HomeMy WebLinkAboutPRESENTATION 07/20/2009 Ellis CreekPROJECT NUMBER C500402
E
LA)a
F m -"q
-ifi%=04
CONSTRUCTION MANAGEMENT
May/June 2009
PRESENTATION
July 20, 2009
PARTICIPANTS
Owner: City of Petaluma Mike Ban
11 English Street Director
Petaluma, CA 94952 (707) 778-4487
Margaret Orr
Engineering Manager
(707) 778-4589
Contractor: Kiewit Pacific Co. Clint Cole
5000 Marsh Drive Project Manager
Concord, CA 94520 (925) 516-4600
Design Engineer: Carollo Engineers Tom Patten
2700 Ygnacio Valley Rd, Suite 300 Principal
Walnut Creek, CA 94598 (925) 932-1710
Doug Wing
Design Engineer
(925) 299-6733
Environmental ESA Jim O'Toole
Management: 8950 Cal Center Drive, Bldg 3, Suite 300 Project Engineer
Sacramento, CA 95826 (707) 795-0900
Jennifer Garrison
Environmental Manager
(916) 564-4500
Programmer: ArcSine engineering Doug McHaney
970 Executive Way Project Manager
Redding, CA 96002 (530) 222-7204
Steve Stewart
Lead Programmer
(530) 222-7204
Construction The Covello Group Bruce Presser
Manager: 1660 Olympic Blvd, Suite 300 Principal
Walnut Creek, CA 94596 (925) 933-2300
Ken Sinclair
Construction Manager
(925) 260-2943
Ed O'Brien
Field Engineer
(925) 382-1246
2
SUMMARY OF CONSTRUCTION STATUS
KIM, frelffIX11
Base Contract Amount (Total Project) .................................... $ 110,329,000.00
Change Orders Executed .................................................. $ 4,590,388.00
Total Contract Cost ......................................................... $ 114,919,388.00
Contract Amount Earned ................................................... $ 114,766,857.00
Progress Payment May & June 2009 (excludes retention)........... $ 465,544.00
Previous Progress Payments (excludes retention) ...................... $ 102,606,646.00
Estimated Percent Complete ............................................................. 99%
• Design Engineer: Carollo Engineers
Authorized Budget (Total Project) ....................................... $ 4,499,075.00
Billings to Date .............................................................. $ 4,383,359.85
• Environmental Manager: ESA
Authorized Budget (Total Project) ...................................... $ 1,434,830.00
Billings to Date ............................................................... $ 1,174,012.76
* ArcSine engineering
Authorized Budget (Total Project) ....................................... $ 2,340,951.00
Billings to Date ............................................................... $ 2,232,073.25
• Construction Manager: The COVELLO GROUP, Inc.
Authorized Budget (Total Project) ....................................... $ 10,231,509.00
Billings to Date ............................................................... $ 9,025,865.87
3
Schedule
Notice to Proceed.................................................................................October 10, 2005
Base Contract Duration............................................................... 1278 consecutive days
Original Completion Date.......................................................................... April 9, 2009
Time Extension Authorized................................................................................ 67 days
Revised Duration........................................................................ 1345 consecutive days
Revised Completion Date........................................................................ June 15, 2009
Weather Days (included in base duration).......................................................... 40 days
Weather Days Expended (included in time expended) ....................................... 82 days
TimeExpended.............................................................................................. 1345 Days
PercentTime Expended......................................................................................... 100%
0
Construction Manager's Summary
1. Schedule
The project is on schedule and substantially complete on time, June 15, 2009.
2. Work Progress
Oxidation Ditches
The facilities are in operation. Final Performance Testing was completed and final
reports are being developed by the Contractor.
Secondary Clarifiers
The facilities are complete and in operation.
Main Electrical Building
The facility is complete and in operation.
Headworks Facility
The facilities are complete and in operation.
Screw Press Building
The facility is in operation. They system will be operated and optimized while the
digester stabilizes in preparation for final performance testing.
Methane Digester
The facility is in operation.
Acid Digester
The facility is complete and in operation.
Boiler Building
The facility is complete and in operation.
Thickener Building
The facility is in operation.
Biofilter
The biofilters are complete and in operation.
Operations and Maintenance Building
The facility is complete and in operation.
Filter Support
This facility is complete and in operation.
Tertiary Filters
This facility is complete and in operation
UV Disinfection
Commissioning testing completed. Contractor is preparing the report to be submitted to
the State.
Recycled Water Pump Station
This facility is complete and in operation.
Wetlands Planting
The plants are planted and growing.
Site Landscaping
Maintenance of the plantings around the site continued during the month.
Polishing Wetlands
Plantings in place and growing. All ponds except Pond 10 are in service. Plantings in
Pond 10 require more time to grow before placing the pond in service.
Existing Chlorine Contact Basin
This facility is complete and in service.
3. Contract Changes
Twenty one change orders were processed in May and ten change orders were
processed in June with a total value of $152,531.00. Four hundred fifty change
orders have been executed to date with a combined value of $4,590,388.00. The
change orders greater than $10,000 executed during May and June are as follows:
c0
No. Description
Amount
422 Gate Modifications at Junction Box No. 2
$10,345.00
423 Purchase of Trees for West Access Road
$10,307.00
430 Life Ring Cabinets
$11,444.00
431 Concrete Conduit Protection at the West Access Road Entrance
$10,050.00
438 Installation of Thermal Mass Flow Meters
$10,013.00
439 RWPS 3W Supply Modifications
$11,477.00
445 Cypress Drive Sidewalk and Landscape Modifications
$14,093.00
The Contractor continues to negotiate change order pricing however, they have asked that
all change orders be issued unilaterally.
4. Field Orders
One new field order was prepared in May and three prepared in June. Two -hundred
seventy nine field orders have been prepared for the project. Of those, fifty seven remain
active with a total estimated value of $896,819.00. Active field orders for general
changes greater than $10,000 are as follows:
FO
No. Description
106 CCB: Addition of Drain Vault Float and Clarification on Heat Trace Controller
113 HVAC Modifications at Filter Support, Thickener & Screw Press
134 CCB Wash down System
145 Existing CCB Piping Modifications
146 EC Purlin Shims & PVC Spacers at Standing Seam Room
164 Ops. Building: Control Room Wiremold Circuitry
173 Ops Bldg: Canopy Hood Single Speed Motors
6
Amount I
$15,000.00
$10,000.00
$50,000.00
$30,000.00
$14,150.00
$16,198.00
$14,141.00
182 Additional Grading at RWSB — Build Up Petals
183 Waste Gas Flare Modifications
188 Tertiary Filters: Sample Feed to Turbidimeters
195 Mntnce Bldg: Addition of Smoke/Heat Detectors
200 CCB Paving/Grading Modifications
204 Entry Road Sidewalks
221 Motor Operated Gates in Fences
225 East Flood Protection Berm
227 24" Cleanout on 42" PWE Piping
234 Headworks Barscreen Enclosure Gas Monitoring
239 Light Pole and Enclosure Grounding
240 Motor Control Wiring Modifications
248 Replacement of Rotometers damaged due to freezing
251 Ops. Bldg.: HVAC Modifications to 19 -AC -01 in Electrical Room No. 1
269 Methane Digester Start up - Sludge Hauling and Gas Purge
271 Ponds B and C Berm Leaks
276 UV Commissioning Test Protocol
277 Methane Digester Mixing Pumps: Add Tee and ARV
278 Fencing at Polishing Wetlands Flow Splitter and Pump Station
Total Active Field Orders < $10,000
$34,812.00
$17,809.00
$12,533.00
$18,705.00
$91,321.00
$51,102.00
$10,000.00
$54,500.00
$17,358.00
$20,000.00
$20,000.00
$20,000.00
$15,418.00
$10,541.00
$34,297.00
$136,652.00
$30,000.00
$10,000.00
$20,000.00
$122,282.00
5. Testing
Remaining testing includes screw press performance testing, solids load out control valve
testing, submittal and review of aerator performance testing, submittal and review of the
UV commission testing, and submission of the UV commission testing to the State.
6. Anticipated Work for Next Month
Commissioning and Process Testing of the UV system will be completed and the data
will be submitted to the California Department of Public Health.
Review of the aerator performance test report.
Testing the solids load out control valves.
Working on punch list.
7
FIELD ORDERS
Total Cost of
Total May -June Active Active Orders
Field Orders Issued 279 4 57 $896,819.00
Total May -June
Value of Change Orders Executed in May -June 31 $152,531.00
Value of Change Orders Executed to Date 450 $4,590,388.00
Percent to Date of Original Contract 4.16%
WEATHER RELATED DELAYS
Days
Base Contract Allowance 40
Weather Related Days in May -June 0
Weather Related Days to Date 82
8
Received
To Date
May -June
Returned
Pending
First Time Shop Drawing Submittals (excludes
O&M Manuals)
911
0
911
0
Request for Information
1564
1
1564
0
C. M. Request for Information
270
0
270
0
FIELD ORDERS
Total Cost of
Total May -June Active Active Orders
Field Orders Issued 279 4 57 $896,819.00
Total May -June
Value of Change Orders Executed in May -June 31 $152,531.00
Value of Change Orders Executed to Date 450 $4,590,388.00
Percent to Date of Original Contract 4.16%
WEATHER RELATED DELAYS
Days
Base Contract Allowance 40
Weather Related Days in May -June 0
Weather Related Days to Date 82
8
Final Cleanup and Insulation of Piping
Painting Touch Continues Throughout the Site
dii
Polishing Ponds Planted and Ready for Service
10
Ellis Creek Water Recycling Facility
CONTRACT CHANGE ORDER TRACKING SHEET
11
Time
cc0 #
Description
Amount
(Days)
1
Time extension for additional soil sampling
0.00
8
2
Lime treatment at Ox Ditch & Secondary Clarifiers
125,000.00
3
Board up Farmhouse
3,385.00
4
Hay Stacker Relocation
493.00
5
Terrorism Insurance and Increased Earthwork
0.00
6
Meter in Temporary Recycled Water Pipeline
3,023.00
7
Temporary Power for Pond 1 Aerators
1,270.00
8
Pavement Repair on Cypress and McDowell
419,681.00
9
Conduit Encasement Coloring Agent
10
Delayed Caltrans Encroachment Permit
16,723.00
11
Trench Cut -Off Walls
12
Horizontal Aerators Extended Warranty Testing
0.00
13
Deletion of Prime Coat under AC Pavement
14
Replace PVC Sched. 40 with EB 20 Conduit in DB
15
Delete Lakeville Highway Access
40,000.00
16
Contract Time Extension for Weather Days 03-04106
0.00
38
17
Change Valve Types
0.00
18
Replace EMT conduits by MC cable @ O&M Bldg
19
Inverter Duty Motors at Oxidation Ditch Aerators
16,466.00
20
Aerated Lagoon and Pond 1 Modifications Milestone
0.00
21
Additional Striping and Loops on McDowell
13,747.00
22
Catch Basins Invert Changes
23
Oxidation Ditch Sump Modifications
24
Change Buried Conduits PVC GRS to PVC Sch. 40
25
Temporary Power to Existing Aerators 4 and 7
7,956.00
26
O&M Bldg: Ceiling & Wall Heights Rms
4,287.00
27
Provide Portable Generator Pads at Ponds
2,554.00
28
FS Bldg: Extend Conduit Stub -ups Beyond Ductbank
9,190.00
29
Headworks: Handrail Extension to Complete Deck
1,254.00
30
Pond 4 Aerator Temp Power
883.00
31
Aerated Lagoon: Reconnecting of Aerator No. 2
537.00
32
Unknown Utility at Pond 1 North Side
855.00
33
Ductbank Encasement with Reinforcing
24,884.00
34
Gun Safe for Storage of Bid Documents
2,410.00
35
S&C Pad Mounted Switch Additions
75,200.00
Time
cc0 #
Description
Amount
(Days)
11
36
Permanent Power Supply for Pond 1 Aerators
98,000.00
37
Temporary Fire Hose
851.00
38
Change material for Temporary Debris Collector
39
Chemical Tank Pads @ Filter Support Bldg
4,425.00
40
Disconnect Aerator No. 2 & reconnect Pond 4 Aerators
607.00
41
Delete Steel Steps in Manholes
42
Add 4" Butterfly Valve in Acid Digester
1,189.00
43
Delete Pre-Action Fire System @ Main Elect. Bldg
_ !
44
Headworks Influent Box Modifications
3,000.00
45
Transformer Pad at Restroom
9,498.00
46
Addition of Construction Joint at Oxidation Ditch Slabs
23,505.00
47
Change Conduits from PVC Rigid Steel to PVC Sch. 40
48
Reader Board & Geogrid placement @ Cypress/McDowell
6,000.00
49
Plant Control System PLC Architecture
50
Grit Pump Room Sump Pump Modification
1,326.00
51
PLC Enclosure Size for PLCs 2, 3 and 8
5,446.00
52
Additional Time Switches at O&M Bldg.
2,722.00
53
Extension for Pond 1 Aerators Milestone Date
0.00
54
Levee Repair at Berm Existing Ponds 8 & 9
289,279.00
55
Operations Bldg. Maintenance Window
1,022.00
56
In-Plant Pump Station Wall Penetration Details
2,807.00
57
Alignment of 42" RSG line to Headworks
4,208.00
58
Revision of Structural Joints at Headworks Facility
5,628.00
59
Pond 9 & 10 Levee Pothole
1,400.00
60
Add pipe for Future Pump Can @ RWPS
6,316.00
61
Home Inspection of Farm House
746.00
62
Alignment of 42" PWE line to Cell D Transfer Structure
8,171.00
63
Delete Locks on Motor Operated Overhead Coiling Doors
64
Dewatering of Pond 8 and Mitigated Wetland
3,488.00
65
UV System Programming
2,777.00
66
Septic Tank Removal at Farm House
739.00
67
Changes to Slide and Sluice Gates
11,177.00
68
PLC System Material for C Street Pump Station
14,915.00
69
PLC - 10 Analog Input Module
1,873.00
70
Change Storm Drain Pipe from RCP to CHDPE
71
Deletion of CMU Coating on non-occupied structures
72
Existing Utilities at West Access Road Entrance
8,543.00
73
Change Handrail for Polishing Wetlands Structures
6,965.00
74
Change SDR for HDPE Pipe Lines
c.^
75
Addition of waterstop in wall @ Filter Support Bldg.
1,330.00
76
Delete waterstop & starter walls @ HW, RAS PS, UV
Time
CCO #
Description
Amount (Days)
12
77
Re-Power Pond Aerators, Reconnect Aerated Lagoon
3,718.00
78
Contract Time extension for Weather Days 10/2006
0.00
1
79
Deletion of waterstop and starter walls at Tertiary Filters
u.
80
Add waterstop at Grit Pump Area of Headworks Structure
6,167.00
81
Fuel Tank Removal at Farmhouse
2,972.00
82
Revised Anchorage for Oxidation Ditch Aerators
40,941.00
83
Deletion of Integrated System Shop Testing (ISST)
0.00
84
Additional Dowels at Maintenance Bldg.
914.00
85
Replace Fuses at MCC 3A after PG&E power spike
1,706.00
86
Remove and replace disconnect switch P. Aerated Laqoon
2,919.00
87
Lower Invert Elevation for 42" RSG Line
18,726.00
88
Addition of Roof Hatch @ Main Electrical Bldg.
3,195.00
89
Filter Support Bldg: NG Connections and Valving
1,361.00
90
Chain Link Fence addition @ Farmhouse
725.00
91
Repair Irrigation Lines @ Kaiser
1,186.00
92
Demo of Spillway at Pond 10
12,109.00
93
Curb and Grading @ Filter Support Bldg
0.00
94
Irrigation System: Concrete Valve Boxes
2,393.00
95
Contract time extension for Weather Days 11/06
0.00
5
96
Mitigation Wetlands Drain
4,370.00
97
Additional vinyl sheets for Levee Repair @ berm Pond 8 & 9
5,498.00
98
Shoring @ Naval Trail
21,271.00
99
Extra excavation @ W Access Rd. for 12" 1W line
8,008.00
100
Replace SBS line @ Chlorine Contact Basin
5,936.00
101
Brush clearing @ Farm House
5,209.00
102
Relocate standby Generator @ CCB
2,005.00
103
Drywall Furring @ Elect Rm #2 in O&M Bldg.
1,630.00
104
Equipment for MCC-3 retrofit
25,360.00
105
Perimeter lighting switching @ Main Elec. Bldg.
1,795.00
106
Wiring for Time-Off Relay @ Wetlands Elec Bldg.
2,282.00
107
Changes to SCADA interface Boiler & PLC 3
3,549.00
108
Disposal of existing MCC 3 transformer
2,141.00
109
Contract time extension for Weather Days 12/06
0.00
7
110
Tree removal @ W Access Rd.
1,419.00
111
Deepening Pull Boxes @ Ox Ditch MCC Bldg.
11,540.00
112
Rebar modification @ Wetlands Pump St Deck Beam
2,187.00
113
Electrical Equipment Pads
9,018.00
114
Delete Catch Basins at W Access Rd.
1,746.00
115
Naval Bldg Lookout Area
3,000.00
116
Changes to TWE and PWE lines
0.00
117
Polishing Wetlands FSS: Add Hand Switch
3,444.00
Time
cC0 #
Description
Amount
(Days)
13
118
Engineering of Anchorage @ Oxidation Ditch Aerators
119
Replace Oxygen Probes @ Aerated Lagoon/Pond 1
13,411.00
120
Change Piping Material for Deionized Water Service
0.00
121
Filter Support Bldg: Relocation of 1W Line
4,568.00
122
Security Lighting at Farmhouse
1,200.00
123
Disposal of Asbestos Containing Pipe
2,087.00
124
Investigation and Disposal of FAA Building
20,512.00
125
Conduit addition @ Boiler Bldg.
15,780.00
126
O&M Bldg: Exhaust fans power supply & controls
34,440.00
127
Addition of Disconnect Switches @ Headworks
25,143.00
128
Level Transmitter addition @ Headworks
23,058.00
129
Contract Time extension Weather Days 01-02/07
7
130
Subgrade Improve & Pipe Encasement @ W Access Rd.
12,128.00
131
Additional Conduit for Fuel Leak Detection
2,714.00
132
HVAC Enclosure Modifications @ Ops Bldg.
8,014.00
133
Wiring of Spare I/Os
45,713.00
134
PLC Enclosure Size for PLC 5
7,823.00
135
Partial Payment for PLC Enclosures
0.00
136
Trench Backfill with Native Material
137
UV Bldg Top Slab Modifications
14,000.00
138
Ops Bldg: HVAC Electrical & Mechanical Modifications
2,854.00
139
24" Pumped Storm Drain Line Coverage
30,000.00
140
Metal Siding @ Main Electrical Bldg.
5,071.00
141
Contract Time Extension for Weather Days April 2007
1
142
Ops: Relocate HVAC duct transition @ Locker Rm Ceiling
878.00
143
Use of Native Material for backfill @ North & Middle Cluster
144
Recycled Water Storage Basin Size Increase
220,867.00
145
Outlet conduit replacement @ Existing CCB
1,260.00
146
Modify Rebar Expansion Joints @ Thickener Bldg
1,610.00
147
Modify Grating Seat @ Headworks Beam B-13
1,737.00
148
Added Space Heater for PLC 8 - RIO 1
1,803.00
149
Additional G2 Light Fixture @ Ops Bldg Lobby
2,013.00
150
Connection Grounding Bldg rebar @ MCC HW Bldg.
974.00
151
Relocate supply line fire riser @ maintenance Bldg.
3,027.00
152
Pipe material for 36" mixed liquor line @ 2ndary Clarifiers
14,271.00
153
Modifications HVAC Pads
9,562.00
154
Mod per PG&E Requiremnts to Main Power Supply
19,886.00
155
Addition of Wall Sleeves at Thickener Building
847.00
156
Reduce Deck Slab Openings @ Wetlands Pump Station
782.00
157
Wall Supports for Pony Wall at Laboratory
2,162.00
158
Concrete Encase HCS pipeline @ Headworks Structure
2,393.00
Time
CCO #
Description
Amount
(Days)
14
159
Convert Conference Rm into 2 Offices @ Ops Bldg.
8,351.00
160
Concrete Backfill around Screw Press Equipment Trench
1,588.00
161
Expansion Joint Rebar @ Headworks Grid Line 10
1,151.00
162
Standby Generator Connection @ Wetlands PS
13,527.00
163
Deletion of Rotameters @ Tertiary Filters
164
Blockouts for Ox Ditch Aerator Anchorage
1,022.00
165
Concrete Encase SD pipe under HWE pipeline @ HW
1,657.00
166
Temporary Power for Transformer @ Aerated Lagoon
28,343.00
167
Rebar @ Headworks Manual Bar Screen Embed
756.00
168
Subgrade Improvement for Wetlands PS Apron Slab
11,799.00
169
Screw Press Bldg Skylight Size Change
3,465.00
170
Additional 1/0 from Power Panel to PLC -9
2,887.00
171
Standby pump @ existing CCB during work @ Pond 10
44,000.00
172
Billing for Potable Water Usage on site through 4/4/07
1,552.00
173
Upgrade starters for Ox Ditch Aerator Motors
78,373.00
174
Blind flanges for future effluent line @ Aerated Lagoon
11,709.00
175
Remove rebar @ Ox Ditch Aerator Motor Block-outs
3,000.00
176
Modification of controls for Tertiary Effluent Bypass Valves
177
Communication between PLC -8 & Thickener PLC
2,032.00
178
Automated 1W Valve @ Recycled Water Storage Basin
46,267.00
179
Modification to HW Bar Screen Channels
6,130.00
180
Relocate Fire Pump Can @ RWPS
4,613.00
181
Add Effluent Conductivity Probe @ JB No. 2
9,680.00
182
Revise DB Routing @ Ferrous Chloride Area
2,463.00
183
Ventilation Alarms @ Boiler Bldg & Thickener Bldg
20,526.00
184
Anti Graffiti Coating @ O&M Bldg and Sound Wall
28,736.00
185
Deletion of Louvers @ HW Bar Screen Enclosures
186
Deletion of Combination Smoke Fire Dampers
187
Fire Rating Janitor Closet Door @ Ops
1,841.00
188
Brush clearing @ Farm House fire season 2007
3,186.00
189
Ops: CMU alignment & wall cap @ HVAC enclosure
1,826.00
190
Ops: addition acoustical ceiling P. electrical rm #1
3,125.00
191
Ops: framing details for Lobby
2,163.00
192
RWPS: modified floor drainage
15,107.00
193
Ops: beam seats in CMU wall pockets
10,067.00
194
Recycled Water Storage Basin Berm Modifications
+'
195
Double Containment System Modifications
90,172.00
196
Site Security Lighting Estimation Cost
10,364.00
197
Grading @ Mitigation Wetlands & RWSB
27,012.00
198
PG&E power connection @ W Access Rd.
55,335.00
199
UV Disinfection Light Pole Mounting Detail
7,027.00
Time
ccO #
Description
Amount (Days)
15
200
Ox Ditch Light Pole Mounting Detail
8,852.00
201
Existing CCB: power to New Chemical Metering Pump
8,588.00
202
Screw Press grating @ Flocculation Tank Opening
1,969.00
203
Anchorage of Diffuser Pipe Ponds 9 & 10
32,659.00
204
Acid Digester changed detail wall penetrations
4,286.00
205
Existing LPN panel in chemical bldg.
2,576.00
206
Revised Details @ RWSB
20,881.00
207
Ops: Deletion of Closet in Control Room
.:.
208
Ultrasonic level sensor mount @ Headworks
1,208.00
209
Mitigation Wetlands Drain — Permanent Installation
75,048.00
210
Ops Bldg: Plumbing Dwgs
29,571.00
211
Ops: Deletion of decking @ Mechanical Chases
1,719.00
212
Headworks: channel floor rebar modification
1,696.00
213
Ops: Furring Men's Restroom Urinal Wall
740.00
214
Informational Kiosks: Addition of 2" PVC 40 Pipe Sleeve
2,560.00
215
Screw Press: Modifications to Underslab Piping
2,607.00
216
Below Grading Coatings
72,507.00
217
Aerated Lagoon: Unknow utility @ 20" URW Alignment
5,225.00
218
Ops Bldg: Additional Window Clips
3,194.00
219
Silt Fence Repair
1,209.00
220
Ops Bldg: control rm. Backing & wood blocking
2,185.00
221
Ops Bldg: Modifying Welding Studs to 1/8" Tubing
5,293.00
222
Pond 10 Apron Slab: Over Ex, Fabric, and Rock
3,870.00
223
Addition of Solenoid Valve @ Recycled Water Surge Tank
5,095.00
224
Thickening Walls @ Ox Ditch Aerator Shafts
11,286.00
225
Relocate Receptacles @ Biofilter Mechanical Pad
3,286.00
226
Equipment Pad Modifications @ Screw Press
5,130.00
227
Footing Elevation @ Filter Support Bldg. Tank Farm
2,098.00
228
Relocation of Cell D Transfer Structure
5,162.00
229
Pipe Elevations & Drainage Swale @ Polishing Wetlands
1,938.00
230
Farm House: Plywood Cover @ Back Entry
756.00
231
Methane Digester construction joint location & piping
1,057.00
232
Ops Bldg: Icemaker Legs
893.00
233
Acid Digester: Overflow Piping Modifications
1,727.00
234
West Cluster: Sitework & Grading Change
277.00
235
Ops Bldg: Future access control conduit stub-outs
1,720.00
236
Ops Bldg: Interior lights & furring strips
2,292.00
237
Potholing & Excavation existing utilities @ CCB
42,606.00
238
Replace Farmhouse Roof
34,194.00
239
SCADA: TWAS sump level set points
1,682.00
240
CCB: Relocation of Ammonia Tank
17,176.00
Time
CCO #
Description
Amount (Days)
16
241
Add wire way in PLC 6 @ Existing Chemical Storage Bldg.
1,775.00
242
Replace Landscaping on Kaiser Property
2,690.00
243
Electrical Modifications @ UV Bldg.
47,188.00
244
Headworks: Rebar Detail @ Channel Wall Ends
1,625.00
245
Rebar @ Screw Press Bldg. Slab Extension
1,625.00
246
Tertiary Filter: 12 Inch Inlet Line
17,248.00
247
Ops: Modifications to Fume Hoods
;
248
Ops: Addition of Compressed Air @ Laboratory
22,641.00
249
Ops: Training Room Modifications
8,494.00
250
Emergency Repair Kit Deletion
251
Increase Cover Over 14 inch Foul Air Line
1,972.00
252
Headworks: Epoxy Coat Rebar @ Block-outs
20,579.00
253
Relocation of Mezzanine Column @ Screw Press
3,225.00
254
Additional Rebar @ Oxidation Ditch
1,348.00
255
Pipe Class Acid Gas & Methane Gas Pipe
256
Modifications to the Potable Water System
105,856.00
257
Thickening Bldg piping modifications
764.00
258
Catch Basin grating modification @ W Access Rd. culvert
4,950.00
259
Headworks FRP grating support @ Gate location
2,219.00
260
Digested Sludge Storage Tank: Piping Modifications
4,828.00
261
Modifications to Analyzer Enclosures
9,315.00
262
Additional Conduits & Wires Miscellaneous Areas
41,620.00
263
Planting modification @ West Access Rd.
2,328.00
264
Install Clapper Rail Trail Gate
2,687.00
265
Amphitheater seating next to Polishing Wetland Cell D
29,577.00
266
Ferrous Chloride- revised electrical & pump pad
24,552.00
267
Chip Down Top of Wall @ Filter Support
3,411.00
268
Conduits for Future Mixer @ CCB
11,320.00
269
Modifications for Interfacing between PLC 6 and PLC 11
5,800.00
270
Headworks Deck Slab Falsework
26,026.00
271
Dewatering of Pond 8
20,157.00
272
Pressure Gauges @ Wetlands Pump Station
4,110.00
273
Irrigation Changes @ Point of Connection
24,050.00
274
Filter Support: 4" chemical drain elevation
872.00
275
Unknown Utilities @ Site Entrance
4,205.00
276
Mitigated Wetland Planting
277
Changes & Additions to 3W System @ Ox Ditches
34,716.00
278
Garbage Bin Structure
25,644.00
279
Relocate Veolia Materials @ CCB
788.00
280
Wetlands PS Portable Eyewash Station
5,217.00
281
Temporary Irrigation Connection to Schollenberger
2,255.00
Time
ccO #
Description
Amount (Days)
17
282
Partial Deletion of Planting @ Polishing Wetlands
283
Change NEMA Rating for Pull Boxes @ Ox Ditches
284
Delete Trail Material W Polishing Wetland Cell D
285
Equipment Pad Modifications @ CCB Bldg.
26,412.00
286
Parapet Detail @ Ops Bldg Lobby
18,746.00
287
Relocate Potable Water Riser @ 1W Pump Station
3,299.00
288
Dewatering Pond 7 for TWIS
14,419.00
289
Additional work for Farmhouse Roof Replacement
41,819.00
290
Material for Clay Liner in RWSB
13,820.00
291
Ops Bldg 1 hr Fire Rating
40,885.00
292
Maintenance Bldg: 2hr Fire Rating
1,282.00
293
Relocate Tie-In to Potable Water Sys @ Cypress Dr.
8,042.00
294
Changes to Gates & Operators @ W Access Rd.
295
Ellis Creek Clean Up
8,395.00
296
Analog Input Module for PLC 11
2,766.00
297
Addition of the Polishing Wetlands Pump Station
415,000.00
298
Natural Gas Connection & Metering Pad
18,435.00
299
Additional Digital Input Points PLC 9
2,335.00
300
Weather Monitoring Station
24,976.00
301
Modifications for future Polishing Wetlands Pump Station
16,899.00
302
Addition of Geofabric @ East Access Rd. Ponds
8,740.00
303
Outlet Cutouts in Backsplash @ Ops Laboratory
1,908.00
304
Ops Bldg: Exhaust Fan Drainlines
7,662.00
305
PVC pipe for Plant Drain Piping
306
Drainage Swale @ W Access Rd.
307
UV Stair Grating Changes
308
UV Channel Blockouts for Wireways
309
CCB: Welding of 42" Pipe Connections
27,142.00
310
Trail Connection @ Schollenberger Park
13,167.00
311
Waste Gas Flare Pedestal
2,366.00
312
Relocation of cabinets in Ops Bldg.
753.00
313
Support for folding Partition in Ops Bldg.
830.00
314
Deepen Fuel Sump @ Generator
3,855.00
315
Operation Bldg: Fire Sprinkler Riser
25,728.00
316
Glass Lined Ductile Iron Pipe
97,613.00
317
Wetlands PS Mixer Mounting Bracket
1,798.00
318
Uninterruptible Power Supply @ Ops Bldg.
24,754.00
319
Clarifier 1 & 2 Light Post Mounting
3,060.00
320
Transformer Relocation @ Existing CCB
6,187.00
321
Ops Bldg: Mudroom Skylight Framing
5,192.00
322
Wetlands Pump Station Interim Milestone
0.00
Time
CCO #
Description
Amount (Days)
18
323
Analyzer Enclosure @ Outfall Structure
11,080.00
324
Additional Grating @ Biofilter Damper Boxes
2,747.00
325
Additional Valves for Hydronic System
762.00
326
Modifications @ Flow Control Structure C-2
r `:
327
Change Manhole & Catch Basin Elevation @ South Cluster
1,923.00
328
Modifications to the Existing Outfall Structure
12,254.00
329
Anti Graffiti Coating @ Garbage Bin Structure
2,389.00
330
Instrumentation and Control Modifications @ Existing Plant
58,658.00
331
Miscellaneous Extra Work @ Junction Box No. 2
49,264.00
332
Miscellaneous Extra Work @ Existing CCB
12,655.00
333
Paint Flashings and install Spark Arrestor @ Farmhouse
2,860.00
334
Temperature Detection for Recycled Water Pumps
19,598.00
335
Raise Top of Electrical Pull Box @ Headworks
3,391.00
336
Modifications to Biosolids Load -out @ Screw Press Bldg.
266,077.00
337
Rerouting of Electrical Conduits @ Headworks Deck
46,510.00
338
Miscellaneous Instrumentation Modifications
5,366.00
339
Reverse Service Generator Plug
4,699.00
340
Submersible Sump Pump Control Panels
2,445.00
341
Flow Meter Transmitters @ WPS
1,597.00
342
Additional Fence & Gate @ Existing Farmhouse
5,299.00
343
Install pressure gauge @ Tertiary Filter Hypochlorite panel
1,684.00
344
Widen Sidewalk @ Filter Support Bldg.
821.00
345
Anti Graffiti Coating @ W Access Rd. Public Restroom
3,920.00
346
Screw Press Parapet Wall Height
2,658.00
347
Handrail Installation @ Ox Ditch Weir Gates
7,798.00
348
Bond and Insurance Over -Billing;:.
r
349
Drains for AC Unit & Backflow Preventers @ Ops Bldg
2,185.00
350
Delete wires @ Headworks & add wires @ PWFSS
0.00
351
Added Sample & Drain Lines @ JB 2
4,127.00
352
Additional Blackout Shades @ Ops Bldg.
885.00
353
Relocation of Drain Lines @ Biosolids Load -out Slab
10,201.00
354
Deletetion of Vinyl Coating- chemical pump pad @ CCB
355
Ferrous Chloride Line Encasement under Equip Pad
2,608.00
356
Power Supply to Current Tranducers @ Ox Ditches
3,999.00
357
Level Switches @ RWPS
5,081.00
358
Contract Milestones O&M Bldg Occupancy / SCADA Readiness
0.00
359
22" Foul Air Pipe Encasement
11,291.00
360
Shoring @ JB 2
48,500.00
361
Dewatering @ JB 2
28,000.00
362
Analyzer Changes & Minor Changes to Instrument Index
23,495.00
363
Sprinkler Repair at West Entrance Road
1,585.00
Time
ccO #
Description
Amount (Days)
19
364
Modification of Light Pole Bases @ Tertiary Filters
693.00
365
Stair Landing @ Tertiary Pump Station
1,001.00
366
Acid Equipment Pad: Ferroud Chloride Line
1,207.00
367
RWPS Hydropneumatic Tank Mechanical
1,543.00
368
Change Diffuser Pipe Supports @ UV
2,448.00
369
Fire Alram System Modifications
370
Site Keying of Permanent Cores
2,745.00
371
Sediment Trap Modifications
12,478.00
372
Additional supports for 24" Mixed Liquor Return Pipes
7,876.00
373
Modification of 1W Fill Line @ RWSB
2,357.00
374
Deletion of Safety Ropes and Floaters @ Ox Ditches
375
Changed Material for Sludge Pressure Relief Lines
376
Electrical and SCADA changes @ Digester Area
7,716.00
377
Addition of Bases for Bollard Lights @ O&M Bldg.
9,176.00
378
Sidewalk Elevation Changes @ MCC 9
3,518.00
379
Reroute conduits @ Filter Support Tank Farm
2,870.00
380
Repair Pipe between Ponds 2 & 3
4,542.00
381
Reroute conduits/wires for Gas Heater Thermostats
4,436.00
382
Changes to Concrete Drain Ditches @ WAR
7,286.00
383
Conduit addition @ TWIS
3,053.00
384
Extend slab @ Polishing Wetland Flow Split Structure
2,661.00
385
Change Transformer Pad @ W Access Rd. Restroom
2,096.00
386
Sanitary Sewer Manhole Elevation @ WAR
6,593.00
387
HCS Injection Mounting Plate at the RWPS
998.00
388
MEB Exterior Fixture Mounting
5,301.00
389
RWPS Truck Fill Station
11,231.00
390
House Keeping Pads in Filter Support Building
5,812.00
391
West Access Road Sidewalk Removal
11,051.00
392
Water Meter Box Modifications - Location and Valves
11,349.00
393
Tertiary Filter HCS Diffusers
9,168.00
394
Conduit for Future Alum Tank at Filter Support Building
1,295.00
395
2008 Brush Clearing at Farm House and Hay Stacker Disposal
3,887.00
396
Raise Pull Box Lid @ Filter Support
3,694.00
397
Fire Pump Instrumentation Modifications
9,534.00
398
Pipe Elevations @ Sludge Storage Tank Equipment Pad
979.00
399
Additional Pressure Regulator & Gauge @ Outfall Bldg.
2,185.00
400
Raise Pull Box Lid @ Storm Water Pump Station
3,301.00
401
Modifications to FBA Piping @ Filter Support Bldg.
2,232.00
402
Modified Handrail Anchorage @ Headworks Structure
10,012.00
403
Biosolids Loadout Slab Modifications @ Screw Press
28,218.00
404
Raise Valve Box Lid @ Existing CCB
2,790.00
Time
CCO #
Description
Amount (Days)
20
405
HCS Panel Modifications
4,632.00
406
Addition of Natural Gas Regulators @ Process Bldg.
4,050.00
407
Project Completion Time Extension
0.00 15
408
Revised Amphitheater Grading
16,231.00
409
Ops Bldg Electrical Room Heating and Cooling
6,439.00
410
Sand Trap Addition @ Tertiary Filters
1,762.00
411
Overflow Weir Modifications @ Headworks Structure
9,038.00
412
Air Gap Tank Coating @ 1W/2W Pump Station
9,970.00
413
Modify Strainer Drains & Check Valve @ RWPS
2,995.00
414
Exit Routing Signage @ Ops & Maintnce Bldg
1,861.00
415
Irrigation Connection at Existing Ponds
10,764.00
416
Methane Gas Pipe change @ Digested Sludge Storage Tank
3,724.00
417
Piping modifications in Analyzer Enclosures
6,916.00
418
Pressure Relief Vent change @ Wetlands Pump Station
4,320.00
419
Additional Drain Groove @ the Ferrous Chloride Area
1,607.00
420
Screw Press FRP Ducts and Crane Rail Conflict
2,852.00
421
Gravity Belt Thickener Reprogramming
4,705.00
422
Gate Modifications at Junction Box No. 2
10,345.00
423
Purchase of Trees for West Access Road
10,307.00
424
Change Level Ball Floats in Chemical Containment Areas
3,348.00
425
Modifications to Influent Sampling at the Headworks
2,883.00
426
Power Supply for Local Control Panel in Screw Press Buildinq
1,357.00
427
Change Light Pole Height at UV Structure Bridge Crane
657.00
428
Reroute 3W Line at Boiler Building
2,426.00
429
Rewire and Retag Valves at the Tertiary Effluent Meter Vault
616.00
430
Life Ring Cabinets
11,444.00
431
Concrete Conduit Protection at the West Access Road Entrance
10,050.00
432
Pipe Modifications at Recycled Water Pump Station
3,462.00
433
Gravity Belt Thickener Spray Water Source Modification
769.00
434
Sidewalk Modifications at the Ferrous Chloride Area
752.00
435
Install Check Valve at Fire Pump Enclosure
1,483.00
436
Grit Classifer Speed Switch Power
3,679.00
437
Maintenance Bldg: Fire Rating for Door #1951
4,235.00
438
Installation of Thermal Mass Flow Meters
10,013.00
439
RWPS 3W Supply Modifications
11,477.00
440
Power to Rollup Door @ the MEB Bldg.
5,973.00
441
Ops & Maintenance Bldg. Green Roof Irrigation
5,537.00
442
Ops Bldg. Server Rack Size Change
8,045.00
443
Clarifier Scum Pump Wire Sizing
5,078.00
444
UV Disinfection UPS Enclosure Location Change
3,127.00
445
Cypress Drive Sidewalk and Landscape Modifications
14,093.00
Time
CCO #
Description
Amount (Days)
21
446 Reduction in Spare Filter Sand ..� `
447 Screw Press Bldg. Two Speed Fan Conductors 2,684.00
448 Barscreen Programming Change 7,943.00
449 Ops Bldg. Lab Epoxy Countertop Modifications 2,749.00
450 RWPS Control Schematic Modifications 1,374.00
CHANGE ORDER TOTAL: 4,590,388.00 82
Contract Amount: 110,329,000.00 1278
Percent Change Orders: 4.16%
Totals: 114,919,388.00 1360
Total Additive Change Orders
Percentage of Contract Amount 5.07%
Total Credit Change Orders
Percentage of Contract Amount 0.91%
Contract Substantial Completion Date 4/9/09
Current Substantial Completion Date 6/15/09
22
nrlu R"'I EMY Fady Tnt�of "'0' zMe 200a
5 0 X 0 jrd, J J A
N D M J F A M MM M N D M
J J A S 0, , D J F A J J A S 0 J. F , 4 m• i "i
Dur Mr Stork rIH'jh pomp Ftmd I A M P , . .
r"A VC� *WU,:IIUL tO P 40CLLU
T 7 F. On 7 -9
K7' ?�I
P[WHUST5 rOI;RFCM%'F, MI !W M VS
AR L V CC C LPAPC Y
S.UnSTANTAL COMPUTIGN jf7.PqMACT - Vl',NIClb
"SOLITH "M- C04NEEMON 77 SCHOLLEASERGFF. 13°T,*5
# HORIZFJV I AL TYM EAUSH AERATOR LAUMIN 5
7REATMENTYJETLAND CrjWSTPU4TIGN4PCN:I 91 3-29-5bw
WC17 OIL, 5L;A4A 2'AQ PRICE' MCPERATIUMAL TESTINC4
N.X RHP, r. WFTI ANO AY C.!'-TCAE'4 205. o
4 EW4ER ML.AYq
.7 i !).,>FAYW,
. . .. ..... ....... .........
SIT'F, 4PR7KI MD I F,,
nNZ SITE U "D vxr-TLAws
rIMAL SIE 30UP I
F INAL;�R-k L AES,
YARD DUCMMA WAT14
EI s Creek Water Recycling Fachty April 2009 Schedule Rc
23
. . . ... ... ... ..
ulq KIM Early Eiamj Intal, 2905
Flwt' :,F Ai W J I A 8!0� N 0 j r, im A MIJ, J AJS 0 N Dj r,m; A V J 4 A 0 H p j F m A v
SL'%n Fl�"i
UPECOWARY CLAPNFIEK X2
Pi ELE,.-.t. SLOG 157'Ati GVC
IM
ilWl�itilf` STAi
PLItAF1 STA71ON
% If
Fl,,'�)'PL 'T 5
Ct AP�ML W I M ICT
3ECctDR E FF,
LUENTJMcTIGNBOX
YAP.D "WZvMAW MIDDLE
m7cli #1
OAWIDW MICH 02
0jr,
X 9&YICj'4 DTCHli 41 ArXW,
�o 1;,r I
WAS i 1.r.A710"
'i,
',Xfad ION b' TCH i LO YJ 8PL4 9 rP.UC' UAL
YARD DUCTSANK'WEST
ft WINFFUTION
UPI"i BUILONO
PF, r' = E U Wiii R PI 'r UP F7ATl IN
Qs1�1,O 6A I
RF WA'r FR 5MWF R AR I N
24
r3fig Rftffi FAdF FAVIV V, TwAl =5 zwsS 1 F M A 207 2008 Z:
Dtf ouf 5"TI F'"ish QGrm Flom °.0 N n i F PA, A M J A
J ,�, q 0, N 0 J V M F M 4 4 A aA r ., M J J A, S.: I,) N D J! F_ M A
MCKLED WATFR WCC S''{ 11,111745W 0M
�f3
TERrARY F.FFLUrtoT t3ErFlR VAULT
50WARY MWER LIFT ST47ION
1w Pupop e-,Tcnot-)
YARn MAUSAY'K 100H
-1 �ce I I .17A
WADNV0rK9
STORM Vk ATER PAI P STATICA
mr-LANT AMP STAT92N
TP.H;K4iNLR OULDING
_A 4 BOILER _UCj aLoo
Rms's il;owmi
A DI,
-%VT1° 14F rg(3F.I;TrR
rmmm. CHLORME AREA
S'PTAGE PECOMNIGSTATM
'AASTF QAS FARE
ft q P Cq A .14 e
25
crip Rom Early P. rnw - 2DO5 2007 2DDB,, 2009,----
5i11P,N D�J F M, A M, J J A S,b V, A, M J 4 .5. t1 0 J M A M J J A % 0,74, D J F V A, M J J
- YARD DUCT&ANN PONDS
- POND' I
A7pAfKr VA I L,%f4c#s PUMP 0A.TsLV4
WIT"40"i I1-'4vjRD,& BUILDING IfFt)INV$l
r,
AERATED I A�'Iwm
tel ti
C�LORINE CZNTAIT WS IN Wkl-ITING'�
UV CAIWa. 9b Jw, L, U
QOX,02
OUTFALL S 5TRUCTURL
PARIa WORK
POND 9
;0 C TA T-," O:Xr I 1:f5
NOW 10
YARD fjUCTU&Nk O;L ILA14W
5
F4
apmmn ®V
Inp;�01�A
A B'.' -L: INA JN
26