HomeMy WebLinkAboutStaff Report 4.E 05/21/2018TT I
DATE: May 21, 2018
TO: Honorable Mayor and Members of the City Council through City Manager
FROM: Dan St. John, F.ASCE — Director, Public Works & Utilities X-(-
Jeff
'(Jeff Stutsman, P.E. — Senior Civil Engineer, Public Works & Utilities
SUBJECT: Resolution Authorizing Award of Contract for the Fire Station 1 Roof Overlay
and Replacement Project to Henris Supply, Inc.
RECOMMENDATION
It is recommended that the City Council adopt the attached Resolution Authorizing Award of
Contract for the Fire Station 1 Roof Overlay and Replacement Project to Henris Supply, Inc.
BACKGROUND
The existing roof on Fire Station 1 has reached the end of its useful life and needs to be
rehabilitated. The Council approved a FY 17/18 project budget of $119,000.
DISCUSSION
Because Fire Station 1 is more than fifty years old and is considered historic, the aesthetics of the
building from the roadway level must be maintained. To accomplish this, the existing shingles on
the visible peaked portion of the roof will be removed and replaced with fiberglass shingles very
similar to what is currently on the roof. Because the flat roof areas are not visible from the
roadway, they will be overlaid with 60 -mil thermoplastic polyolefin (TPO) single -ply membrane.
A walkway pad will be installed from the roof access hatch to the HVAC equipment to protect
the TPO membrane. This project will reduce the ongoing repair and maintenance costs and
eliminate leaks during winter rains.
Contract documents were prepared by staff and the Notice Inviting Bids for the work was issued
on April 5, 2018. The base bid included the majority of the work on the peaked and flat sections
of roof. An additive alternative was included in case favorable bids allowed sufficient funding to
replace the counter flashing at the building perimeter. On April 26, 2018, five (5) bids were
received as follows:
Name of Bidder
Business Location
Total Base Bid
Henris Supply, Inc.
Petaluma, CA
$107,375.90
I & A Contractor, Inc.
Redwood City, CA
$142,000.00
Andy's Roofing Co., Inc.
San Leandro, CA
$142,650.00
Pioneer Contractors, Inc.
San Francisco, CA
$150,500.00
Stronger Building Services
San Leandro, CA
$161,500.00
Engineer's Estimate
N/A
$100,000.00
Bids were ranked by base bid amounts. The lowest responsible bidder, Henris Supply, Inc., has
performed work for the City of Petaluma, and has performed similar public works projects. The
contractor, Henris Supply, Inc., possesses the necessary California Contractor's License, Class
C-39, number 220964, which expires on August 31, 2019, to perform the work.
It is recommended that the Council award the base -bid contract only to Henris Supply, Inc., for
$107,375.90. Construction would be scheduled to begin August 2018 and be completed in about
one month. The contract documents require completion within twenty (20) working days. The
project is categorically exempt from California Environmental Quality Act because it perfoinns
maintenance and minor upgrades to an existing facility project.
The proposed action meets Council Goal: "Plan and Deliver Capital Improvements: Renovate
and Expand Fire Stations 2 and 3."
FINANCIAL IMPACTS
The project is included in the FY 17/18 CIP Budget as C11201706 with an approved project
budget of $119,000 and funded by Transient Occupancy Taxes. The construction contract budget
of $100,000, was based on a square foot average of the City's recent roofing projects. However,
the conditions for this specific roof resulted in higher costs based on the actual roofing contractor
bids.
Because Fire Station 1 is considered historic and the currect aesthetics of the building must be
maintained staff anticipated higher roofing costs as compared to recent roofing overlays at Fire
Stations 2 and 3 and City Hall. The unused funds from these three previous roofing projects were
transferred to the Fire Station 1 Roof Overlay and Replacement project Construction Contract
budget item.
0)
FY 17/18 CIP
C11201706
Revised Project
Estimate
Design
Environmental
Construction Contract
$100,000
$128,752
Construction Management
$6,000
$6,000
Contingency
$10,000
$10,000
CIP Overhead
$3,000
$3,000
Total
$119,000
$147,752
0)
Any unused project funds at contract acceptance will be returned to the Transit Occupancy Tax
fund.
ATTACHMENTS
1. Resolution
Attachment 1
RESOLUTION AUTHORIZING AWARD OF CONTRACT FOR
THE FIRE STATION 1 ROOF OVERLAY AND REPLACEMENT PROJECT TO
HENRIS SUPPLY, INC.,
WHEREAS, City staff has prepared construction bid documents and advertised for
construction of this Project; and
WHEREAS, in accordance with the City of Petaluma Charter and Municipal Code,
California Public Contract Code Section 20162 and other applicable law, City staff solicited bids
for the Project; and
WHEREAS, the project was bid on April 5, 2018, and five (5) bids were received and
opened on April 26, 2018, in accordance with applicable law; and
WHEREAS, the lowest responsive bid for the Project was submitted by Henris Supply,
Inc., from Petaluma, CA for $107,375.90; and
WHEREAS, staff has determined that the Contractor's bid satisfies the bidding
requirements for the Project; and
WHEREAS, staff has verified that Contractor possesses a valid California Contractor's
License, Class C-39, number 220964 that is appropriate for the work to be performed for the
Project; and
WHEREAS, the Project is categorically exempt pursuant to California Environmental
Quality Act ("CEQA") and Title 14, the California Code of Regulations ("CEQA Guidelines"),
Section 15301, because the project consists of the operation, repair, maintenance or minor
alteration of existing public structures involving negligible or no expansion of use beyond that
previously existing; and
.19
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of
Petaluma hereby:
1. In accordance with the City of Petaluma Charter and Municipal Code, California Public
Contract Code Section 20162 and other applicable law, waives any and all non-
conformance in the bid of Henris Supply, Inc., for the Fire Station #1 Roof Overlay and
Replacement Project, finds the bid of $107,375.90 to be the lowest, responsive bid and
further finds that Henris Supply, Inc., is the lowest responsible bidder.
2. Awards the contract for the Fire Station 1 Roof Overlay and Replacement Project No.
C11201706 to Henris Supply, Inc., in the amount of $107,375.90, the amount of the
lowest responsive bid, conditioned on Henris Supply, Inc.'s timely executing the project
contract and submitting all required documents, including but not limited to, executed
bonds, certificates of insurance, and endorsements, in accordance with the project bid
documents.
3. Authorizes a construction contract contingency of $10,000.
4. Authorizes and directs the City Manager to execute the project contract documents on