HomeMy WebLinkAboutStaff Report 4.H 04/16/2018DATE: April 16, 2018
TO: Honorable Mayor and Members of the City Council through City Manager
FROM: Da St SCE — Director, Public Works & Utilities
Jef uts an, P.E. — Senior Civil Engineer
SUBJECT: Resolution Authorizing Award of Contract for the Pavement Restoration 17/18
Project to American Asphalt Repair and Resurfacing Company, Inc.
RECOMMENDATION
It is recommended that the City Council approve the Resolution Authorizing the Award of
Contract for the Pavement Restoration 17/18 Project to American Asphalt Repair and
Resurfacing Company, Inc.
BACKGROUND
The Street SaverTM pavement management system is used to evaluate road conditions in the City
and prioritize maintenance and rehabilitation priorities under a regional MTC program. Priority
streets are cross-referenced with the City's other street maintenance projects, City's pavement
crack sealing program, development projects, and proposed PG&E and outside utility work to
assure that new or nearly new pavement will not be impacted by other planned projects. Streets
proposed for rehabilitation are clustered to improve efficiency for the Contractor and provide the
most cost effective pricing.
The proposed action meets Council Goal: "Plan for and implement priority capital projects as
funding permits."
DISCUSSION
This project will utilize high volume slurry seal, asphalt dig outs, and pavement overlay
methods. To reduce contract costs, many of the pavement cracks were sealed by City crews
under its preventative maintenance program.
The Americans with Disabilities Act (ADA) requires that local governments ensure that persons
with disabilities have access to the pedestrian routes in the public right-of-way. Under ADA law,
when a street, roadway, or highway is altered, compliant curb ramps are required where
pedestrian walkways intersect with the altered street. A roadway alteration in this project
includes overlays. For that reason, 23 new curb ramps will be installed within the project limits.
The project is partially funded by Senate Bill 1, which is known as the Road Repair and
Accountability (RMRA) Act of 2017, to address basic road maintenance, rehabilitation, and
critical safety needs on both the state highway and local streets and road system. On October 2,
2017, Resolution 2017-156 N.C.S. approved the proposed project list for RMRA and revised the
project budget.
High Volume Slurry Seal treatment is a maintenance measure to extend the life of a street by
sealing and protecting the road surface, improving drainage and road friction. Seal coat type
applications are typically used on roads in reasonably good condition. This work will be funded
by approximately $200,000 from the existing CIP project 1651602, entitled Downtown ADA
Improvements. The remainder of the project is funded from CIP C1610823, entitled Pavement
Restoration.
The project includes the following streets, as shown on Attachment 2
4th Street
D Street
B Street
Grind and Overlay
6th Street
Liberty Street
D Street
Grind and Overlay
Adrienne Drive
Kresky Way
Lindberg Lane
High Volume Slurry Seal
Albert Way
McGregor Avenue
Weaverly Drive
High Volume Slurry Seal
Atlantic Court
Lombardi Avenue
End
High Volume Slurry Seal
B Street
Petaluma Blvd S.
El Rose Drive
High Volume Slurry Seal
Carlin Court
Ramona lane
End
High Volume Slurry Seal
Corona Road
Hwy 101
McDowell Blvd S.
High Volume Slurry Seal
Grant Street
I Street
Mountain View Ave
High Volume Slurry Seal
I Street
Petaluma Blvd S
City Limits
High Volume Slurry Seal
Keller Street
Western Avenue
A Street
Two Part High Volume
Slurry Seal
Kresky Way
Stuart Drive
Lindberg Lane
High Volume Slurry Seal
Liberty Street
Washington Street
6th Street
Two Part High Volume
Slurry Seal
Lindberg Way
Saint Francis Dr
McDowell Blvd S.
High Volume Slurry Seal
Lombardi Avenue
Saint Francis Dr
Lombardi Court
High Volume Slurry Seal
Madison Street
Arlington Drive
Lakeville Street
High Volume Slurry Seal
McGregor
McDowell Blvd S.
Stuart Drive
High Volume Slurry Seal
McKenzie Avenue
McDowell Blvd S.
Stuart Drive
High Volume Slurry Seal
Olive Street
I Street
Mountain view Ave
High Volume Slurry Seal
Ramona Lane
Nucklin Street
Saint Francis Drive
High Volume Slurry Seal
Regina Court
Ramona Lane
End of CDS
High Volume Slurry Seal
Reynolds Drive
Kresky Way
Marian Way
High Volume Slurry Seal
S. McDowell Blvd
Ext
Lakeville Hwy
Bridge
High Volume Slurry Seal
St. Francis Drive
Lindberg lane
Lombardi Avenue
High Volume Slurry Seal
Stuart Drive
Kresky Way
McKenzie Avenue
High Volume Slurry Seal
Teresa Court
Ramona Land
End of CDS
High Volume Slurry Seal
Weaverly Drive
Ely Boulevard S.
McDowell Blvd S.
High Volume Slurry Seal
2
The construction plans and specifications were prepared by engineering staff and a Notice
Inviting Bids was advertised on January 18, 2018. Four (4) bids were received as follows:
Name of Bidder Base Bid
American Asphalt and Concrete, Inc. $ 1,032,097.07
Intermountain Slurry Seal $ 1,075,235.50
Team Ghilotti Inc. $ 1,097,928.93
Coastside Concrete $ 1,103,248.47
The lowest responsible and responsive bidder, American Asphalt Repair and Resurfacing
Company, Inc., has performed similar projects throughout the Bay Area and possesses a valid
Class A California Contractor's License, #439591, which allows American Asphalt Repair and
Resurfacing Company, Inc. to perform the work. It is recommended that Council adopt the
resolution awarding the contract to American Asphalt Repair and Resurfacing Company, Inc.,
the lowest and responsive bidder, in the amount of $1,032,097.07
Construction is scheduled to begin in May 2018 and to be completed by September 2018.
Construction management and inspection services will be conducted by City staff with assistance
by an outside consultant for material testing.
FINANCIAL IMPACTS
The project is funded from the Pavement Restoration 17/18 Project (C16101823) with a current
budget of $1,091,124 and the Downtown ADA Improvement Project (C16501602) with a current
budget of $200,000.
The following is a breakdown of the budget for the project:
Uses
Project Budget in
CIP
Revised Project
Budget
Planning and Environmental
$
2,000
$
1,000
Design (City Staff)
$
25,000
$
45,000
Legal Services
$
1,000
$
1,000
Administration
$
2,000
$
2,000
Construction Contract (low bid)
$
1,141,124
$ 1,032,097
Construction Management & Inspection
$
55,000
$
70,000
Contract Contingency
$
62,000
$
138,027
CIP Overheads
$
3,000
$
2,000
Total
$1,291,124
$1,291,124
Funding Source
Street Maintenance (RMRA- SB 1)
$
341,124
$
341,124
Utility Pavement Fees Water
$
435,000
$
435,000
Utility Pavement Fees Sewer
$
315,000
$
315,000
CIP C16501602
$
200,000
$
200,000
Total
$1,291,124
$1,291,124
3
ATTACHMENTS
1. Resolution
2. Location Map
Attachment 1
RESOLUTION AUTHORIZING THE AWARD OF CONTRACT FOR
THE COMMUNITY CENTER REHABILITATION PROJECT TO
AMERICAN ASPHALT REPAIR AND RESURFACING COMPANY, INC.
WHEREAS, in accordance with the City of Petaluma Charter and Municipal Code,
California Public Contract Code Section 20162 and other applicable law, City staff prepared
construction bid documents and solicited bids for the Project; and
WHEREAS, the project was bid on January 18, 2018, and four (4) bids were received
and opened on February 8, 2018 in accordance with applicable law; and
WHEREAS, the lowest responsible bid for the Project was submitted by American
Asphalt Repair and Resurfacing Company, Inc. from Hayward, CA for $1,032,097.07; and
WHEREAS, staff has determined that American Asphalt Repair and Resurfacing
Company, Inc., bid satisfies the bidding requirements for the Project; and
WHEREAS, American Asphalt Repair and Resurfacing Company, Inc., possesses a
valid California Contractor's License, Class A, #439591 that allows American Asphalt Repair
and Resurfacing Company, Inc. to perform the work for the Project; and
WHEREAS, the Project is categorically exempt pursuant to California Environmental
Quality Act ("CEQA") and Title 14, the California Code of Regulations ("CEQA Guidelines"),
Section 15301, because the project consists of repair and maintenance to an existing public
street.
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Petaluma
hereby:
1. Approve the revised project budget for the Pavement Restoration 17/18 Project.
2. In accordance with the City of Petaluma Charter and Municipal Code, California Public
Contract Code Section 20162 and other applicable law, waives any and all non-
conformance in the bid of American Asphalt Repair and Resurfacing Company, Inc. for
the Pavement Restoration 17/18, Project No. C16101823, finds the bid of $1,032,097.07
to be the lowest, responsive bid and further finds that American Asphalt Repair and
Resurfacing Company, Inc., is the lowest responsible bidder.
3. Awards the contract for the Pavement Restoration 17/18, Project No. C16101823 to
American Asphalt Repair and Resurfacing Company, Inc., in the amount of
$1,032,097.07, the amount of the lowest responsive bid, conditioned on American
Asphalt Repair and Resurfacing Company, Inc., timely executing the project contract and
submitting all required documents, including but not limited to, executed bonds,
certificates of insurance, and endorsements, in accordance with the project bid
documents.
6. Directs staff to issue a notice of award American Asphalt Repair and Resurfacing
Company, Inc.
7. Authorizes and directs the City Manager to execute the project contract on behalf of the
City of Petaluma upon timely submission by American Asphalt Repair and Resurfacing
Company, Inc., of the signed project contract and all other required document, including
but not limited to, executed bonds, certificates of insurance, and endorsements, in
accordance with the project bid documents.
8. Approves a construction contract contingency of $246,903.
G
Attachment 2
PAVMENT RESTORATION 17/18
PROJECT NO. C16101823
LOCATION MAP
� � Y
G q
.�..
iLj a
AFT�G /
LAKE ILL H HWAY
e
G�
N
J f
Date :MARCH 12, 2018
N �p LLr
City of Petaluma
PROJECT SITE w E
VARIOUS LOCATIONS Public Works and Utilities
S Department
zs5$
7
PAVMENT RESTORATION 17/18
PROJECT NO. C16101823
Stre e t Name
B e innin
End
4th Street
D Street
B Strreet
6th Street
Liberty Street
D Street
Adrienne Dirve
Kresky Way
Lindberg Lane
Albert Way
McGregor Avenue
Weaverly Drive
Atlantic Court
Lombardi Avenue
End of CDS
B Street
Petaluma. Blvd South
El Rose Drive
Carlin Court
Ramona lane
End of CDS
Corona Road
HWY 101
McDowell Blvd S.
Grant Street
I Street
Mountain View Ave
I Street
Petaluma Blvd South
City Limits
Keller Street
Western Avenue
A Street
Kresky Way
Stuart Drive
Lindberg Lane
Liberty Street
Washington Street
6th Street
Lindberg Way
Saint Francis Drive
McDowell Blvd S.
Lombardi Avenue
Saint Francis Drive
Lombardi Court
Madison Street
Arlington Drive
Lakeville Street
Olive Street
I Street
Mountain view Ave
Ramona Lane
nucklin Street
Saint Francis Drive
Regina Court
Ramona Lane
End of CDS
Reynolds Drive
Kresky Way
Lindberg Lane
Reynolds Drive
Lindberg lane
manan Way
S. McDowell Blvd E)d
Lakeville Hwy
Bridge
St. Francis Drive
Lindberg lane
Lombardi Avenue
Stuart Drive
Kresky Way
McKensie Avenue
Teresa Court
Ramona Land
End of CDS
Weaverly Drive
Ely Boulevard South
McDowell Blvd S.
Date :MARCH 12, 2018
L l�
PROJECT SITE N City of Petaluma
VARIOUS LOCATIONS
`" E Public Works and Utilities
S Department
z85$
8