyond Ductbank
9,190.00
29
Headworks: Handrail Extension to Complete Deck
1,254.00
30
Pond 4 Aerator Temp Power
883.00
31
Aerated Lagoon: Reconnecting of Aerator No, 2
537.00
32
Unknown Utility at Pond 1 North Side
855.00
33
Ductbank Encasement with Reinforcing
24,884.00
34
Gun Safe for Storage of Bid Documents
2,410.00
35
S&C Pad Mounted Switch Additions
75,200.00
36
Permanent Power Supply for Pond 1 Aerators
98,000.00
37
Temporary Fire Hose
851.00
38
Change material for Temporary Debris Collector
(36,150 ()0)
13
CGO #
Description
Amount
39
Chemical Tank Pads @ Filter Support Bldg
4,425.00
40
Disconnect Aerator No. 2 & reconnect Pond 4 Aerators
607.00
41
Delete Steel Steps in Manholes
i s),t} I ' tkt 3 i
42
Add 4" Butterfly Valve in Acid Digester
1,189.00
43
Delete Pre -Action Fire System @ Main Elect. Bldg
(I" ,2 1,t. uu)
44
Headworks Influent Box Modifications
3,000.00
45
Transformer Pad at Restroom
9,498.00
46
Addition of Construction Joint at Oxidation Ditch Slabs
23,505.00
47
Change Conduits from PVC Rigid Steel to PVC Sch. 40
21 912 00)
48
Reader Board & Geogrid placement (n� Cypress/McDowell
6,000.00
49
Plant Control System PLC Architecture
(6 i 18 001
50
Grit Pump Room Sump Pump Modification
1,326.00
51
PLC Enclosure Size for PLCs 2, 3 and 8
5,446.00
52
Additional Time Switches at O&M Bldg.
2,722.00
53
Extension for Pond 1 Aerators Milestone Date
0.00
54
Levee Repair at Berm Existing Ponds 8 & 9
289,279.00
55
Operations Bldg. Maintenance Window
1,022.00
56
In -Plant Pump Station Wall Penetration Details
2,807.00
57
Alignment of 42" RSG line to Headworks
4,208.00
58
Revision of Structural Joints at Headworks Facility
5,628.00
59
Pond 9 & 10 Levee Pothole
1,400.00
60
Add pipe for Future Pump Can (aD RWPS
6,316.00
61
Home Inspection of Farm House
746.00
62
Alignment of 42" PWE line to Cell D Transfer Structure
8,171.00
63
Delete Locks on Motor Operated Overhead Coiling Doors
(383 OM
64
Dewatering of Pond 8 and Mitigated Wetland
3,488.00
65
UV System Programming
2,777.00
66
Septic Tank Removal at Farm House
739.00
67
Changes to Slide and Sluice Gates
11,177.00
68
PLC System Material for C Street Pump Station
14,915.00
69
PLC - 10 Analog Input Module
1,873.00
70
Change Storm Drain Pipe from RCP to CHDPE
12 39'st.UO)
71
Deletion of CMU Coating on non -occupied structures
i2 538 it(t)
72
Existing Utilities at West Access Road Entrance
8,543.00
73
Change Handrail for Polishing Wetlands Structures
6,965.00
74
Change SDR for HDPE Pipe Lines
511,4 p 5,00)
75
Addition of waterstop in wall (ai Filter Support Bldg.
1,330.00
76
Delete waterstop & starter walls na. HW, RAS PS, UV
(4 _ 0(3 001
77
Re -Power Pond Aerators, Reconnect Aerated Lagoon
3,718.00
78
Contract Time extension for Weather Days 10/2006
0.00
79
Deletion of waterstop and starter walls at Tertiary Filters
384 001
80
Add waterstop at Grit Pump Area of Headworks Structure
6,167.00
81
Fuel Tank Removal at Farmhouse
2,972.00
14
Days
1
Status
CCO #
Description
Amount
82
Revised Anchorage for Oxidation Ditch Aerators
40,941.00
83
Deletion of Integrated System Shoo Testing (ISST)
0.00
84
Additional Dowels at Maintenance Bldg.
914.00
85
Replace Fuses at MCC 3A after PG&E power spike
1,706.00
86
Remove and replace disconnect switch @ Aerated Lagoon
2,919.00
87
Lower Invert Elevation for 42" RSG Line
18,726.00
88
Addition of Roof Hatch @ Main Electrical Bldg.
3,195.00
89
Filter Support Bldg: NG Connections and Valvinq
1,361.00
90
Chain Link Fence addition @ Farmhouse
725.00
91
Repair Irrigation Lines @ Kaiser
1,186.00
92
Demo of Spillway at Pond 10
12,109.00
93
Curb and Grading @ Filter Support Bldg
0.00
94
Irriqation System: Concrete Valve Boxes
2,393.00
95
Contract time extension for Weather Days 11106
0.00
96
Mitigation Wetlands Drain
4,370.00
97
Additional vinyl sheets for Levee Repair @ berm Pond 8 & 9
5,498.00
98
Shoring @ Naval Trail
21,271.00
99
Extra excavation @ W Access Rd. for 12" 1W line
8,008.00
100
Replace SBS line @ Chlorine Contact Basin
5,936.00
101
Brush clearing @ Farm House
5,209.00
102
Relocate standby Generator @ CCB
2,005.00
103
Drywall Furring @ Elect Rm #2 in O&M Bldg.
1,630.00
104
Equipment for MCC -3 retrofit
25,360.00
105
Perimeter lighting switching @ Main Elec. Bldg.
1,795.00
106
Wiring for Time -Off Relay @ Wetlands Elec Bldg.
2,282.00
107
Changes to SCADA interface Boiler & PLC 3
3,549.00
108
Disposal of existing MCC 3 transformer
2,141.00
109
Contract time extension for Weather Days 12/06
0.00
110
Tree removal (a) W Access Rd.
1,419.00
111
Deepening Pull Boxes @ Ox Ditch MCC Bldg.
11,540.00
112
Rebar modification @ Wetlands Pump St Deck Beam
2,187.00
113
Electrical Equipment Pads
9,018.00
114
Delete Catch Basins at W Access Rd.
1,746.00
115
Naval Bldg Lookout Area
3,000.00
116
Changes to TWE and PWE lines
0.00
117
Polishing Wetlands FSS: Add Hand Switch
3,444.00
118
Engineering of Anchorage @ Oxidation Ditch Aerators
t70,0`993 00)
119
Replace Oxygen Probes @ Aerated Laqoon/Pond 1
13,411.00
120
Change Piping Material for Deionized Water Service
0.00
121
Filter Support Bldg: Relocation of 1W Line
4,568.00
122
Security Lighting at Farmhouse
1,200.00
123
Disposal of Asbestos Containing Pipe
2,087.00
124
Investigation and Disposal of FAA Building
20,512.00
is
Days
5
Status
CCO #
Description
Amount Days Status
125
Conduit addition @ Boiler Bldg.
15,780.00
126
O&M Bldg: Exhaust fans power supply & controls
34,440.00
127
Addition of Disconnect Switches @ Headworks
25,143.00
128
Level Transmitter addition (aHeadworks
23,058.00
129
Contract Time extension Weather Days 01-02/07
7
130
Subgrade Improve & Pipe Encasement @ W Access Rd.
12,128,00
131
Additional Conduit for Fuel Leak Detection
2,714,00
132
HVAC Enclosure Modifications @ Ops Bldg,
8,014.00
133
Wiring of Spare I/Os
45,713.00
134
PLC Enclosure Size for PLC 5
7,823.00
135
Partial Payment for PLC Enclosures
0.00
136
Trench Backfill with Native Material
172,000,00)
137
UV Bldg Top Slab Modifications
14,000.00
138
Ops Bldg: HVAC Electrical & Mechanical Modifications
2,854.00
139
24" Pumped Storm Drain Line Coverage
30,000.00
140
Metal Siding @ Main Electrical Bldg.
5,071.00
141
Contract Time Extension for Weather Days April 2007
1
142
Ops: Relocate HVAC duct transition @ Locker Rm Ceiling
878.00
143
Use of Native Material for backfill (o) North & Middle Cluster
W),1)00 sxn
144
Recycled Water Storage Basin Size Increase
220,867.00
145
Outlet conduit replacement (a) Existing CCB
1,260.00
146
Modify Rebar Expansion Joints @ Thickener Bldg
1,610.00
147
Modify Grating Seat (a) Headworks Beam B-13
1,737.00
148
Added Space Heater for PLC 8 - RIO 1
1,803.00
149
Additional G2 Light Fixture (q) Bldg Lobby
2,013.00
150
Connection Grounding Bldg rebar @ MCC HW Bldg.
974.00
151
Relocate supply line fire riser (cD maintenance Bldg.
3,027.00
152
Pipe material for 36" mixed liquor line @ 2ndary Clarifiers
14,271.00
153
Modifications HVAC Pads
9,562.00
154
Mod per PG&E Requiremnts to Main Power Supply
19,886.00
155
Addition of Wall Sleeves at Thickener Building
847,00
156
Reduce Deck Slab Openings @ Wetlands Pump Station
782.00
157
Wall Supports for Pony Wall at Laboratory
2,162.00
158
Concrete Encase HCS pipeline @ Headworks Structure
2,393.00
159
Convert Conference Rm into 2 Offices @ Ops Bldg,
8,351.00
160
Concrete Backfill around Screw Press Equipment Trench
1,588.00
161
Expansion Joint Rebar @ Headworks Grid Line 10
1,151,00
162
Standby Generator Connection (a) Wetlands PS
13,527.00
163
Deletion of Rotameters (cD Tertiary Filters
'074 00)
164
Blockouts for Ox Ditch Aerator Anchorage
1,022,00
165
Concrete Encase SD pipe under HWE pipeline @ HW
1,657.00
166
Temporary Power for Transformer (c) Aerated Laqoon
28,343.00
167
Rebar @ Headworks Manual Bar Screen Embed
756.00
16
CCO #
Description
Amount
168
Subgrade Improvement for Wetlands PS Apron Slab
11,799.00
169
Screw Press Bldg Skylight Size Change
3,465.00
170
Additional 1/0 from Power Panel to PLC-9
2,887.00
171
Standby pump @ existing CCB during work @ Pond 10
44,000.00
172
Billing for Potable Water Usage on site through 4/4/07
1,552.00
173
Upgrade starters for Ox Ditch Aerator Motors
78,373.00
174
Blind flanges for future effluent line (o, Aerated Lagoon
11,709.00
175
Remove rebar @ Ox Ditch Aerator Motor Block-outs
3,000.00
176
Modification of controls for Tertiary Effluent Bypass Valves
(aW/5 OU)
177
Communication between PLC-8 & Thickener PLC
2,032.00
178
Automated 1W Valve @ Recycled Water Storage Basin
46,267.00
179
Modification to HW Bar Screen Channels
6,130.00
180
Relocate Fire Pump Can @ RWPS
4.613.00
181
Add Effluent Conductivity Probe (a7 JB No. 2
9,680.00
182
Revise DB Routing @ Ferrous Chloride Area
2,463.00
183
Ventilation Alarms @ Boiler Bldg & Thickener Bldg
20,526.00
184
Anti Graffiti Coating @ O&M Bldg and Sound Wall
28,736.00
185
Deletion of Louvers @ HW Bar Screen Enclosures
? 374 00)
186
Deletion of Combination Smoke Fire DampersYa
00
187
Fire Rating Janitor Closet Door @ Ops
1,841.00
188
Brush clearing @ Farm House fire season 2007
3,186.00
189
Ops: CMU alignment & wall cap (cD HVAC enclosure
1,826.00
190
Ops: addition acoustical ceiling @ electrical rm #1
3,125.00
191
Ops: framing details for Lobby
2,163.00
192
RWPS: modified floor drainage
15,107.00
193
Ops: beam seats in CMU wall pockets
10,067.00
194
Recycled Water Storage Basin Berm Modifications
(1 119b Ocr )
195
Double Containment System Modifications
90,172.00
196
Site Security Lighting Estimation Cost
10,364.00
197
Grading @ Mitigation Wetlands & RWSB
27,012.00
198
PG&E power connection @ W Access Rd.
55,335.00
199
UV Disinfection Light Pole Mounting Detail
7,027.00
200
Ox Ditch Light Pole Mounting Detail
8,852.00
201
Existing CCB: power to New Chemical Metering Pump
8,588.00
202
Screw Press grating @ Flocculation Tank Opening
1,969.00
203
Anchorage of Diffuser Pipe Ponds 9 & 10
32,659.00
204
Acid Digester changed detail wall penetrations
4,286.00
205
Existing LPN panel in chemical bldg.
2,576.00
206
Revised Details @ RWSB
20,881.00
207
Ops: Deletion of Closet in Control Room
,,>,;nla
208
Ultrasonic level sensor mount @ Headworks
1,208.00
209
Mitigation Wetlands Drain - Permanent Installation
75,048.00
210
Ops Bldg: Plumbing Dwgs
29,571.00
17
Days status
cco #
( Description
Amount Days Status
211
Ops: Deletion of decking @ Mechanical Chases
1,719.00
212
Headworks: channel floor rebar modification
1,696.00
213
Ops: Furring Men's Restroom Urinal Wall
740.00
214
Informational Kiosks: Addition of 2" PVC 40 Pipe Sleeve
2,560.00
215
Screw Press: Modifications to Underslab Piping
2,607.00
216
Below Grading Coatings
72,507.00
217
Aerated Lagoon: Unknow utility @ 20" URW Alignment
5,225.00
218
Ops Bldg: Additional Window Clips
3,194.00
219
Silt Fence Repair
1,209.00
220
Ops Bldg: control rm. Backing & wood blocking
2,185.00
221
Ops Bldg: Modifying Welding Studs to 1/8" Tubing
5,293.00
222
Pond 10 Apron Slab: Over Ex, Fabric, and Rock
3,870.00
223_
Addition of Solenoid Valve @ Recycled Water Surge Tank
5,095.00
224
Thickening Walls @ Ox Ditch Aerator Shafts
11,286.00
225
Relocate Receptacles (a) Biofilter Mechanical Pad
3,286.00
226
Equipment Pad Modifications (a, Screw Press
5,130.00
227
Footing Elevation @ Filter Support Bldg. Tank Farm
2,098.00
228
Relocation of Cell D Transfer Structure
5,162.00
229
Pipe Elevations & Drainage Swale (a.) Polishing Wetlands
1,938.00
230
Farm House: Plywood Cover (a), Back Entry
756.00
231
Methane Digester construction joint location & piping
1,057.00
232
Ops Bldg: Icemaker Legs
893.00
233
Acid Digester: Overflow Piping Modifications
1,727.00
234
West Cluster: Sitework & Grading Change
277.00
235
Ops Bldg: Future access control conduit stub -outs
1,720.00
236
Ops Bldg: Interior lights & furring strips
2,292.00
237
Potholing & Excavation existing utilities @ GCB
42,606.00
238
Replace Farmhouse Roof
34,194.00
239
SCADA: TWAS sump level set points
1,682.00
240
CCB: Relocation of Ammonia Tank
17,176.00
241
Add wire way in PLC 6 @ Existing Chemical Storage Bldg.
1,775.00
242
Replace Landscaping on Kaiser Property
2,690.00
243
Electrical Modifications @ UV Bldg.
47,188.00
244
Headworks: Rebar Detail @ Channel Wall Ends
1,625.00
245
Rebar @ Screw Press Bldg. Slab Extension
1,625.00
246
Tertiary Filter: 12 Inch Inlet Line
17,248.00
247
Ops: Modifications to Fume Hoods
( 490 not
248
Ops: Addition of Compressed Air @ Laboratory
22,641.00
249
Ops: Training Room Modifications
8,494.00
250
Emergency Repair Kit Deletion
(56i N))
251
Increase Cover Over 14 inch Foul Air Line
1.972.00
252
Headworks: Epoxy Coat Rebar (@ Block-outs
20,579.00
253
Relocation of Mezzanine Column (aD Screw Press
3,225.00
l8
CCO #
Description
Amount Days Status
254
Additional Rebar @ Oxidation Ditch
1,348.00
255
Pipe Class Acid Gas & Methane Gas Pipe
U tr it
256
Modifications to the Potable Water System
105,856.00
257
Thickening Bldg piping modifications
764.00
258
Catch Basin grating modification @ W Access Rd. culvert
4,950.00
259
Headworks FRP grating support(d) Gate location
2,219.00
260
Digested Sludge Storage Tank: Piping Modifications
4,828.00
261
Modifications to Analyzer Enclosures
9,315.00
262
Additional Conduits & Wires Miscellaneous Areas
41,620.00
263
Planting modification @ West Access Rd.
2,328.00
264
Install Clapper Rail Trail Gate
2,687.00
265
Amphitheater seating next to Polishing Wetland Cell D
29,577.00
266
Ferrous Chloride- revised electrical & pump pad
24,552.00
267
Chip Down Top of Wall @ Filter Support
3,411.00
268
Conduits for Future Mixer @ GCB
11,320.00
269
Modifications for Interfacing between PLC 6 and PLC 11
5,800.00
270
Headworks Deck Slab Falsework
26,026.00
271
Dewaterinq of Pond 8
20,157.00
272
Pressure Gauges @ Wetlands Pump Station
4,110.00 _
273
Irrigation Changes @ Point of Connection
24,050.00
274
Filter Support: 4" chemical drain elevation
872.00
275
Unknown Utilities @ Site Entrance
4,205.00
276
Mitigated Wetland Planting
3?,30900)
277
Changes & Additions to 3W System @ Ox Ditches
34,716.00
278
Garbage Bin Structure
25,644.00
279
Relocate Veolia Materials @ CCB
788.00
280
Wetlands PS Portable Eyewash Station
5,217.00
281
Temporary Irrigation Connection to Schollenberqer
2,255.00
282
Partial Deletion of Planting @ Polishing Wetlands
Ifi;st70 no)
283
Change NEMA Rating for Pull Boxes @ Ox Ditches
t 10 /:c,Fi 00 a
284
Delete Trail Material W Polishing Wetland Cell D
C!/ 161) (10)
285
Equipment Pad Modifications @ CCB Bldg.
26,412.00
286
Parapet Detail @ Ops Bldg Lobby
18,746.00
287
Relocate Potable Water Riser @ 1 W Pump Station
3,299.00
288
Dewatering Pond 7for TWIS
14,419.00
289
Additional work for Farmhouse Roof Replacement
41,819.00
290
Material for Clay Liner in RWSB
13,820.00
291
Ops Bldg 1 hr Fire Rating
40,885.00
292
Maintenance Bldg: 2hr Fire Rating
1,282.00
293
Relocate Tie -In to Potable Water Sys @ Cypress Dr.
8,042.00
294
Changes to Gates & Operators @ W Access Rd.
U08-1 00)
295
Ellis Creek Clean Up
8,395.00
296
Analog Input Module for PLC 11
2,766.00
19
CCO #
Description
Amount Days Status
297
Addition of the Polishing Wetlands Pump Station
415,000.00
298
Natural Gas Connection & Metering Pad
18,435.00
299
Additional Digital Input Points PLC 9
2,335.00
300
Weather Monitoring Station
24,976.00
301
Modifications for future Polishing Wetlands Pump Station
16,899.00
302
Addition of Geofabric @ East Access Rd. Ponds
8,740.00
303
Outlet Cutouts in Backsplash @ Ops Laboratory
1,908.00
304
Ops Bldg: Exhaust Fan Drainlines
7,662.00
305
PVC pipe for Plant Drain Piping
(4,357 00)
306
Drainage Swale @ W Access Rd.
500 000
307
UV Stair Grating Changes
;. I I om
308
UV Channel Blockouts for Wireways
ft, 849 Oil)
309
CCB: Welding of 42" Pipe Connections
27,142.00
310
Trail Connection @ Schollenberger Park
13,167.00
311
Waste Gas Flare Pedestal
2,366.00
312
Relocation of cabinets in Ops Bldg.
753.00
313
Support for folding Partition in Ops Bldg.
830.00
314
Deepen Fuel Sump @ Generator
3,855.00
315
Operation Bldg: Fire Sprinkler Riser
25,728.00
316
Glass Lined Ductile Iron Pipe
97,613.00
317
Wetlands PS Mixer Mounting Bracket
1,798.00
318
Uninterruptible Power Supply @ Ops Bldg.
24,754.00
319
Clarifier 1 & 2 Light Post Mounting
3,060.00
320
Transformer Relocation (d), Existing CCB
6,187.00
321
Ops Bldg: Mudroom Skylight Framing
5,192.00
322
Wetlands Pump Station Interim Milestone
0.00
323
Analyzer Enclosure @ Outfall Structure
11,080.00
324
Additional Grating @ Biofilter Damper Boxes
2,747.00
325
Additional Valves for Hydronic System
762.00
326
Modifications @ Flow Control Structure C-2
.1)9 3 00)
327
Change Manhole & Catch Basin Elevation @ South Cluster
1,923.00
328
Modifications to the Existing Outfall Structure
12,254.00
329
Anti Graffiti Coating @ Garbage Bin Structure
2,389.00
330
Instrumentation and Control Modifications @ Existing Plant
58,658.00
331
Miscellaneous Extra Work @ Junction Box No. 2
49,264.00
332
Miscellaneous Extra Work @ Existing CCB
12,655.00
333
Paint Flashings and install Spark Arrestor @ Farmhouse
2,860.00
334
Temperature Detection for Recycled Water Pumps
19,598.00
335
Raise Top of Electrical Pull Box (a) Headworks
3,391.00
336
Modifications to Biosolids Load -out @ Screw Press Bldg.
266,077.00
337
Rerouting of Electrical Conduits @ Headworks Deck
46,510.00 Unilateral
338
Miscellaneous Instrumentation Modifications
5,366.00 Unilateral
339
Reverse Service Generator Plug
4,699.00
20
CCO # 1
Description
Amount
Days Status
340 11
Submersible Sump Pump Control Panels
2,445.00
341
Flow Meter Transmitters @ WPS
1,597.00
342
Additional Fence & Gate ii Existing Farmhouse
5,299.00
343
Install pressure gauge (a) Tertiary Filter Hypochlorite panel
1,684.00
344
Widen Sidewalk (a) Filter Support Bldq.
821.00
345
Anti Graffiti Coating (aW Access Rd. Public Restroom
3,920.00
346
Screw Press Parapet Wall Height
2,658.00
347
Handrail Installation (a) Ox Ditch Weir Gates
7,798.00
348
Bond and Insurance Over-Billinq
(68.172 00)
349
Drains for AC Unit & Backflow Preventers (a(7 Ops Bldg
2,185.00
350
Delete wires @ Headworks & add wires (a) PW FSS
0.00
351
Added Sample & Drain Lines (a? JB 2
4,127.00
352
Additional Blackout Shades (aD Ops Bldg.
885.00
353
Relocation of Drain Lines (pil Biosolids Load -out Slab
10,201.00
354
Deletetion of Vinyl Coating- chemical pump pad (a) CCB
1,4Lil tr(i)
355
Ferrous Chloride Line Encasement under Equip Pad
2,608.00
356
Power Supply to Current Tranducers (a) Ox Ditches
3,999.00
357
Level Switches (a. RWPS
5,081.00
358
Contract Milestone O&M Bldg Occupancy/SCADA Readiness
0.00
360
Shoring (a) JB 2
48,500.00
Unilateral_
361
Dewatering P JB 2
28,000.00
Unilateral
362
Analyzer Changes & Minor Changes to Instrument Index
23,495.00
Unilateral
CHANGE ORDER TOTAL:
4,141,218.00
67
Contract Amount:
110,329,000.00
1278
Percent Change Orders:
3.75%
i
Totals:
114,470,218.00
1345
I
Total Additive Change Orders
-, 29.947 Ute
Percentage of Contract Amount
4.65%
Total Credit Change Orders 1988.729 001
Percentage of Contract Amount 0.90%
Contract Substantial Completion Date 4/9/09
Current Substantial Completion Date 6/15/09
21
a
R
4
U
LL
T
Fu
w
Q
a, I
4.
M.
w
E4 9