HomeMy WebLinkAboutStaff Report 3.J 07/11/2005CITY OF PETALUMA, CALIFORNIA 3.J
A.J
PETALUMA COMMUNITY DEVELOPMENT C July 11,
1' 2005
AGENDA BILL
Aeenda Title: Discussion and Action Adopting a Resolution Meetine Date:
Accepting Completion of the North Bay Construction, hie. July 11, 2005
Construction Petaluma Railroad Depot Renovation — Phase 2
Contract, Project No. 3300-54151-C200303 And Approving the Meetine Time: ® 3:00 PM
Final Project Budget. Total Project Cost: $1,472,078, Funded by ❑ 7:00 PM
Central Business District Project Area Fund 3300
Cateeory (check one): ® Consent Calendar ❑ Public Hearing ❑ New Business
❑ Unfinished Business ❑ Presentation
Department Director: Contact Person: Phone Number:
ED & Redevelopment Paul Marangella Evelyn Onderdonk 776-3673
G
Cost of Proposal: $1,472,078 Account Number:
3300-54151- C200303
Amount Budgeted: $1,525,397
Name of Fund: Central Business
District Capital Improvement Fund
3300
Attachments to Aeenda Packet Item:
1. Resolution Accepting the Completion of Petaluma Railroad Depot Renovation - Phase 2 and
Approving the Final Project Budget.
Summary Statement: North Bay Construction, Inc. completed Phase 2 of the Petaluma Downtown
Improvements Phase 2 for a final cost of $1,152,514.
Work under Phase 2 consisted of infrastructure improvements such as installation of storm drain, sanitary
sewer, water, gas, electrical, fire line, railroad signal interconnect conduit, and lighting. Work also
included planting trees, AC paving, curb and gutter, concrete pathways and sidewalks, and some
decomposed granite sidewalks.
Recommended PCDC Action/Sueeested Motion:
Adopt a resolution accepting the completion of Petaluma Railroad Depot Renovation — Phase 2, Project
No. C200303 and file a Notice of Completion with Sonoma County Recorder. The Administrative Services
Department will release the 10% retention to the contractor 45 days after the recordation of the Notice of
Completion.
Reviewed by Finance Director: Reviewed by City Attornev: A ro City Mana er:
Date: Date: Date:
k6lWI (( I
Todav's Date: Revision # and Date Revised: File Code:
June 30, 2005 # EDR S:\CIP Depot C200303 (9040)\Const uefion
Phase 2 - Siteworrk, Paving\30 Agenda Rills\Resp
Accepting Depot Phase 2Cempletion 06 02 05 co.doe
Page 1
CITY OF PETALUMA, CALIFORNIA
Petaluma Community Development Commission
July 11, 2005
AGENDA REPORT
DISCUSSION AND ACTION ADOPTING A RESOLUTION ACCEPTING COMPLETION OF THE
NORTH BAY CONSTRUCTION, INC. CONSTRUCTION PETALUMA RAILROAD DEPOT
RENOVATION PHASE 2 CONTRACT, PROJECT NO. 3300-54151-C200303 AND APPROVING THE
FINAL PROJECT BUDGET
1. EXECUTIVE SUMMARY:
North Bay Construction, Inc. completed Phase 2 of the Petaluma Railroad Depot Renovation — Phase 2
for a final cost of $1,152,514.
Work under Phase 2 consisted of infrastructure improvements such as installation of storm drain,
sanitary sewer, water, gas, electrical, fire line, railroad signal interconnect conduit, and lighting. Work
also included planting trees, AC paving, curb and gutter, concrete pathways and sidewalks, and some
decomposed granite sidewalks. In addition, the PCDC implemented material and scope of work
changes requested by the Fire Department.
2. BACKGROUND:
The Petaluma Railroad Depot complex, which consists of three buildings, the Main Depot, the Baggage
Building and the Freight Building, were badly deteriorated and renovation was needed to preserve the
historic value of the buildings.
Discussions to preserve the buildings and use them for City functions began several years ago. The first
step was the securing of a lease of the three buildings from the NWPRA. A 25 -year lease between the
City and NWPRA became effective on July 14, 2003. Phase 1 of construction involved the renovation
of the exterior of the buildings. Phase 2 of construction consisted of the renovation of the landscaping
of the site and infrastructure improvements. Phase 3 involves the renovation of the interior of the Depot
and Baggage buildings and installation of Trash Enclosure. Phase 4 will involve the renovation of the
Freight building interior. The NWPRA and SMART have been informed of each step of the historic
renovation and appreciate that the PCDC will continue with the renovations, as required by the lease.
During the course of construction, the Fire Department expressed interest in adding a fire line to the
buildings to provide for fire sprinkler system thereby modifying the scope of work.
The contractor has completed the work for a final construction cost of $1,152,514. The 10% retention
payment is due and payable 45 days after the City Clerk records the Notice of Completion.
3. ALTERNATIVES:
Accept the completion of the project.
Pap 2
4. FINANCIAL ImpAcrs:
The PCDC appropriated $1,525,397 for the Petaluma Railroad Depot Renovation Project, Phase 2,
including the work in this package plus purchasing trees and street furniture, as well as design,
construction management, administration and general overhead. Of this amount, $1,472,078 was
expended
Project Cost Summary
Construction — Bid Package $1,200,516 $1,152,514
NBC w/Contingency
PG& E, SBC, Fence $30,000 $28,600
Purchase Site Furnishings $43,865 $39,865
Total $1,525,397 $1,472,078
Pagc 3
RR Depot
RRDepot
RR Depot Renovation
Renovation Phase 2
Renovation
Budget By Category
Project
Phase 2 Final
Budget
Expenditures
General Fund Overhead
$72,638
$70,099
Administration
$30,367
$35,000
Planning/Environmental
$0
$0
Design
I $67,344
$63,000
Legal Counsel
I $0
$0
Construction
Mgmt./hispection
$80,667
$83,000
Construction — Bid Package $1,200,516 $1,152,514
NBC w/Contingency
PG& E, SBC, Fence $30,000 $28,600
Purchase Site Furnishings $43,865 $39,865
Total $1,525,397 $1,472,078
Pagc 3
5. CONCLUSION:
Following the acceptance of the project, the City Clerk will file a notice of completion with Sonoma
County Recorder and the Finance Department will release the 10% retention to the contractor 45 days
after the recordation of the notice of completion.
6. OUTCOMES OR PERFORMANCE MEASUREMENTS TIIAT WILL IDENTIFY SUCCESS OR COMPLETION:,
Completion of the Petaluma Railroad Depot Renovation — Phase 2, Project # C200303.
7. RECOMMENDATION:
Adopt the resolution approving the completion of the Petaluma Railroad Depot Renovation — Phase 2,
Project # C200303, approving the final project budget, and authorizing the release of the 10% retention
to the contractor 45 days after the recordation of the Notice of Completion.
Pagc 4
Attachment 1
RESOLUTION ACCEPTING COMPLETION OF THE NORTH BAY
CONSTRUCTION, INC. CONSTRUCTION PETALUMA RAILROAD
DEPOT RENOVATION - PHASE 2 CONTRACT
Page 5
RESOLUTION NO.2005-
PETALUMA COMMUNITY DEVELOPMENT COMMISSION
ACCEPTING COMPLETION OF THE NORTH BAY CONSTRUCTION, INC. CONSTRUCTION
PETALUMA RAILROAD DEPOT RENOVATION — PHASE 2 CONTRACT,
PROJECT NO. 3300-54151-C200303 AND APPROVING THE FINAL PROJECT BUDGET
WHEREAS, the Petaluma Community Development Commission (PCDC) awarded the contract for the
Petaluma Railroad Depot Renovation — Phase 2, to North Bay Construction, Inc. on August 16, 2004; and
WHEREAS, North Bay Construction, Inc. has completed all the work at a total value of $1,152,514 to the
satisfaction of the Director of Economic Development and Redevelopment and the Redevelopment inspection
team;
NOW, THEREFORE, BE IT RESOLVED by the Petaluma Community Development Commission that the
final total project budget of $1,472,078 is approved and that the City Clerk/Recording Secretary is hereby
authorized to sign the Notice of Completion.
BE IT FURTHER RESOLVED that the Finance Department is hereby authorized to release the ten (10°l0) to
North Bay Construction, Inc. forty five (45) days after the recordation of the Notice of Completion provided
that all stop notices have been released.
Adopted this I I" Day of July 2005 by the following vote:
Commissioner Ave No Absent
Glass
Canevaro
Harris
Healy
Nau
O'Brien
Torliatt
ATTEST:
Claire Cooper, Recording Secretary
Page 6
David Glass, Chairperson