HomeMy WebLinkAboutStaff Report 3.A 02/24/2020DATE Im Agenda Item #3.A February 24, 2020 r` Honorable Mayor and Members of the City Council through City Manager Jason Beatty, P.E — Director, Public Works and Utilities Dan Herrera, P.E. — Senior Civil Engineer, Public Works and Utilities SUBJECT: Resolution Authorizing the City Manager to Execute an Amendment to a Professional Services Agreement and Approving a Revised Budget for the Payran Underground Storage Tank Site Remediation Project RECOMMENDATION It is recommended that the City Council adopt the attached Resolution Authorizing the City Manager to Execute an Amendment to a Professional Services Agreement and Approve a Revised Budget for the Payran Underground Storage Tank Site Remediation Project. BACKGROUND The former City fire station site located at 301 Payran Street previously had an underground storage tank (UST) that was removed in 1988. The tank was found to be compromised and leaking fuel into the soil and groundwater. Remediation work was required to remove the contamination caused by the leaking UST. The City originally obtained grant funding from the States UST Cleanup Fund to perform the work. Since then, the site has undergone extensive subsurface investigations and remediation work to remove hydrocarbons in the groundwater that resulted from apparent leaks from the old UST. The remediation has included installation of numerous monitoring wells and operation of a "pump and treat" extraction and cleanup system. The City employed Van Houton Consultants from 1988 until 1995 to oversee the work, evaluate nearby domestic water wells, and conduct a soil vapor study to evaluate potential impacts from contaminated groundwater. From this study it was determined that no domestic wells in the area were impacted, but the "pump and treat" method did not eliminate the groundwater contamination. From 2009 — 2014, the City worked with ECON, a remediation consulting firm, to perform various remediation efforts to in order to bring contamination levels to an acceptable level for site closure. Unfortunately, these efforts were insufficient to bring the site to closure levels and more remediation work was needed. In accordance with California Code of Regulations, Title 23 Waters, Division 3 State Water Resources Control Board and Regional Water Quality Control Boards, Chapter 16 Underground Tank Regulations, Article 11 Corrective Action Requirements, the City of Petaluma is required to continue remediation of site until contamination levels are low enough for the site to be closed. The Sonoma County Department of Health Services (SCDHS), acting as the Local Oversight Program on behalf of the State Water Resources Control Board, has the authority to oversee the City's progress to remediate the site and been working with the City to promptly accomplish that goal. In June 2016, City Staff prepared an RFP for the continued remediation of the site and Edd Clark & Associates (ECA) was selected to perform the work. In July 2016, City Council approved a professional services agreement (PSA) with ECA to complete the remediation work for the site and bring it to within closure levels (Resolution No. 2016-128 N.C.S.). In addition to awarding the PSA, the Council action approved of budget adjustment and a new funding source, due to the exhaustion of grant funding for this project. It was determined that due to the risk of impact to the City's current and future groundwater wells in the vicinity of the project, the use of Water Funds was approved. ECA has installed and operated remediation equipment since December 2017 and is continuing operations of remediation at the site until site closure requirements are met. DISCUSSION In the Fall 2017, ECA installed a High Vacuum Dual Phase Extraction (HVDPE) equipment and began full time remediation operations in February 2018. The equipment operates by extracting both groundwater and vapor from various extraction wells and uses combustion and carbon filtration to remove the contamination. The contract was originally intended to have up to 24 - months of remediation operations and up to 36 -months of groundwater monitoring and testing. We are currently approaching the estimated 24 -months of remediation operations, and the contamination levels are nearing site closure levels, but have not yet met them. The original amount of the contract was for $506,152.80, and costs are approaching the contract limit. There are several factors which contributed to the original budgeted amount not being sufficient to complete the project. These factors include: • The anticipated construction costs were underestimated. Although efforts were made to reduce construction costs, the total costs to install the system were triple the estimated costs. This was due to unanticipated obstacles encountered during excavation and relocation of equipment. • The site is located in a sensitive area, adjacent to a charter elementary school, and non- profit organization. Efforts to adjust operational hours to address and accommodate these neighbors' concerns decreased the efficiency of the system, and increased maintenance costs for the equipment. • Installation costs for proposed gas and electrical upgrades were found to be cost prohibitive. The use of propane for combustion and using the existing electrical service increased the monthly operations costs to operate the system. Efforts were made to increase productivity and reduce costs throughout the project. The remediation method was modified from the dual phase method of combustion and filtration to a method that solely uses carbon filtration to remove the contamination. This change in operations allows the system to be run continuously rather than having reduced operational hours and I eliminated the high costs for propane used in combustion. With these changes, the project requires additional budget and an amendment to the contract with ESA to cover the anticipated costs through closure of the site. City Staff consulted with ECA to determine an estimated scope and budget for an additional 6 - months of remediation operations using the groundwater carbon filtration method and additional work for site closure operations that were not included in the original contract. This additional work includes demolition of existing wells, site cleanup and reporting. The total cost for this additional work is $149,409.00 (Attachment 2). This would bring the total cost of the contract with ECA to $655,562.80. It is expected with this amendment, the change in methods and continuous operation of the equipment that contamination levels will reach closure levels July 2020, with total project closeout by December 2020. It is recommended that Council approve of Amendment No. l to the PSA with Edd Clark & Associated for a contract budget increase of $149,409. PUBLIC OUTREACH In the initial stages of the project, ESA completed a Corrective Action Plan (CAP) which outlined the remediation of the site. The CAP was submitted to the County and subject to public input. In addition, the project requires a permit from the Bay Area Air Quality Management District (BAAWMD). City staff has maintained an open communication with the neighbors of the site, Rebuilding Together and Live Oak Charter School. Throughout the project, City staff has had on-site meetings as well as phone and email communication with the neighbors, to ensure they were informed of the progress of the project. Communication is vital to the success of the project, and City Staff is maintaining open communication lines with these stakeholders to ensure their concerns and questions are addressed through completion of the project. COUNCIL GOAL ALIGNMENT This project meets the following City's Goals: Workplan item #42 — "Establish and promote a citywide sustainability program leading with exemplary environmental practices". ALTERNATIVES The alternatives to this action are limited. The remediation of the site until closure levels are met is required by the State of California. The only alternative to amending the existing contract is to allow the contract limit to be reached and close out the existing contract, then solicit another Request for Proposal (RFP) from remediation consultants and begin the process again. This action would take several months of valuable time that could be used for remediation efforts to reach site closure levels. The current consultant has been very responsive to City and neighbor concerns and has made significant progress in reaching site closure levels and it is recommended that the City amend the existing contract to continue remediation efforts. FINANCIAL IMPACTS The project has been included in the City's Capital Plan for several years, as program e16082012. The original total project budget was for $1,430,000. With the approval of the amendment to ECA's PSA, the total budget for the project will need to be increased to $1,528,000, a total increase of $98,000. This project expenditure adjustment will result in an increase of $86,000 for FY 2019/20 budget, which will be funded by increased revenues from the State UST Clean up Fund and Water Enterprise Fund. Staff recommends bringing the adjustment forward in conjunction with the year-end budget adjustment action. The following is a breakdown of the project expenses, approved and revised budget. As outlined in the Discussion section of this memo, it is proposed that the Water Enterprise Fund be used to fund the proposed expenses identified above to complete the remediation. There are adequate reserves in the Water Fund to cover these expenses. ATTACHMENTS 1. Resolution 2. Exhibit A - Amendment No. 2 to Professional Services Agreement 3. Exhibit B - Original Professional Services Agreement 4. Location Map 11 Approved C1P el 6082012 Actuals Budget Revised Budget Payran UST Clean -Up Proiect Thru I Total Project FY 18/19 FY 19/20 FY 19/20 FY 20/21 Estimate i Project Expenses Planning/Environmental $ 437,000 $ 160,000 $ 50,000 $ 647,000 Design $ 405,000 $ 74,000 S 405,000 Legal Services $ 0 S 0 Administration $ 10,000 S 10,000 Construction Contracts $ 400,000 $ 400,000 Construction/Project Management $ 21,000 $ 15,000 $ 15,000 $ 10,000 S 41,000 Proiect Contineencv $ 0.00 $ 10,000 $ 10,000 $ 10,000 $ 10,000 TOTAL $1,273,000 $ 99,000 $ 185,000 $ 70,000 $1,528,000 Funding Sources State UST Cleanup Fund $ 727,000 $ 29,600 $ 756,600 Successor Agency - PDCC $ 50,000 $ 50,000 General Fund $ 173,000 S 173,000 Water Enterprise Fund $ 365,000 $ 133,000 $ 155,400 $ 28,000 $ 548,400 TOTAL $1,315,000 $ 133,000 $ 185,000 $ 28,000 $1,528,000 As outlined in the Discussion section of this memo, it is proposed that the Water Enterprise Fund be used to fund the proposed expenses identified above to complete the remediation. There are adequate reserves in the Water Fund to cover these expenses. ATTACHMENTS 1. Resolution 2. Exhibit A - Amendment No. 2 to Professional Services Agreement 3. Exhibit B - Original Professional Services Agreement 4. Location Map 11 Attachment 1 RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE AN AMENDMENT TO A PROFESSIONAL SERVICES AGREEMENT AND APPROVING A REVISED BUDGET FOR THE PAYRAN UNDERGROUND _3K67MIT" aI OML-14YYa901u1of17Ir11[17►i9.TOIpro] WHEREAS, the site of a former fire station located at 301 Payran Street has had extensive subsurface investigations and remediation work to address apparent contamination resulting from an underground storage tank (UST) since approximately 1988. Groundwater sampling and analysis has confirmed that both onsite and offsite groundwater is impacted with petroleum hydrocarbons that have apparently emanated from the former UST; and WHEREAS, the City of Petaluma has an obligation to the State Water Resources Control Board to continue remediation at the 301 Payran Street site until approved for closure by the Sonoma County Department of Health Services; and WHEREAS, this project requires the services of a quality professional firm familiar with the project and experienced in underground storage tank remediation; and WHEREAS, Edd Clark & Associates responded to the City's Request for Proposals and was awarded a Professional Services Agreement in July 2016 under Resolution 2016-128 N.C.S. in the amount of $506,152.80; and WHEREAS, Edd Clark & Associates has been operating the remediation equipment for approximately twenty-three (23) months and is approaching the contract's budgetary limits; and WHEREAS, the City of Petaluma is required to continue remediation of the site until contamination levels are low enough for the site to be closed; and WHEREAS, the site has not achieved contamination removal and may require up to six (6) additional months of treatment to achieve contamination levels for closure; and WHEREAS, the City has amended the project scope and budget to include an additional 6 -months of remediation operations, preparation of required reporting, and site closure measures including well demolition and removal not included in the original project scope; and WHEREAS, it is recommended that the City execute an Amendment to a Professional Services Agreement (PSA) with Edd Clark & Associates for groundwater remediation services in order to continue remediation efforts for site closure and to satisfy state requirements; and WHEREAS, the FY 19/20 CIP Budget is not sufficient to complete the project. NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Petaluma hereby: Authorizes the City Manager to sign the attached Amendment to Professional Services Agreement for specialized environmental services with Edd Clark & Associates, Inc. (EC&A) of Rohnert Park for the 301 Payran UST Site Remediation Project in the amount not to exceed $655,562.80. 2. Authorizes a revised budget for the Payran UST CIP Project number e16082012 as summarized in the table contained in the "Financial Impacts" section of the accompanying memorandum. 3 Attachment 2 Exhibit A to Resolution AMENDMENT NO.2 TO PROFESSIONAL SERVICES AGREEMENT FOR Remediation and Groundwater Monitoring Services for 301 Payran Street THE AGREEMENT entered into and effective as of August 25, 2016, by and between the City of Petaluma, a municipal corporation and a charter city (hereinafter referred to as "City") and Edd Clark & Associates, Inc. (hereinafter referred to as "Consultant") is hereby amended as follows: (Please check applicable boxes and complete highlighted areas below): [ ] SCOPE The following sentence is added to the end of Section 1, "Services": In addition to the services described in Exhibit A, Consultant shall provide the additional services described in Exhibit A- (name of exhibit) attached hereto. [X ] COST The "Not -to -Exceed Amount" specified in Section 2.A is amended as follows: Original Agreement Amount $506,152.80 Amendment No. (list amendment number) $149,409.00 Total Not -to -Exceed Amount $655,561.80 [] TERM The term of this Agreement commences on the Effective Date, and terminates on December 31, 2020, unless sooner terminated in accordance with Section 3. Upon termination, any and all of the City's documents or materials provided to Consultant and any and all of the documents or materials prepared for City or relating to the performance of the Services, shall be delivered to the City as soon as possible, but not later than fourteen (14) days after termination of the Agreement. [ ] SECTION 18(D) Consultant agrees to waive subrogation rights for commercial general liability, automobile liability and worker's compensation against City regardless of the applicability of any insurance proceeds, and to require all contractors, subcontractors or others involved in any way with the Services to do likewise. It shall be a requirement under this Agreement that any available insurance proceeds broader than or in excess of the specified minimum insurance coverage requirement and/or limits shall be available to the additional insured. Furthermore, the requirement for coverage and limits shall be (1) the minimum coverage and limits specified in this Agreement, or (2) the broader coverage and maximum limits of coverage of any insurance policy or proceeds available to the named insured; whichever is greater. Amendment to Professional Services Agreement (All PSA's) Oct 2019 7 The limits of insurance required in this Agreement may be satisfied by a combination of primary and umbrella or excess insurance. Any umbrella or excess insurance shall contain or be endorsed to contain a provision that such coverage shall also apply on a primary and non-contributory basis for the benefit of the City of Petaluma before the City of Petaluma's own insurance or self-insurance shall be called upon to protect it as a named insured. IN WITNESS WHEREOF, the parties hereto have executed this document the day of ,20 CITY OF PETALUMA CONSULTANT City Manager ATTEST: City Clerk APPROVED AS TO FORM: City Attorney By e� _ OSignature 3 v� �, G.,( , o is rt s / j -,-e, 6 r11 p4r,, Name and Title �q N. Addres11s o -e a ppw<, City State Zip Taxpayer I.D. Number Petaluma Business Tax Certificate Number 2 Amendment to Professional Services Agreement (All PSA's) Oct 2019 M Attachment 3 Exhibit B to Resolution PROFE SSIONAL SERVICES AGREEME NT Reniediation and Groundwater Monii scrVices for 301 pa vrall Street ('Title of' prqject) FY 1(L)07 Fund 4_ C(ist Cel -Iter _ 01)ject Code 30101) Projed # — Amount $506ji2ff) For multi-ycar conjr,Qt,, ov contracts with zntdtip c aceLitiltig: FY _ FUnd V _ Cost Centel- _ 01jecl Code Projed 0 Aniount FY — FLmd V _ Cost Center 01jecf Code Proect 4 J Aniount FY Fund C rj.�j I Center — Objeo Code Pro-iccl # Aimunt FY Fund Cost Centel, 01jcct Code P t'qjucl It Amount FY— Fund Utast Center _ ObJeo ('(.)lie Project # Aolount THIS PR �FESSIONAL SERVICES AGREE MENT("Agrectilent") is entered into rand efi'ective as of I, , ! � "' 3 2 (, ("Efloctivc Date"), by and between the City of Petaluma. a (city trY [nay} J11U111Cip3l corporation and a chal-ter city ("City") and Edd Clark -,Associates. Inc., a California for)o j (`,C.on, ratiosultant") (collectively, the "Parties'), J ------ n WHEREAS, tutu. Parties enter into this Agreement for the purpose of' Consultant providing professional services to City under the terms and conditions set forth herein. THEREFORE, in consideration of tile inutual covenants contained in this Agreement, the Parties agree as follows: Scitwices. Consultant shall provide the services as described in and in accordance with [lie schedule Set forth in Exhibit "A" attached hereto and incorporated herein ("Services"). 2. carneellsatio . Business Tax Cerfiflcate. A. For the full performance of the ServIces as described herein, City shall compensate Consultantin accoTdan-cc with the rates soccified in Exhibit ibit A, 13. Consultant shall submit detailed monthly invoices reflecting all services performed during the preceding month, and including a revised schedule for perforniance and additional documentation requested by City, as applicable. C. Consultant shall be compensated -for services in addition to those described in Exhibit A, only if Consultant and City execute a written aniendment to this Agreement dcscribirig the additional services to be pertbrined and the compensation to be paid for such services. 11, no case shall the total compensation under this Agreement exceed $50 0.152.80 (Five Hundred 5'ix Thousand One Hundred Fifly-two Dollars and EiLdity Cents I without prior written authorization of the City Manager. Further, no compensation for a section or work prograin component attached with a specific budget sliall be exceeded without prior written authorization of tile City Manager. PROR-SNIONAL SERVICES AGRIEEMEN'r — PR UVAILING WAGES (107730) Atigt1812(t I s 9 D. Notwithstanding any provision herein, Consultant shall not be paid any compensation until such time as Consultant has on file with the City Finance Department a current W-9 form available from the IRS website (www.irs.jzov) and has obtained a currently valid Petaluma business tax certificate. E. City's obligation to pay compensation to Consultant as provided herein is contingent upon Consultant's performance of the Services pursuant to the terms and conditions of this Agreement and any amendments thereto. 3. Term. The term of this Agreement commences on the Effective Date, and terminates on June 30, 2019, unless sooner terminated in accordance with Section 4. Upon termination, any and all of City's documents or materials provided to Consultant and any and all of the documents or materials prepared for City or relating to the performance of the Services, shall be delivered to the City as soon as possible, but not later than fourteen (14) days after termination of the Agreement. 4. Termination. City may terminate this Agreement without cause upon ten (10) days' written notice. City may immediately terminate or suspend this Agreement for cause. Cause for immediate termination or suspension shall include, but not be limited to, any breach of this Agreement by Consultant or Consultant's bankruptcy or insolvency. Upon receipt of notice of termination or suspension for cause, Consultant shall immediately stop all work in progress under this Agreement. In the event of early termination of this Agreement by City, Consultant shall be entitled to payment for all Services performed to the date of termination to the extent such Services were performed to the satisfaction of City in accordance with the terms and conditions of this Agreement. If City terminates this Agreement for cause, Consultant shall be liable to City for any excess cost City incurs for completion of the Services. 5. Consultant's Representation, Independent Contractor. Consultant represents that Consultant possesses distinct professional skills in performing the Services. City has relied upon said representation as a material inducement to enter into this Agreement. Consultant shall, therefore, provide properly skilled professional and technical personnel to perform all Services under this Agreement. It is expressly understood that Consultant and its agents and employees, shall act in an independent capacity and as an independent contractor and not as officers, employees or agents of City. This Agreement shall not be construed as an agreement for employment. 6. Facilities and Equipment. Consultant shall, at its sole cost and expense, furnish all facilities and equipment that may be required for furnishing Services pursuant to this Agreement. City shall furnish to Consultant no facilities or equipment, unless the City otherwise agrees in writing to provide the same. 7. Licenses, Permits, Etc. Consultant shall, at Consultant's sole cost and expense, keep in effect at all times during the term of this Agreement any licenses, permits or other such approvals which are legally required for performing the Services. 2 PROFESSIONAL SERVICES AGREEMENT — PREVAILING WAGES (1037730) August 2015 10 8. Time. Consultant shall devote such time to the performance of the Services as may be reasonably necessary for satisfactory performance of Consultant's obligations pursuant to this Agreement. 9. Inspection. Consultant shall provide the City every reasonable opportunity to ascertain that the Services are being performed in accordance with the requirements and intentions Of this Agreement. All work done and materials furnished, if any, shall be subject to inspection and approval by the City. The inspection of such work shall not relieve Consultant of any of its obligations pursuant to this Agreement. 10. Progress Reports. Upon the City's request, Consultant shall provide, in a form acceptable to City, written progress reports of all oral and written observations, opinions, recommendations, analyses, progress and conclusions related to Consultant's performance of the Services. 11. Confidentiality. In the course of Consultant's employment, Consultant may have access to trade secrets and confidential information, disclosure of which is protected or limited by law. Consultant shall not directly or indirectly disclose or use any such confidential information, except as required for the performance of the Services. 12. Conflict of Interest. Consultant represents that it presently has no interest, and covenants that it shall not acquire any interest, direct or indirect, financial or otherwise, which would conflict in any manner or degree with the performance of the Services hereunder. Consultant further covenants that, in the performance of this Agreement, it shall not employ any subcontractor or person having such a conflict of interest. Consultant represents that no one who has or will have any financial interest under the Agreement is an officer or employee of City. If such conflict of interest arises during this Agreement or any extension, Consultant will immediately advise City and City may, at its sole discretion, immediately terminate this Agreement. Certain Consultants are subject to the requirements, including the disclosure and reporting requirements, of the City's Conflict of Interest Code adopted pursuant to the Political Reform Act. Such Consultants subject to the City's Conflict of Interest Code include those whose work may involve: making government decisions regarding approval or adoption of rates, rules, or regulations, action on permits or other applications, authorization to enter into or modify contracts, or approval of plans, designs, reports, or studies. Consultant agrees to comply fully with all such requirements to the extent they apply to Consultant's performance of the Services. 13. Consultant No Agent. Except as City may specify in writing, Consultant shall have no authority, express or implied, to act on behalf of City in any capacity whatsoever as an agent. Consultant shall have no authority, express or implied, pursuant to this Agreement to bind City to any obligation whatsoever. 14. Standard of Performance. Consultant shall perform all the Services in a manner consistent with the standards of Consultant's profession. All instruments of service of whatsoever nature, which Consultant delivers to City pursuant to this Agreement, shall be prepared in a substantial, workmanlike manner and conform to the standards of 3 PROFESSIONAL SERVICES AGREEMENT—PREVAILING WAGES (1037730) August 2415 Consultant's profession. All such instruments of service shall become the sole and exclusive property of City upon delivery of the same. 15. Assignment/Transfer. No assignment or transfer in whole or in part of this Agreement shall be made without the prior written consent of City. 16, Subcontractors. Consultant shall directly perform all Services, and shall not subcontract any portion of performance of the Services without the prior written consent of City. Any such subcontractors shall be required to comply, to the full extent applicable, with the terms and conditions of this Agreement, including but not limited to, procuring and maintaining insurance coverage as required herein and which shall name City as an additional insured. 17. Compliance With All Laws. Consultant shall fully comply with all applicable local, state and federal rules, laws, regulations and ordinances pertaining to the performance of the Services required hereunder, including but not limited to, the California Building Standards Code as in effect in the City, the Americans with Disabilities Act, and any laws and regulations related to any copyright, patent, trademark or other intellectual property right involved in performance of the Services. Consultant's failure to comply with any law(s) or regulation(s) applicable to the performance of the Services hereunder shall constitute a material breach of this Agreement. To the extent that any other government agency or entity provides compensation for any Services, Consultant shall comply with all rules and regulations applicable to such fiscal assistance. 18. Prevailing Wages. This Agreement is subject to the requirements of the California Prevailing Wage Law, California Labor Code Section 1720 et seq., and the Services as described in Exhibit A will be performed in accordance with all applicable requirements of the California Prevailing Wage Law, including, but not limited to, all applicable requirements contained in Exhibit C, which is attached to and made a part of this Agreement. 19. Living Wage Ordinance. Without limiting the foregoing Section 17, Consultant shall comply fully with all applicable requirements of Petaluma Municipal Code, Chapter 8.36, Living Wage (the "Living Wage Ordinance"), as the same may be amended from time to time. Upon the City's request Consultant shall promptly provide to the City documents and information verifying Consultant's compliance with the requirements of the Living Wage Ordinance, and shall within fifteen (15) calendar days of the Effective Date of this Agreement, notify each of its affected employees as to the amount of wages and time off that are required to be provided to them pursuant to the Living Wage Ordinance. The Acknowledgement and Certification Pursuant to City of Petaluma Living Wage Ordinance, attached to this Agreement at Exhibit D, shall be a part of this Agreement for all purposes, and Consultants that are subject to Living Wage Ordinance requirements, as determined by the City, must provide a properly completed Exhibit D in accordance with the requirements of the Living Wage Ordinance. Consultant's noncompliance with the applicable requirements of the Living Wage Ordinance shall constitute cause for City's termination of this Agreement pursuant to Section 4 hereof 4 PROFESSIONAL SERVICES AGREEMENT— PREVAILING WAGES 12 (1037730) August 2015 20. Discrimination. During the performance of this Agreement, Consultant shall not discriminate against any employee or applicant for employment because of race, religion, creed, color, national origin, ancestry, gender, sexual orientation, age or physical or mental disability in violation of any applicable law. 21. Notice. Except as otherwise specified in this Agreement, all notices to be sent pursuant to this Agreement shall be made in writing, and sent to the Parties at their respective addresses specified below or to such other address as a Party may designate by written notice delivered to the other Party in accordance with this Section. All such notices shall be sent by: (i) personal delivery, in which case notice is effective upon delivery; (ii) certified or registered mail, return receipt requested, in which case notice shall be deemed delivered on receipt if delivery is confirmed by a return receipt; (iii) nationally recognized overnight courier, with charges prepaid or charged to the sender's account, in which case notice is effective on delivery if delivery is confirmed by the delivery service; or (iv) facsimile transmission, in which case notice shall be deemed delivered upon transmittal, provided that (a) a duplicate copy of the notice is promptly delivered by first-class or certified mail or by overnight delivery, or (b) a transmission report is generated reflecting the accurate transmission thereof. Any notice given by facsimile shall be considered to have been received on the next business day if it is received after 5:00 p.m. recipient's time or on a nonbusiness day. City: City Clerk City of Petaluma Post Office Box 61 Petaluma, California 94953 Phone: (707) 778-4360 Fax: (707) 778-4554 Email: cityclerk@ci.petaluma.ca.us And: Dan St. John. Director Department of Public Works & Utilities 202 North McDowell Boulevard Petaluma, CA 94954 Phone: (707) 778-4546 Fax: (707) 778-4508 Email: dstiohn(t_),ci.-oetaluma.ca.us Consultant: John Calomiris Edd Clark & Associates, Inc. P.O. Box 3039 Rohnert Park, CA. 94927-3039 Phone: 707-792-9500 PROFESSIONAL SERVICES AGREEMENT—PREVAILING WAGES 13 (1037730) August 2015 Fax: 707-792-9504 Email: info( a �eddclarkandassociates.com 22. Ownership of Documents. All original papers, documents or computer material on disk or microfilm, and copies thereof, produced as a result of this Agreement, shall be the property of City and may not be used by Consultant without the written consent of City. Copies of such documents or papers shall not be disclosed to others without the written consent of the City Manager or his or her designated representative. 23. Indemnification. To the maximum extent permitted by law, Consultant shall, at its own expense, indemnify, defend with counsel acceptable to the City, (which acceptance will not be unreasonably withheld), and hold harmless City and its officers, officials, employees, agents and volunteers ("Indemnitees") from and against any and all alleged liability, loss, damage, claims, suits, actions, arbitration proceedings, administrative proceedings, regulatory proceedings, civil penalties and fines, expenses and costs (including, without limitation, claims expenses, attorney's fees and costs and fees of litigation) (collectively, "Liability") of every nature, whether actual, alleged or threatened, arising out of or in connection with the Services or Consultant's failure to comply with any of the terms of this Agreement, regardless of any fault or alleged fault of the Indemnitees. The Consultant's obligation to indemnify, defend and hold harmless under this provision shall not be excused because of the Consultant's inability to evaluate Liability, or because the Consultant evaluates Liability and determines that the Consultant is not or may not be liable. The Consultant must respond within 30 calendar days to any tender for defense and indemnity by the City, unless the time for responding has been extended by an authorized representative of the City in writing. If the Consultant fails to accept tender of defense and indemnity within 30 calendar days, in addition to any other remedies authorized by law, so much of the money due or that may become due the Consultant under this Agreement as shall reasonably be considered necessary by the City, may be retained by the City until disposition has been made of the matter subject to tender, or until the Consultant accepts the tender, whichever occurs first. In the event that the City must file responsive documents in a matter tendered to Consultant prior to Consultant's acceptance of tender, Consultant agrees to fully reimburse all costs, including but not limited to attorney's fees and costs and fees of litigation, incurred by the City in filing such responsive documents. The Consultant waives any and all rights to express or implied indemnity against the Indemnitees concerning any Liability of the Consultant arising out of or in connection with the Services or Consultant's failure to comply with any of the terms of this Agreement. The Consultant's responsibility of such defense and indemnity obligations shall survive the termination or completion of this Agreement for the full period of time allowed by law. The defense and indemnification obligations of this Agreement are undertaken to, and shall not in any way be limited by, the insurance obligations contained in this Agreement. 0 PROFESSIONAL SERVICES AGREEMENT—PREVAILING WAGES (1037730) August 2015 14 Notwithstanding the foregoing, to the extent this Agreement is a "construction contract" as defined by California Civil Code Section 2783, as may be amended from time to time, Consultant's duty to indemnify under this provision shall not apply when to do so would be prohibited by California Civil Code Section 2782, as may be amended from time to time. Notwithstanding the foregoing, to the extent that the Services include design professional services subject to California Civil Code Section 2782.8, as may be amended from time to time, Consultant's duty to indemnify shall only be to the maximum extent permitted by California Civil Code Section 2782.8. 24. Insurance. Consultant shall comply with the "Insurance Requirements for Consultants" in Exhibit B-2, attached hereto and incorporated herein by reference. [Indicate attached exhibit, e.g., "B-1, " "B-2, " "B-3, " or "B-4. "] 25. Amendment. This Agreement may be amended only by a written instrument executed by both Parties. 26. Litigation. If litigation ensues which pertains to the subject matter of Consultant's services hereunder, Consultant, upon request from City, agrees to testify therein at a reasonable and customary fee. 27. Construction. This Agreement is the product of negotiation and compromise on the part of both Parties and that the Parties agree that, notwithstanding Civil Code section 1654, any uncertainty in the Agreement shall not be construed against the drafter of the Agreement. 28. GoverninLy Law, Venue. This Agreement shall be enforced and interpreted under the laws of the State of California and the City of Petaluma. Any action arising from or brought in connection with this Agreement shall be venued in a court of competent jurisdiction in the County of Sonoma, State of California. 29. Non -Waiver. The City's failure to enforce any provision of this Agreement or the waiver thereof in a particular instance shall not be construed as a general waiver of any part of such provision. The provision shall remain in full force and effect. 30. Severabilitv. If any term or portion of this Agreement is held to be invalid, illegal, or otherwise unenforceable by a court of competent jurisdiction, the remaining provisions of this Agreement shall continue in full force and effect. 31. No Third Partv Beneficiaries. The Parties do not intend to create, and nothing in this Agreement shall be construed to create any benefit or right in any third party. 32. Mediation. The Parties agree to make a good faith attempt to resolve any dispute arising out of this Agreement through mediation prior to commencing litigation. The Parties shall mutually agree upon the mediator and shall divide the costs of mediation equally. 7 PROFESSIONAL SERVICES AGREEMENT—PREVAILING WAGES 15 (1037730) August 2015 31 COUIS111611CS B0010 and Records. ( A. Consultant shall maintain my and all ledgers, books of accounts, invojr vouchers, canceled checks, and other records or documents evidencing or relating to charges for services, or expenditures and disbursements charged to the City for a Inuinnum period of three (3) year: or for any longer period required by law, from tire- date of final payment to Consultant pursuant to this Agreement. K Consultant shall maintain all documents and records which demonstrate pci-f6rmance under this Agreement for a minimum period of three (3) years or for any longer period required by law, from the date of termination or completion of this Agreement. Any records or documents required to be maintained pursuant to this Agreement shall be made available for inspection or audit, at an), time during regular business hours, upon written request by the City Manager, City Attorney, City Finance Dirmtor, or as designated representative of these officers. Copies of � .;uch documents shall be provided to the City for inspection at Petalurra City Hall when it is practical to do so- Otherwise, unless an alternative is mutually agreed upon, the records shall be available at Consultant's address indicated for receipt of notices in this Agreement. 1), Where City has reason to believe thatsuch records or docuinents may be lost or discarded due to dissolution, disbandment or termination of' Consu'Itant's business, City may, by written rcqucst by any of the above -earned officers' require that custody of the records be given to the City and that the records and documents be maintained in Petaluma City Hall. Access to such records and documents shall be granted to any party aUtborized by Consultant, Consultant's representatives, or Consultant's successor in interest, 34j1j1KAAjW. The headings, used in this Agreement are for convenience only and are not intended to affect the interpretation or construction of any provisions herein. 35. Survival. All obligations arising prior to the termination or expiration of this Agreement and all provisions of this Agreement allocating liability between City and Consultant shall survive the termination or expiration of this Agreement. 36. Elifire A . 9 L Ee Meast. This Agreement, including the exhibits attached hereto and incorporated herein, constitutes the entire agreement between the Parties witil 1-cspect to the Services, and supersedes all prior agreements or understandings, oral or written, between the Parties in this regard, IN WITN17-SS WHEREOF, the parties hereto have executed this document the day, month and year first above written. CITY OF PETALUMA CONSU1,TANT By Cit --4 "" -) , " — ,y Man�iger NanW AP PROFEWONALSERVICPS AOREEMENT— PRFVAjj,jN(j wN,r%GpS i 1011710) August 1015 16 ATTEST: 6ty Clerk APPROVED AS TO FORM: elf City Attomey A, APPR07,D:, "T Department Direc;tcsr Risk Manager A Pt� (A V c Dire I otor Title Address City state Zip I 'aXpayer LD. Number Petaluma Business Tax Certificate Number file mlmc5:1t,IPlI'siajccis4Pta�a asUSTE 16082012 1 -da l903WDcsip%l40 Consullatil Ag7ctmunt%140,04 201(1 PSA.docx 9 PROFESSIONAL SERVI(TS AGRI,'I'MENT— PREVAILING WAGF.s' (1037730) Aupusl 2015 17 EXHIBIT A UNDERGROUND STORAGE TANK SITE REMEDIATION FOR 301 PAYRAN STREET SCOPE OF WORK This proposed scope of work is to address residual source areas contributing to soil and groundwater impacts at 301 Payran Street, select the most cost-effective remedial technology for site mitigation, and implement the selected remedial alternative in as expeditious a fashion as feasible to obtain site closure in the shortest timeframe. The proposed scope of work includes preparing a Feasibility Study/Corrective Action Plan (FS/CAP); the feasibility study will include the three remedial technologies listed below: 1. Dual-phase extraction (multiphase) 2. In-situ oxidation using ozone/hydrogen peroxide 3. Soil over -excavation to remove soil in source areas The FS/CAP will include recommendations to conduct exploratory soil test trenches in areas identified where substantial residual soil contamination likely remains. Highly impacted soil serves as source material to groundwater and its removal should significantly shorten the timeframe to clean up groundwater. Soil analytical data and site observations will be used to assess the necessity for additional over -excavation at the time of the excavation of the exploratory soil trenches. As part of the FS/CAP, the Consultant may recommend the removal of fuel hydrocarbon -impacted soils (if present). The FS/CAP will also select the most cost efficient and technologically effective remediation technology to remediate FHC-impacted soil and groundwater to levels acceptable for site closure under the State Water Resource Control Board's Low Threat Closure Policy (LTCP). Based on available soil and groundwater analytical data, previous site remediation conducted at the site, and discussions with County of Sonoma Department of Health Services (CSDHS), it is likely that a dedicated Dual Phase Extraction (DPE) system will be selected as the most cost efficient and technologically effective remediation technology. Based on the CSDHS review and approval of the FS/CAP, the Consultant will implement and operate the approved remediation system for up to 24 months. During the operation of the system, the Consultant will review groundwater and influent stream analytical data, to determine the shortest time frame the system should operate to obtain site closure. When the site appears to meet LTCP criteria, the system will be turned off and up to one year of verification groundwater monitoring will be conducted to assess whether FHCs rebound in groundwater and if free product remains. Page I of 10 IN An estimated timeline is shown in the table below. Project Timeline Task Item £ampletaona A`ats FS/CAP s ubmittal to CSDHS September 1, 2016 FS/CAP approval Implement CAP Implement soil test trenches Results of soil test trenches (CAP addendum) to Client/CSDHS Submit remedial action plan/system design Project coordination system permitting BAAQMD acquisition Install remedial system Remedial system operation Groundwater monitoring COMPENSATION September 30, 2016 October 2016 October November 2016 November 2016 December 2016 December 2016 January -February 2017 February 2017 - February 2019 February 2017 - February 2020 Compensation shall be based on actual time and materials expended to complete each of the project tasks. The detailed tasks have been included at the end of this Exhibit A. The Consultant will not proceed beyond Task 1 Feasibility Study/Corrective Action Plan (FS/CAP) without prior written approval from the City. In addition, the total compensation for any one task shall not exceed the total amount indicated for that task without prior written approval from the City. Note: Estimated task and costs for active remediation are based on the approval of a dual phase extraction system and may change with the review and approval of the FS/CAP. PROJECT TEAM ORGANIZATION The professional staff for this project was selected based on their particular expertise and experience with the type of work proposed. Each individual has been allotted a specific budget for their task(s) in the project. Mr. John Calomiris, Technical Operations Manager/Associate, (25 years professional experience) will manage the project and be responsible for maintaining communications with the City of Petaluma to verify that project activities are proceeding as planned, and that any potential problems are addressed in a timely manner. Additionally, Mr. Calomiris' responsibilities include keeping the project on schedule and within the budget. Finally, he will review and edit the various work plans, fee estimates and reports. EXHIBIT A Page 2 of 10 19 Mr. Richard Ely, Senior Professional Geologist, (30+ years professional experience) will perform the final technical review and edit of work plans, corrective and remedial action plans, and other project reports. He will be responsible for evaluation of soil and groundwater conditions at the site, delineating locations requiring remediation and/or additional investigation, and directing the preparation of a plan for acquiring the data needed to proceed directly toward site closure. Mr. Ely will establish how to best proceed with the investigative aspects of the project and working with Mr. Wingard design a remediation system for the site. Mr. Brian Wingard, Project Geologist and Remediation Specialist (17 years professional experience) will work with Mr. Ely on the evaluation of site conditions, preparation of the FS/CAP, and later the RAP. Additionally, Mr. Wingard's primary responsibility will be for design, construction, installation, operation and maintenance of the remediation system. Mr. Kevin Coker, Project Scientist (18 years professional experience) will oversee field, site soil investigations, collect samples for analyses, map trench/excavation locations, and profile soils for disposal. Additionally, Mr. Coker prepares our fee estimates. Mr. Derrick Crayford, Field Technicians, (8 years professional experience) will perform groundwater monitoring events, participate in construction of the remediation system, and maintain its operation. The table below presents a general project contact list. ly'rauel -77 John Calomiris Project Managed Associate Project Contact Last 707 484-7241 iohncCo)cddclarkandassociates.com Richard Ely Senior 707792-9500 richarde(i,eddelarkandassociates.com Professional Geologist Brian Wingard Project 707 292-7658 brianwCa),eddelarkandassociates.com Geologist Remediation Specialist Kevin Coker Project 707 326-9915 keviiic(i4eddclarkaiidassociates.com Scientist Derrick Crajford O&MField 707 888-8055 derrickc(ia eddelarkandassociates.com Technician EXHIBIT A Page 3 of 10 20 FS/CAP, Remediation, Groundwater Monitoring and Contingency Costs 301 Payran Street, Petaluma, CA Task 01: Preparation of Feasibility Study/Corrective Action Plan 8 @ $155.00 thr. $1,240.00 Project Manager 2 @ $155.00 /hr. $310.00 Professional Geologist 4 @ $165.00 /hr. $660.00 Project Engineer/Geologist 14 @ $139.00 /hr. $1,946.00 Project Geologist 22 @ $119.00 /lm•. $2,618.00 Clerical 8 ( @ $60.00 /hr. $480.00 Total Task 01 ( $6,014.00 Task 02: Project Management, Permitting and Pre -field Activities Project management through excavation of two exploratory trenches/test pits, the installation and up to 24 -months of operation of a high vacuum dual phase extraction (DPE) system, and up to three years of groundwater monitoring and reporting. Pre -field activities includes acquisition of an air permit from the Bay Area Air Quality Management District (BAAQMD), coordination with the City of Petaluma for the proposed excavation, discharging extracted groundwater, and public notice preparation and distribution for the air district as part of their permit requirements. Project Manager 92 @ $155.00 /hr. $14,260.00 Project Engineer/Geologist 36 @ $139.00 /hr. $5,004.00 Project Geologist 36 @ $119.00 /hr. $4,284.00 BAAQMD air permit fees ($5200/year; assumes 2 yrs) ($5200/year) $10,400.00 Clerical 110 I @ $60.00 /hr. $6,600.00 Total Task 02 1 $40,548.00 Task 03: Preparation of Remedial Action Plan/System Engineering Design Project Manager 8 @ $155.00 thr. $1,240.00 Professional Geologist I 8 @ $165.00 /hr. $1,320.00 Project Engineer/Geologist 24 @ $139.00 /hr. $3,336.00 Project Geologist 14 @ $119.00 /hr. $1,666.00 Clerical 8 I @ $60.00 /hr. $480.00 Total Task 03 $8,042.00 EXHIBIT A Page 4 of 10 21 Task 04a: Soil Excavation (Subcontractor) and Sample Collection (EC&A) Includes overseeing the excavation of two test pit/trenches, one in the vicinity of the former UST and extending towards the location of DPE-1 (Area A), and one in the general vicinity of DPE-2 and DPE-5 (Area B). The trenches are proposed to be approximately 25 ft long, 6 -ft wide and 10 ft deep. Based on the proposed excavation areas, approximately 115 tons of soils are proposed for excavation. Costs for soil disposal are presented in Task 4C as unit costs and based on available information at the time of preparation of this Estimate. Additional costs which may be incurred as a result of additional excavation will be billed at the rates listed below. Costs presented below assume soil is loaded and transported to Potrero Hills, a Class 11 Landfill in Suisun City, CA. If groundwater is encountered (which is not expected based on the maximum anticipated depth of 10 ft bgs) in the excavation trenches, it will have to be pumped into a storage tank, sampled, and transported to an offsite disposal facility. if groundwater is not encountered in sufficient quantities, the costs detailed below will not be incurred. Soil Excavation I Soil Excavation (Subcontractor) Professional Geologist (lump sum; — $22,000) 2 @ 165 $/hr. $22,000.00 $330.00 Project Geologist I 12 @ 119 I $/1... I $1,428.00 Photoionization Detector (PID) I 1 @ 132 1 $/day 1 $132.00 Soil Sample Tubes I 14 I @ 8 I $/each I $112.00 Misc. Field Supplies i 1 I @ 33 I $/day I $33.00 I Groundwater Management If groundwater is encountered in sufficient quantities, which is not expected, it would have to be pumped fi•om the excavation into an onsite fisc tank, sampled and disposed at a permitted offsite disposal facility. Costs outlined below assume 10,000 -gallons of groundwater. Actual costs incurred would be based on volume of groundwater encountered at $0.38/gallon, $125/hr for transportation and additional associated contractor costs up to approximately $1300/project. Project Geologist Water Tank Rental (21,000 -gallon tank) Water Tank Delivery and Pick-up (— 5 hrs) Water pump, hose & labor Disposable Bailers Groundwater Samples (from excavation & water tank; 24 -hr TAT) TPHg 1 0 BTEX, MTBE & Naphthalene I 0 1 @ I EDF Report I 0 I nn. Total Task 04a Task 04b: Confirmation Soil Sampling and Stockpile Sample Anaiv ses (5 -day TAT) TPI -Ig 11 @ BTEX, MTBE & Naphthalene 11 @ EDF Report I 1 @ Total Task 04b EXHIBIT A Page 5 of 10 119 $/hr. $0.00 28 $/day $0.00 115 $/hr. $0.00 407 ( $/job I $0.00 11 I S/each ( I I I I $0.00 124.30 1 $/Sample 1 $0.00 242.00 I $/Sample I $0.00 30.80 I $/Sample ( i $0.00 I I I I $24,035.00 55.00 $/Sample j� $605.00 121.00 I $/Sample I $1,331.00 30.80 ( $/Sample I $30.80 i $1,966.80 W Task 04c: Landfill Profiling & Disposal Project Geologist 4 1 @ 114 $/hour S476.40 Landfill Waste Accept. Fees ($20/ton) 115 @ 20.00 $/ton $2,300.00 Total Task 04c I $2,776.00 Total Task 04 1 $28,777.80 Task 05: DPE and Groundwater Treatment System Procurement I I Coordination with venders on lease/purchase contract for DPE system included in Task 1, Project Management. Vender (Mako Industries) I I I 20/25 horsepower soil vapor extraction (DPE) system (24 month lease $68400.00 + 5% mark-up $71,820.00 at $2850 monthly) Perform system installation and construction activities, including (but not limited to) installing minimum 3 -inch Sch-80 PVC Thermal/catalytic oxidizer use fee $1750 + 5% mark-up I $1,850.00 Thermal/catalytic oxidizer installation fee $750 + 5% mark-up $788.00 Liquid phase carbon vessels (2-1000-1b vessels) $10800 + 5% in S11,340.00 Wireless telemetry/dedicated phone line installation $0 + 5% markup ( $0.00 Freight delivery of DPE system and taxes I @ $2,000.00 /each $2,000.00 Forklift rental for DPE skid I @ $225.00 /day $225.00 Total Task 05 I $88,023.00 Task 06: Sy=stem Construction/Trenching/Piping Connection Perform system installation and construction activities, including (but not limited to) installing minimum 3 -inch Sch-80 PVC conveyance piping, 1 1/4 -inch flex tubing connection to extraction wells and well head assembly. Electrical connection provided by subcontractor (100 amp/3-phase). Above ground piping will be used where appropriate to reduce underground excavation costs. Details of extraction line trench(s) and above ground segments will be included in the Remedial Action/System Design phase. System Installation Labor I Project Engineer/Geologist ' 16 1 @ $139.00 /hr. $2,224.00 Senior Field Engineer 40 @ $92.00 /hr. $3,680.00 Field Construction Tech 60 @ $79.00 /hr. $4,740.00 System Installation Materials/Equipment 1 1/4 PEF flexible extraction tubing 1000 @ $4.04 /foot $4,040.00 3 -inch Sch-80 PVC conveyance piping 400 I @ S3.57 /foot $1,428.00 Sch-80 PVC fittings/suction connectors/glue, etc. (lump sum) $800.00 Dwyer vacuum gauges 6 @ I $94.00 I /gauge $564.00 Backfill Material (if suitable will re -use existing backfill) (lump sum) $1,200.00 Asphalt cutter 2 @ $300.00 /day $600.00 Trenching (digger rental) 2 @ $250.00 /day $500.00 Compaction (handheld vibra compactor) 2 @ $125.00 /day 5250.00 Electrical installation/connection (subcontractor) (lump sum) $6,200.00 EXHIBIT A Page 6 of 10 23 PG&E electrical drop/connection to sub -panel ( ( (lump Sulu) Professional Geologist $1,200.00 System compound/Security Fence include electrical service and propane usage for oxidizer vapor abatement. O&M visits will include collecting system performance (lump sum) $1,600.00 Total Task 06 Project Geologist 24 I @ Project Manager $29,026.00 Task 07: DPE System Startup Procedures /hr. $6,200.00 Project Engineer/Geologist ( 120 @ $139.00 System startup procedures with contractor/vender personnel. Includes all tasks associated with DPE system startup but not limited to), testing the system, electrical inspection and system performance evaluation and setting up the telemetry network if installed. $79.00 Project Manager 2 @ $155.00 /hr. $310.00 Project Engineer/Geologist 12 @ $139.00 /hr. $1,668.00 Field Construction Tech 16 @ $79.00 /br. $1,264.00 Startup assistance (vender/subcontractor) $24,000.00 Propane (liquid gas), based on 1.5 gallons per/minute (lump sum) $800 Misc. Field Supplies 2 @ $33.00 1 /day $66.00 DO/ORP Meter 2 @ $45.00 /day $90.00 Tedlar bags (vapor samples) 6 @ $16.50 /sample $99.00 TPHg/BTEX (8015/8010) 4 @ $110.00 /sample $440.00 Total Task 07 1 $4,737.00 Task 08: DPE System Operation and Maintenance (up to 24 -months) 2 @ $165.00 /hr. $330.00 Professional Geologist Following system startup, and BAAQMD air board emission requirements, the system will be inspected weekly for operation. Costs include electrical service and propane usage for oxidizer vapor abatement. O&M visits will include collecting system performance 18 I @ readings, vapor samples from the extraction wells, system manifold and vapor abatement stack. Project Geologist 24 I @ Project Manager 40 @ $155.00 /hr. $6,200.00 Project Engineer/Geologist ( 120 @ $139.00 /hr. $16,680.00 Field Engineer 420 @ $79.00 /hr. $33,180.00 Misc. Field Supplies 60 @ $33.00 /day $1,980.00 DO/ORP Meter 30 ( @ $53.00 /day $1,590.00 Electrical Usage (Estimated based on system) 24 @ $1,000.00 /month $24,000.00 Propane (liquid gas), based on 1.5 gallons per/minute 24 @ $2,000.00 /month $48,000.00 Tediarbags 120 @ $16.50 /sample $1,980.00 Vapor analysis (TPHg, BTEX 8015/8010) 60 @ $110.00 /sample $6,600.00 Total Task 08 1 $140,210.00 Task 09: System Installation and Startup Report I I Report will include the results of the pre-DPE groundwater monitoring event, DPE system installation activities and system startup procedures and sampling. Project Manager 2 @ $165.00 /hr. $330.00 Professional Geologist 4 I @ $165.00 /hr. $660.00 Project Engineer/Geologist 18 I @ $139.00 /hr. $2,502.00 Project Geologist 24 I @ $119.00 Am $2,856.00 EXHIBIT A Page 7 of 10 24 Drafting ( 6 @ I $73.00 /hr. $438.00 Clerical 6 @ $60.00 /hr. $360.00 GeoTracker Submittal I 1 @' $79.00 /hr. $79.00 I I Total Task 09 I I ( I $7,225.00 Task 10a: Groundwater Monitoring (Includes 6 Events) I I I Costs below assume semi-annual groundwater monitoring as approved by the CSDHS in their September 14, 2014 regulatory letter to consist of sampling of all 15 monitoring wells. However, due to the presence of free phase floating product and absorbent socks installed, MW -5, MW -8, MW -13, DPE-2, DPE-5 and DPE-6 were not sampled during the most recent monitoring event in February 2016. Costs below assume sampling of all 15 wells; if the presence of fi•ee phase floating product and/or absorbent socks prevents the sampling of these wells, the costs detailed below will be reduced. Also included in the cost estimate for groundwater monitoring are costs for purge water disposal and absorbent socks replacement. The groundwater monitoring program and costs for groundwater monitoring will likely change as remediation progresses. Sample Collection(l) Professional Geologist I 1 @ $165.00 /hr. $165.00 Environmental Technician I 20 @ $79.00 /hr. $1,580.00 Submersible Pump I 3 I@ I $45.00 I /day I $135.00 Oil -water Interface Probe 13 I@ I $33.00 I /day I $99.00 Field Parameters Meter (DO/ORP/IDS/EC/Temp/EC) I 3 I @ I $100.00 I /day I $300.00 Disposable Bailees I 15 I @ I $11.00 I /each I $165.00 55 -Gallon DOT Drum (reconditioned) I 4 I @ I $25.00 I /each $100.00 Misc. Field Supplies ( 3 I @ ( $33.00 ( /day I $99.00 Groundwater Sample Analyses TPHg/BTEX/MTBE by Method 8015/8021 I 15 I @ I $55.00 I /Sample I $825.00 EDF Report Format I l I@ I $30.80 I /Report I $31.00 I I I I I (1): Note, that there are currently SoakEasc- absorbent socks installed in MW -5, MW -8, MW -13, DPE-2, DPE-5 and DPE-6. The absorbent socks are replaced as necessary at the time of groundwater monitoring. Installed in MW -5, MW -8 and MW -13 are also steel canisters in which the absorbent socks are installed. During the February 2016 groundwater monitoring event, the consultant ( West Yost), recommended the installation of steel canisters in DPE-2, DPE-5 and DPE-6. If the CSDHS concurs with this recommendation, additional costs for the steel canisters will be incurred at the unit rates listed above; absorbent socks will be replaced as determined necessary at the time of groundwater sampling and additional costs incurred at the unit rates listed below. SoakEaseT" Absorbent Socks (2 -inch) ( 0 @ $12.50 /each $0.00 SoakEaseTM Absorbent Socks (4 -inch) I 0 @ $13.50 /each $0.00 SoakEaseT" Absorbent Sock Canister (2 -inch) I 0 @ $178.00 /each $0.00 SoakEaseT" Absorbent Sock Canister (4 -inch) I 0 I @ I $234.00 /each I $0.00 Total Task 10a per Event I I I I I I I I I I $3,499.00 Total Task 10a for 6 Events I I ( ( ( I I $20,994.00 ) Task 10b: Groundwater Monitoring & Remediation System O&M Report Preparation I I I Note that costs for reporting assume installation of a DPE remediation system and will include remediation system operations & management (O&M) will be included. Project Manager i 1 I@ I $155.00 I /hr. i $155.00 EXHIBIT A Page 8 of 10 25 Professional Geologist 4 @ $165.00 /hr. $660.00 Project Engineer/Geologist 4 @ $139.00 /hr. $556.00 Project Geologist 14 @ $119.00 /hr. $1,666.00 Drafting 5 @ $73.00 /hr. $365.00 Clerical 6 @ $60.00 /hr. $360.00 GeoTrackcr Submittal 1 @ $79.00 /hr. $79.00 Total Task 10b per Event 1 @ $79.00 /hr. $3,841.00 Total Task 10b for 6 Reports $23,046.00 Total Task 10 ` $44,040.00 Task 11: Wash/Decon Water Drum Disposal (Assumes Semi -Annual Pick-up/Disposal) Costs below assume generation of 4 55 -gallon drums of purge/decon water per semi-annual monitoring event for a total of 24 drums over the course of three years. Note that if a DPE remediation system is installed at the site, purge/decon water can be treated through the system and the costs detailed below will not be incurred. EC&A Personnel (profiling, coordination) 6 (a7 99 $/hour $594.00 Waste Decon/Purge Water (Empty, leave on site) 24 @ 39 $/Drum $936.00 Waste Decon/Purge Water (Remove Drum) 24 @ 55 $/Drum $1,320.00 Waste Decon/Purge Water (Transportation) 6 @ 150 $/run $900.00 * = assumes non -hazardous 4 @ $73.00 /hr. $292.00 Total Task 11 (Drums emptied, left on site) $2,430.00 Total Task 11 (Remove drums) $2,814.00 Task 12: Remediation System O&M Report Preparation Project Manager 1 @ $165.00 /br. $165.00 Professional Geologist 2 @ $165.00 /hr. $330.00 Project Engineer/Geologist 4 @ $139.00 /hr. $556.00 Project Geologist 12 @ $119.00 /hr. $1,428.00 Drafting 4 @ $73.00 /hr. $292.00 Clerical 4 @ $60.00 N% $240.00 GeoTracker Submittal 1 @ $79.00 /hr. $79.00 Total Task 12 per Report $3,090.00 Total Task 12 for 12 Reports ` $37,080.00 I II SUBTOTAL: REMEDIATION & GROUNDWATER MONITORING COSTS (3 -YEARS) ( $436,152.80 CONTINGENCY COSTS I Contingency costs are for over -excavation, extraction well installation, and/or unforeseen conditions as site work progresses. EXHIBIT A Page 9 of 10 R CONTINGENCY COSTS SUBTOTAL TOTAL PROJECT COSTS @ 1 $70,000.00 Edd dark & Associates, Inc. Schedule of Charges 2016 $506,152.80 UC&A has designed this schedule of charges to be competitive with current market conditions~ and fees demanded by competitor firms. The fees charged by EUA will be: 1) unit hourly rates for all employees; 2) unit hourly or daily rates for all Geld and safety equipment; and 3) cost plus 5% for subcontractors. The Pecs charged by EC&A are as followx: Principal P-ngineedGeologist $ 163/hour Project Manager $155/hour Senior E;T1neer/Geologist $139/hour Projcet/Associate Enginecr/Gcologist $1 d91bour Staff Engineer/Geologist $991hour Senior Technician $921hour EnvironmentaUfield Toelmician $79kour Dra rwn $73/hour Clerical $60/hour deepen WitnesVDepositions $225/hour Cather Charges,. Purge Pump S20/day (l day min) Submersibic Pump S59/day 0 day min) Peristaltic Pump $451day (I day min) Band Augerld:quip. S33/day 0 day min) Gastech S50/day (l day min) PID St32/day (1 day min) Water -level Meter 333/day(1 daymin) Conductivity Meter S53./day (1 day min) Oil/Water Meter $53/day (l day rain) DO Meter S531day (l day min) ORP Meter $401 day (I day ruin) Ozone Meter 5401day (I day min) Turbidity Meter 526/day (1 day nun) Disposable Bailors S11/bailcr Misc. Sampling liens $331day Replacement Well Lock $13/lock Replacement Locking Well Cap (2") S26/cap Replacement locking Well Cap (41 329/cap Vehicle S0.5751mi Sample Tubes (brass) S81tube Sample Tubes (stainless) $13/tube FtteoroSamplers (5 gram) SI 1.5Wdach DOT 171 -155 -gallon Drums (new) S53/drum Drums (reconditioned) $25/drtun 4" Pump $125/day Flow Meter $30 day Prints and Materials Cost + $% Subcontractors Cost + 3% Miscellaneous Expenses Cort + 5% GPS Survey $150.00 per well + travel 1000 gad. Water -storage Tank $17/day The foes for other equipment netded to completaa project will be made available at the time ofproposal preparation or contract negotiations. EXHIBIT A Page 10 of 10 27 INSURANCE REQUIREMENTS EXHIBIT B-2 Consultant's performance of the Services under this Agreement shall not commence until Consultant shall have obtained all insurance required under this paragraph and such insurance shall have been approved by the City Attorney as to form and the Risk Manager as to carrier and sufficiency. All requirements herein provided shall appear either in the body of the insurance policies or as endorsements and shall specifically bind the insurance carrier. Consultant shall procure and maintain for the duration of the contract all necessary insurance against claims now and in the future for injuries to persons or damages to property which may arise from or in connection with the performance of the Services by the Consultant, the Consultant's agents, representatives, employees and subcontractors. Required professional liability insurance shall be maintained at the level specified herein for the duration of this Agreement and any extension thereof and for twelve additional months following the Agreement termination or expiration. A. Minimum Scope of Insurance Coverage shall be at least as broad as: I Insurance Services Office Commercial General Liability coverage: a. Personal injury; b. Contractual liability. 2. Insurance Services Office form covering Automobile Liability, code I (any auto). 3. Workers' Compensation insurance as required by the State of California and Employer's Liability Insurance. 4. Professional Liability insurance. 5. Such other insurance coverages and limits as may be required by the City. B. Minimum Limits of Insurance Consultant shall maintain limits no less than: I General Liability: $1,000,000 per occurrence for bodily injury, personal injury and property damage. If Commercial General Liability Insurance or other form with a general aggregate liability is used, either the general aggregate limit shall apply separately to this Agreement or the general aggregate limit shall be twice the required occurrence limit. 2. Automobile Liability: $ 1,000,000 per accident for bodily injury and property damage. 3. Employer's Liability: Bodily Injury by Accident - $ 1,000,000 each accident. Bodily Injury by Disease - $ 1,000,000 policy limit. Bodily Injury by Disease - $ 1,000,000 each employee. 4. Professional Liability insurance: $ 1,000,000. 5. Such other insurance coverages and limits as may be required by the City. C. Deductibles and Self -Insured Retentions Any deductibles or self-insured retentions must be declared to and approved by the City. At the option of the City, either: the insurer shall reduce or eliminate such deductibles or Exhibit B2 Pagel of INSURANCE REQUIREMENTS (City) (609325) August 2015 28 self-insured retentions as respects the City, its officers, officials, employees, and volunteers; or the Consultant shall procure a bond guaranteeing payment of losses and related investigations, claim administration and defense expenses. D. Other Insurance Provisions The required general liability and automobile policies are to contain, or be endorsed to contain the following provisions: I The City, its officers, officials, employees, agents and volunteers are to be covered as Additional Insureds as respects: liability arising out of activities performed by or on behalf of the Consultant; products and completed operations of the Consultant; premises owned, occupied or used by the Consultant; or automobiles owned, leased, hired or borrowed by the Consultant. The coverage shall contain no special limitations on the scope of protection afforded to the City, its officers, officials, employees, agents or volunteers. 2. For any claims related to this project, the Consultant's insurance coverage shall be primary insurance as respects the City, its officers, officials, employees, agents and volunteers. Any insurance or self-insurance maintained by the City, its officers, officials, employees, agents or volunteers shall be excess of the Consultant's insurance and shall not contribute with it. 3. Any failure to comply with reporting or other provisions of the policies including breaches of warranties shall not affect coverage provided to the City, its officers, officials, employees, agents or volunteers. 4. The Consultant's insurance shall apply separately to each insured against whom claim is made or suit is brought except, with respect to the limits of the insurer's liability. 5. Each insurance policy required by this clause shall be endorsed to state that coverage shall not be suspended, voided, canceled by either party, reduced in coverage or in limits except after thirty (30) days' prior written notice by certified mail, return receipt requested, has been given to the City. 6. Consultant agrees to waive subrogation rights against City regardless of the applicability of any insurance proceeds, and to require all contractors, subcontractors or others involved in any way with the Services to do likewise. 7. It shall be a requirement under this Agreement that any available insurance proceeds broader than or in excess of the specified minimum insurance coverage requirement and/or limits shall be available to the additional insured. Furthermore, the requirement for coverage and limits shall be (1) the minimum coverage and limits specified in this Agreement, or (2) the broader coverage and maximum limits of coverage of any insurance policy or proceeds available to the named insured; whichever is greater. S. The limits of insurance required in this Agreement may be satisfied by a combination of primary and umbrella or excess insurance. Any umbrella or excess insurance shall contain or be endorsed to contain a provision that such coverage shall also apply on a primary and non-contributory basis for the benefit of the City of Petaluma before the City of Petaluma's own insurance or self-insurance shall be called upon to protect it as a named insured. Exhibit B2 Page 2 of 2 INSURANCE REQUIREMENTS (City) (609325) August 2415 29 E. Acceptability of Insurers Insurance is to be placed with insurers with a current A.M. Best's rating of no less than ANIL F. Verification of Coverage Consultant shall furnish the City with original endorsements effecting coverage required by this clause. The endorsements are to be signed by a person authorized by that insurer to bind coverage on its behalf. All endorsements are to be received and approved by the City before the Services commence, Exhibit B2 Page 3 of 2 INSURANCE REQUIREMENTS (City) (609325) August 2015 30 PREVAILING WAGE EXHIBIT C HOURS OF WORK: A. In accordance with California Labor Code Section 1810, eight (8) hours of labor in performance of the Services shall constitute a legal day's work under this Agreement. B. In accordance with California Labor Code Section 1811, the time of service of any worker employed in performance of the Services is limited to eight hours during any one calendar day, and forty hours during any one calendar week, except in accordance with California Labor Code Section 1815; which provides that work in excess of eight hours during any one calendar day and forty hours during any one calendar week is permitted upon compensation for all hours worked in excess of eight hours during any one calendar day and forty hours during any one calendar week at not less than one -and -one-half times the basic rate of pay. C. The Consultant and its subconsultants shall forfeit as a penalty to the City $25 for each worker employed in the performance of the Services for each calendar day during which the worker is required or permitted to work more than eight (8) hours in any one calendar day, or more than forty (40) hours in any one calendar week, in violation of the provisions of California Labor Code Section 1810 and following. WAGES: A. In accordance with California Labor Code Section 1773.2, the City has determined the general prevailing wages in the locality in which the Services are to be performed for each craft or type of work needed to be as published by the State of California Department of Industrial Relations, Division of Labor Statistics and Research, a copy of which is on file with the City and shall be made available on request. The Consultant and subconsultants engaged in the performance of the Services shall pay no less than these rates to all persons engaged in performance of the Services. B. In accordance with Labor Code Section 1775, the Consultant and any subconsultants engaged in performance of the Services shall comply Labor Code Section 1775 which establishes a penalty of up to $50 per day for each worker engaged in the performance of the Services that the Consultant or any subconsultant pays less than the specified prevailing wage. The amount of such penalty shall be determined by the Labor Commissioner and shall be based on consideration of the mistake, inadvertence, or neglect of the Consultant or subconsultant in failing to pay the correct rate of prevailing wages, or the previous record of the Consultant or subconsultant in meeting applicable prevailing wage obligations, or the willful failure by the Consultant or subconsultant to pay the correct rates of prevailing wages. A mistake, inadvertence, or neglect in failing to pay the correct rate of prevailing wages is not excusable if the Consultant or subconsultant had knowledge of their obligations under the California Labor Code. The Prevailing Wage Exhibit for Service Agreements Provisions Required Pursuant to California Labor Code § 1720 et seq. (1037770)(Sept 2OO7) 31 Consultant or subconsultant shall pay the difference between the prevailing wage rates and the amount paid to each worker for each calendar day or portion thereof for which each worker was paid less than the prevailing wage rate. If a subconsultant worker engaged in performance of the Services is not paid the general prevailing per them wages by the subconsultant, the Consultant is not liable for any penalties therefore unless the Consultant had knowledge of that failure or unless the Consultant fails to comply with all of the following requirements: 1. The Agreement executed between the Consultant and the subconsultant for the performance of part of the Services shall include a copy of the provisions of California Labor Code Sections 1771, 1775, 1776, 1777.5, 1813, and 1815. 2. The Consultant shall monitor payment of the specified general prevailing rate of per them wages by the subconsultant by periodic review of the subconsultant's certified payroll records. 3. Upon becoming aware of a subconsultant's failure to pay the specified prevailing rate of wages, the Consultant shall diligently take corrective action to halt or rectify the failure, including, but not limited to, retaining sufficient funds due the subconsultant for performance of the Services. 4. Prior to making final payment to the subconsultant, the Consultant shall obtain an affidavit signed under penalty of perjury from the subconsultant that the subconsultant has paid the specified general prevailing rate of per them wages employees engaged in the performance of the Services and any amounts due pursuant to California Labor Code Section 1813. C. In accordance with California Labor Code Section 1776, the Consultant and each subconsultant engaged in performance of the Services, shall keep accurate payroll records showing the name, address, social security number, work classification, straight time and overtime hours worked each day and week, and the actual per them wages paid to each journeyman, apprentice, worker, or other employee employed in performance of the Services. Each payroll record shall contain or be verified by a written declaration that it is made under penalty of perjury, stating both of the following: 1. The information contained in the payroll record is true and correct. 2. The employer has complied with the requirements of Sections 1771, 1811, and 1815 for any Services performed by the employer's employees on the public works project. The payroll records required pursuant to California Labor Code Section 1776 shall be certified and shall be available for inspection by the Owner and its authorized representatives, the Division of Labor Standards Enforcement, the Division of Apprenticeship Standards of the Department of Industrial Relations and shall otherwise be available for inspection in accordance with California Labor Code Section 1776. In addition, Consultant and sub -consultant shall be required to be registered with the Department of Industrial Relations pursuant to Labor Code section 1725.5. Consultant 2 Prevailing Wage Exhibit for Service Agreements Provisions Required Pursuant to California Labor Code § 1720 et seq. (1037770) (Sept 2007) 32 and any sub -consultant shall submit certified payroll records to the Department of Industrial Relations Labor Commissioner online: htt-ps:Ha-pt)s.dir.ca.gov/ecl)r/DAS/AltLogin. Consultant is responsible for ensuring compliance with this section. D. In accordance with California Labor Code Section 1777.5, the Consultant, on behalf of the Consultant and any subconsultants engaged in performance of the Services, shall be responsible for ensuring compliance with California Labor Code Section 1777.5 governing employment and payment of apprentices on public works contracts. E. In case it becomes necessary for the Consultant or any subconsultant engaged in performance of the Services to employ on the Services any person in a trade or occupation (except executive, supervisory, administrative, clerical, or other non manual workers as such) for which no minimum wage rate has been determined by the Director of the Department of Industrial Relations, the Consultant shall pay the minimum rate of wages specified therein for the classification which most nearly corresponds to Services to be performed by that person. The minimum rate thus furnished shall be applicable as a minimum for such trade or occupation from the time of the initial employment of the person affected and during the continuance of such employment. file name: 3 Prevailing Wage Exhibit for Service Agreements Provisions Required Pursuant to California Labor Code § 1720 el seq. (1037770)(Sept2007) 33 EXHIBIT D ACKNOWLEDGEMENT AND CERTIFICATION PURSUANT TO CITY OF PETALUMA LIVING WAGE ORDINANCE PETALUMA MUNICIPAL CODE CHAPTER 8.36 The City of Petaluma Living Wage Ordinance ("Ordinance"), Petaluma Municipal Code Chapter 8.36, applies to certain service contracts, leases, franchises and other agreements or funding mechanisms providing financial assistance (referred to hereafter as an "Agreement") between the City of Petaluma ("City") and/or the Petaluma Community Development Commission ("PCDC") and contractors, lessees, franchisees, and/or recipients of City and/or PCDC funding or financial benefits ("covered entities"). Pursuant to Petaluma Municipal Code Section 8.36.120, as part of any bid, application or proposal for any Agreement subject to the Ordinance, the covered entity shall: • Acknowledge that the covered entity is aware of the Ordinance and intends to comply with its provisions. Complete the Report of Charges, Complaints, Citations and/or Findings contained in this Acknowledgement and Certification by providing information, including the date, subject matter and manner of resolution, if any, of all wage, hour, collective bargaining, workplace safety, environmental or consumer protection charges, complaints, citations, and/or findings of violation of law or regulation by any regulatory agency or court including but not limited to the California Department of Fair Employment and Housing, Division of Occupational Safety and Health (OSHA), California Department of Industrial Relations (Labor Commissioner), Environmental Protection Agency and/or National Labor Relations Board, which have been filed or presented to the covered entity within the ten years immediately prior to the bid, proposal, submission or request. Pursuant to Petaluma Municipal Code Section 8.36.120, before the beginning of the term of any covered Agreement, or prior to the execution of said Agreement by the City or the PCDC, each covered entity shall certify that its employees are paid a living wage that is consistent with Petaluma Municipal Code Chapter 8.36. By executing this Acknowledgement and Certification, the covered entity (i) acknowledges that it is aware of the Ordinance and intends to comply with its provisions, (ii) attests to the accuracy and completeness of information provided in the Report of Charges, Complaints, Citations and/or Findings contained herein, (iii) certifies that it pays its covered employees a Living Wage as defined in Petaluma Municipal Code Chapter 8.36 and (iv) attests that the person executing this Acknowledgement and Certification is authorized to bind the covered entity as to the matters covered in this Acknowledgment and Certification. Page I of 3 LIVING WAGE ACKNOWLEDGEMENT AND CERTIFICATION (1638697.2) Nov 2012 34 SO ACKNOWIjiDGED and CERTIFIED: Prqject or Contract I,D: Remediation and Groundwater Monitorinfo i -Se.rvioe - 301 Pa ~an St. 9- s 7� Da,te: (Ptint Name off'overed Entity/Business Cd'picity) -4— By (Print Name) its (Title /Capacity of Authorized Signer) Page 2 ot'3 LIVING WA( -,,r- ACKN()Wj-j;DCor,,Mr AND CERTIVICA-rION 063809U) Nov 2012 35 REPORTOF CHARGES, COMPLAINTS, CITATIONS At IVOR FINDINGS PURSUANT TO PETALUMA MUNICIPAL CODE SECTION 8.36.1 20 FOR F'ACI I WAG , HOUR, C0I_I.1C1'IVI-,. 13ARGAININ(l, WORKPI _ACE SAFETY, ENVIRONMEN FAL OR CONSI TMER PROTECTION Cl JARGE, COMPLAINT, I'FATION, AND/OR FINDING OF VIOLATION 01: LAW OR R LOULATION BY ANY REGIJ LATORY AGENCY OR CIOURT, INCLUDING BUT NOT HN4 J_)'I_0TF1I; CALIFORNIA DETARTMENT 017 FAIR EmPLOYNIT."NTAND HOUsiNci, DivIsioN OFOC( , 'UPATIONAL SAFUTY AND HEALTH (CISHA), CALIFORNIA DEPAR"I'MYNTOF INDUSTRIAL RET.Allo-Ns (LABOR COMMISSIONER), FNVIRONMENTAL PROTECTION Ac,[,'N('Y AND/M NA"FIONAL, LABolz R.171-A,rio-im's BOARD, WHICH: AFFECTS YOU AS A ]'IZOSPIr(-'IIVF-,('ONI'iZAC'I'OR, SUBCONTRACTOR, LESSI-T, FRANCIIISFrF AND/OR PART)"I'(1) ANY C11 Y OF 193'rA1,.UMA ANIVOR PHTALUMA COMMUNITY DEVI:1-01)'MFNI'C'ON,li\IISSION-[-I INDF`D AGREIMi"NT OR BENCI!`FSIIBJECTTO PETALUMA MIJINICIVAL C("aDECHAPTER 836 (LiVINCi WAG L 01u)INANCE), AND 'ryiEnN YEARS IMMEDIATELYPRIOR TO FHE BID, PROPOSAL, SUBMISSION OR RL;QUES'J- Fol!z wl:ilctrrws A(.XNOWLEDGI1M1_-_N_I_ AND CH(TIFICATION, IS MADE. I'MASEPROVIDE TIM DATF,,THE RFOULATORY AGEINCY OR COURTMAKINGTHE CHARGE COMPLAINT, CITATION OR FINDING, I HE SUBJECT MATT[T AND THE MANNER OFRESOLLITION" IT ANY, FOR EACH SUCH CHARGE COMPLAINT, CITATION OR FINDJNG 11"NONE', PLEASE STATE"NONE": �,"­ : , .- ATTACH ADDITIONAL PAGF'S ir NEEDEJ). Em Regulatory Agency or Court: su0ject Matter Resolution, if any. Expecte(liesoltition.it'knowii-, ___ 11age 3 of 3 LIVING WACA7 AC KNOW LET)OF N1 I;N'I AND CERTIFICA1 ION P 16.1''5697,2) No % 2012 36 Attachment 4 301 PAYRAN STREET REMEDIATION LOCATION MAP Date: FEBRUARY 24, 2020 N City of Petaluma 0 PROJECT SITE w E Public Works and Utilities S Department 37