RECOMMENDATION
It is recommended that the City Council adopt the attached Resolution Accepting Completion of
the American Asphalt Repair and Resurfacing Company, Inc. Contract for the Various Streets
16/17 Project.
BACKGROUND
A pavement management system is used to evaluate road conditions in the City and prioritize
maintenance and rehabilitation projects. Priority streets are cross - referenced with the City's other
street maintenance projects and pavement crack sealing program, development projects, and
proposed PG &E and outside utility work to endeavor to assure that new or nearly new pavement
will not be impacted. This project used micro surfacing as a cost effective alternative to surface
grinding and overlay as has been done more frequently on projects such as Petaluma Boulevard
and Madison Street. To reduce costs, pavement cracks were sealed by City crews within all the
project limits. In the past, this work has typically been done by the contractor at a higher cost.
The project included portions of Lakeville Street, South McDowell Boulevard and Ely
Boulevard South, and change order work at the Petaluma Airport and Ellis Creels Water
Treatement Plant as shown on Attachment 2. These streets were selected to provide the most cost
effective improvements for the entire pavement system and to provide the most benefit to the
traveling public. To remain compliant with the Americans with Disabilities Act (ADA), twenty -
three new curb ramps within the projects limits were installed.
The proposed action meets Council Goal: "Plan for and implement priority capital projects as
funding permits."
DISCUSSION
Two change orders were included in the project to micro surface Executive Drive and Sky Ranch
Drive at the Petaluma Airport as well as the access road in and around the Ellis Creek Water
Treatment Facility ( ECWRF). This work was outside the geographic scope of the contract, but
the type of work was identical to the original contract work. It was to the City's advantage to
approve these change orders to avoid a delay of the pavement maintenance until spring of 2018,
which would allow further pavement degradation and to benefit from an existing contract with
favorable unit prices. Since both the Airport and the ECWRF have adequate funding within their
operating budgets to fund the respective work, it was recommended to include this work into the
project to secure the competitive bid prices and get the work done this year. The project was
managed and inspected by Public Works and Utilities engineering staff.
The final construction contract cost is $692,669.21, which includes two change orders totaling
$99,758.89. The two change orders are $55,569.50 to micro surface the Petaluma Airport and
$44,189.39 to micro surface the ECWRF. All overruns and underruns of estimated unit quantities
added up for an overage of $26,222.82 based on the quantities that were actually used. There are
no disputed claims and the project was completed satisfactorily without any significant incidents.
FINANCIAL IMPACTS
Council approved a project budget of $726,000, which was funded by the street maintenance
operating budget. An additional $55,569.50 in the Airport operating budget and $44,189.39 in
ECWRF operating budget is required and will increase the total project to $807,669.21.
Uses
Contract
Award
Contract Acceptance
Design
$ 45,000.00
$ 5,000.00
Legal
$ 0
$ 0
Planning/Environmental
$ 0
$ 0
Construction Contract
$566,687.50
$592,910.32
Change Orders
$ 0
$ 99,758.89
Construction Management
$ 65,000.00
$ 65,000.00
City Furnished Materials
$ 0
$ 0
Project Contingency
$ 44,312.50
$ 0
Administration
$ 2,000.00
$ 2,000.00
CIP Overhead
$ 3,000.00
$ 3,000.00
TOTAL
$726,000.00
$807,669.21
Funding Sources
Street Maintenance Fund
$726,000.00
$707,910.32
Airport Hanger Repair budget
$ 0
$ 55,569.21
ECWRF CIP
$ 0
$ 44,189.39
TOTAL
$726,000.00
$807,669!.21
2
It is recommended that the project budget be amended and the transfer of funds for a new revised
budget be authorized in the next budget adjustment process. Unused funds will be returned to the
Street Maintenance Fund upon project closeout.
ATTACHMENTS
1. Resolution
3
Attachment 1
RESOLUTION ACCEPTING COMPLETION OF THE
AMERICAN ASPHALT REPAIR AND RESURFACING COMPANY, INC. CONTRACT
FOR THE VARIOUS STREETS 16/17, PROJECT NO. C67501714
WHEREAS, in accordance with Section 68 of Article X of the City of Petaluma Charter,
Section 20162 of the California Public Contract Code and other applicable law, the City of
Petaluma solicited bids for the Petaluma Complete Streets project ( "Project "); and
WHEREAS, bids for the Project were opened on April 7, 2017, in accordance with
California Public Contract Code Section 4104.5 and other applicable law; and
WHEREAS, the apparent low bid for the Project was the bid of American Asphalt
Repair and Resurfacing Company Inc. in the amount of $566,687.50; and
WHEREAS, by Resolution No. 2017 -057 adopted April 7, 2017, the City Council of the
City of Petaluma found the bid of $566,687.50 for the Project to be the lowest responsive bid and
awarded the Project to American Asphalt and Repair and Resurfacing Company, Inc. in the
amount of $566,687.50 conditioned on American Asphalt and Repair and Resurfacing Company,
Inc. timely executing the Project contract and submitting all required documents, and authorized
and directed the City Manager to sign the Project contract on behalf of the City; and
WHEREAS, the following change orders affecting the Project amount have been
approved:
Change Order Number Description Amount
CC0#1 Airport Micro surface $55,569.50
CCO #2 Ellis Creek Micro surface $44,189.39
Total Change Orders $99,758.89
; and
WHEREAS, the final construction contract amount as amended including all change
orders, overruns, and underruns is $692,669.21 and is within the approved project budget; and
WHEREAS, City staff have inspected the Project and determined that it has been
completed in accordance with the contract requirements subject to the Contractor's continuing
warranty and other obligations pursuant to the contract; and
WHEREAS, based on the foregoing, staff recommends acceptance of the Project on
behalf of the City.
11
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Petaluma
as follows:
1. Authorizes the City Manager to include the transfer of $55,569.50 from the Airport
Hanger Repair budget 6100.61300.54270 to the project budget for the Various Streets
16/17, Project No. C16101303 in next scheduled mid -year budget adjustment.
2. Authorizes the City Manager to include transfer of $44,189.39 from the ECWRF CIP
No.C66501305 -30600 to the project budget for the Various Streets 16/17, Project No.
C 161013 03 at the next scheduled mid -year budget adjustment.
3. The contract entitled Various Streets 16/17, Project No. C16101303 with a final
construction contract amount of $692,669.21 is accepted as complete subject to the
Contractor's continuing warranty and other obligations pursuant to the contract.
4. The City Clerk/Recording Secretary is hereby authorized and directed to file a Notice of
Completion concerning the Project with the Sonoma County Clerk's Office within ten
(10) days of the date of this Resolution.
5. Staff is hereby authorized and directed to release all undisputed retention not subject to
pending change orders within sixty (60) days of the date of this Resolution and in
accordance with the terms of the Project contract, the Petaluma City Charter, California
Public Contract Code Section 7107 and applicable law.