Loading...
HomeMy WebLinkAboutStaff Report 4.C 08/05/2019z85s DATE: TO: FROM: SUBJECT: Agenda Item #4.0 August 5, 2019 Honorable Mayor and Members of the City Council through City Manager' Dan St. John, F.ASCE — Director, Public Works & Utilities Phil Benedetti — Assistant Engineer II, Public Works & Utilities Resolution Accepting Completion of the Ellis Creek Solids Handling Upgrades Project C66501305 RECOMMENDATION It is recommended that the City Council adopt the attached Resolution Accepting Completion of the Ellis Creek Solids Handling Upgrades Project C66501305. BACKGROUND The City's Ellis Creek Water Recycling Facility (ECWRF) has been in operation since early 2009 and currently processes an average dry weather daily flow of 4.8 MGD (million gallons per day). Since 2010, the plant has experienced increases in organic loading. A large part of this increased loading is the growth of the City's food processing industries. To understand better the City's wastewater treatment and reclaimed water needs, the City Council held a workshop on March 11, 2013, and adopted a goal to: "Focus attention on supporting food and beverage processing, manufacturing, and alternative energy business clusters." In addition, a review of the plant was conducted to evaluate loading trends. The plant evaluation resulted in a recommendation to upgrade the solids treatment system to address wastewater loading increases while filling the need for redundancy in the plant system by adding a second anaerobic digester and other ancillary improvements. The project included adding a second 550,000 -gallon anaerobic digester to mirror the existing digester. The second digester will provide a factor of safety to the regulatory requirement of a minimum 15 -day solids detention time where current operation hovers at 16 to 18 days detention time. These improvements have resulted in modification of the activated sludge process to reduce oxygen demand and improve aeration. This project also completed the first phase of the larger Biomass to Biof iel project by providing digester capacity to accept high strength waste from the City's food and beverage industries. Subsequent phases of this project are currently under construction at ECWRF and are expected to be completed by October 2019. Additional upgrades within this project include a second gravity belt thickener, third thickened waste pump, and related piping, controls, and heating equipment. Additionally, the project includes replacement of the existing dewatered sludge conveyance system, which has been problematic, and the addition of a truck scale for the biosolids hauling trucks. Bids for the construction contract were opened on June 1, 2016, and on July 11, 2016, the City Council awarded the construction contract to C. Overaa & Co., of Richmond, CA in the amount of $6,204,000. Construction was substantially completed in September 2018. The proposed action meets Council Goals: "Our Environmental Legacy, Goal 51- Complete Biomass to Biofuel project at the City's Ellis Creek Water Recycling Facility." DISCUSSION The final construction contract cost is $7,052,428, which included nine change orders. The change orders are described in the table below: Change Value Order # Summary I During construction of Digester #2, the adjacent Sludge Storage Tank was 1 $58,130.00 emptied to eliminate the need for extensive shoring to prevent settlement. During this time the tank was cleaned and several maintenance items were addressed. During construction of the Treatment Wetlands Effluent pipeline, additional provisions were needed to stabilize the trench due to the presence of 2 $89,795.00 groundwater. During excavation for Digester #2, an electrical ductbank was discovered in the footprint of the foundation to be installed, requiring demolition of the ductbank and re-routing of several existing electrical conduits. During a routine inspection of the ECWRF Outfall pipeline, it was noted that several sections of the pipe had developed signs of failure and that a possibility 3 $163,914.00 of collapse was high. A temporary bypass system was designed by City Staff and installed by the contractor as a contingency plan, should the outfall pipe fail and prevent discharge. An alternative routing of the dewatered solids cake conveyor system was devised to allow the use of both truck load -outs. This was facilitated by changing 4 $270,093.00 plans during the design of the High Strength Waste project, which eliminated the need for a second screw press. This required different conveyors, supports, electrical equipment, and controls. During construction of Digester #2, it was determined that the proposed method of operating the digesters in series configuration via gravity flow would pose 5 $183,751.00 operational issues. A new plan was designed that would allow series operation of the digesters, utilizing pumped sludge. This required piping changes, additional electrical equipment, and controls changes. This credit was received from the Contractor as a result of eliminating the second digester gas blower from the contract. During the design of the 6 -$261,801.00 CNG/HSW projects, City Staff were able to determine that the dual fuel boilers would primarily use utility natural gas instead of digester gas. This eliminated the need for a redundant blower unit. I Change Value Order # Summary This change order included numerous additional equipment including piping, valves, electrical conduit, and equipment supports that were the result of 7 $134,353.00 changes from other change orders. A new bucket was provided for one of the large chopper pumps that was specified to use an existing bucket with an undersized motor starter unit. This resulted in a delay of the project addressed in change order #8. The delay caused by the bucket replacement described in change order #7 8 $29,056.00 resulted in a delay of 24 working days on the critical path of the project. The contractor's claim of $109,056 was reduced by City Staff via negotiation for contractor delays related to the startup of the dewatered cake conveyor system. The new dewatered cake conveyors selected required different conduit and conductors than what were described in the original contract. Changes to the 9 $181,137.00 lighting around the digester required additional conduit, conductors and switches. An additional stainless pipe spool was needed to allow the addition of High Strength Waste to Digester #1. Total Cost of $848,428.00 Changes FINANCIAL IMPACTS The total approved project budget (Project Number C66501305) was $9,795,000. With the design, construction contract, final quantities, contingency, construction management and inspection, the total revised cost for the project was $9,795,000, as shown in following project breakdown: Ellis Creek Solids Handling Approved Upgrade Project C66501305 CIP Budget Planning/Environmental $ 445,000 Design $ 1,053,000 Construction Contracts $ 7,001,000 Construction Management $ 456,000 CIP Overhead/Administration $ 40,000 Contingency $ 800,000 TOTAL EXPENSES $ 9,795,000 FUNDING SOURCES Wastewater Capital $ 9,795,000 TOTAL FUNDING $ 9,795,000 Revised Project Cost $ 84,018 $ 1,130,038 $ 7,202,257 $ 720,400 $ 84,710 $ 573,577 $ 9,795,000 $ 9,795,000 $ 9,795,000 The project is funded through the wastewater capital fund. At project closeout, any remaining funds will be returned to the Wastewater CIP fund to be used on other future projects. Following 3 the acceptance of the project, the City Clerk will file a Notice of Completion with the Sonoma County Recorder and the Finance Department will release the contract retention account to the contractor within 60 days. ATTACHMENTS 1. Resolution 2. Location Map 11 Attachment 1 RESOLUTION ACCEPTING COMPLETION OF THE ELLIS CREEK SOLIDS HANDLING UPGRADES PROJECT 066501305 WHEREAS, City staff prepared construction bid documents and advertised for the Ellis Creek Solids Handling Upgrades Project C66501305 to construct a new anaerobic digester and install various other solids handling equipment at 3890 Cypress Drive, Petaluma, CA 94954 ("the project"); and WHEREAS, the Project was bid on April 20, 2016, and five (5) bids were received and opened on June 1, 2016 in accordance with applicable law; and WHEREAS, the lowest responsible bid for the Project was submitted by C. Overaa & Co., of Richmond, CA for $6,204,000.00; and WHEREAS, by Resolution No. 2016-112 N.C.S., adopted on July 11, 2019, the City Council found the bid of $6,204,000.00 for the project to be the lowest responsive bid, awarded the Project to C. Overaa & Co., in the amount of $6,204,000.00, conditioned on C. Overaa & Co.'s timely executing the project contract and submitting all required documents and authorized and directed the City Manager to sign the project contract on behalf of the City; and WHEREAS, the following contract change orders (CCO) affecting the Project amount have been approved: Proiect (C66501305) Cost Change Order #1 $ 58,130.00 Change Order #2 $ 89,795.00 Change Order #3 $ 163,914.00 Change Order #4 $ 270,093.00 Change Order #5 $ 183,751.00 Change Order #6 $ <261,801.00> Change Order #7 $ 134,353.00 Change Order #8 $ 29,056.00 Change Order #9 $ 181,137.00 Total Change Orders $ 848,428.00 ; and WHEREAS, the final contract amount, as amended, including all change orders, overruns and underruns is $7,052,428.00 and is within the approved project budget, and 5 WHEREAS, based on the foregoing, staff recommends acceptance of the project on behalf of the City. NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Petaluma hereby: The contract titled Ellis Creek Solids Handling Upgrades Project, project no. 066501305, with the final contract amount of $7,052,428.00, is accepted as complete, subject to the Contractor's continuing warranty and other obligations pursuant to the contract. 2. The City Clerk is hereby authorized and directed to file a Notice of Completion concerning the project with the Sonoma County Clerk's Office within 10 days of the date of this Resolution. 3. Staff are hereby authorized and directed to release all undisputed retention not subject to pending change orders within 60 days of the date of this Resolution and in accordance with the terms of the project contract, California Public Contract Code Section 7107 and applicable law. 3 ELLIS CREEK WATER RECYCLING FACILITY SOLIDS PROCESS UPGRADES PROJECT NO. 066501305 I 11113614I.Awspi L a &A 1219 419T 7 FSSO�/ � � C ELLIS CREE/W� WATER RECY6ING/ � J "rry x/ r Date: June 1, 2015 Attachment 2 N City of Petaluma PROJECT SITE w E Public Works and Utilities S Department 185'6