Loading...
HomeMy WebLinkAboutAgenda Packet 3.F 05/02/2011DATE: May 2, 2011 TO: Honorable Mayor and Members of the City Council through City Manager FROM: Larry Zimmer, PW Engineering Manager/-e SUBJECT: Resolution Authorizing the City Manager to Execute Amendment No. 1 to the Cooperative Agreement between Caltrans and the City of Petaluma for the East Washington Street Interchange Project: RDA100280, which is Segment C =1 of the Marin Sonoma Narrows Segment C (MSN -C) Project RECOMMENDATION It is recommended that the City Council adopt the attached resolution authorizing the City Manager to execute Amendment No. 1 to the Cooperative Agreement between Caltrans and the City of Petaluma for the East Washington Street Interchange Project RDA100280, which is Segment C -1 of the Marin Sonoma Narrows Segment C (MSN -C) Project. BACKGROUND On June 1, 2009, the City Council approved a cooperative agreement between the City of Petaluma and Caltrans, which outlined City and Caltrans responsibilities. on delivery of the East Washington Street Interchange Project improvements. The East Washington Street Interchange Project will improve two quadrants of the interchange — southwest and northeast by widening and improving the existing southbound on -ramp and constructing a new on -ramp, bridge, and retaining wall in the northbound direction. The Project has environmental clearance (PA/ED) and the design is nearly 100% complete. The remaining tasks include: • final design (plans specifications and estimates, or PS &E) review by Caltrans District Office and Headquarters; • right of way support, engineering and capital outlay associated with utility relocation and environmental mitigation; • capital outlay associated with right of way dedication or purchase from Plaza North, Plaza. and Regency Centers; • advertisement, award and approval of the construction contract; and • construction. Agenda Review: City Attorney 0— Finance Director L��City Manag e� 7 Based on the current status of the project, it is anticipated the schedule for project delivery will be as follows: Design PS &E :Complete June 2011 RAN'Complete June 2011 Advertise June 2011 Award, Approve September 2011 Construction Start October 2011 DISCUSSION Under normal conditions, Caltrans would require all existing utilities (PG &E, AT &T, Comcast, City sewer /water, etc.) to be relocated prior the start of interchange construction. Due to staging issues with relocation of the City's water and sewer utilities, it was determined during the design phase that these utilities must be relocated during the interchange construction. That, being the case, the relocation costs need to shift from right -of -way capital outlay to construction capital funds. The original City /Caltrans cooperative agreement requires the City to pay for the relocation of all existing utilities prior to the interchange construction, as part of the completion of the right of way process. Due to the above mentioned staging issues, Caltrans, SCTA and the City agree that this requirement cannot be met. - To reflect these changes, along with cost increases described below, the existing cooperative agreements between Caltrans /City, and Caltrans /Sonoma County Transportation Authority (SCTA) will. need to be amended. The attached Amendment. No. 1 to the City /Caltrans cooperative agreement eliminates the City's responsibility to relocate the City sewer and water utilities and also revises the funding table. The SCTA/Caltrans cooperative agreement will be revised to include the sewer and water utilities relocation and also revise the funding table. The financial plan, as outlined in the original cooperative agreement between Caltrans and the City of Petaluma, is shown in the table below: ORIGINAL, COOPERATIVE. PROJECT FUNDING SUMMARY " Note; Total City commitment is task based and not to exceed $4,000,000. The remaining amount of $1,150,000 is allocated to construction costs. 2 UJ ;a CL o 0. 0 a O L 'o ~ c 08 v Cn 0 Q 0 LL co LL 0. nom. co U) co U U) 7 LL LOCAL CITY Local $1,700,000. $1,000,000. $150,000. $1,850,000. $1,000,000. $2,850,000. " Note; Total City commitment is task based and not to exceed $4,000,000. The remaining amount of $1,150,000 is allocated to construction costs. 2 The detailed engineering design work adjusted the location of the new northbound on -ramp, bridge and retaining wall, which has resulted in more utility relocation work than originally estimated in preliminary design. Constraining features and the requirement to relocate existing PG &E vaults and transmission lines out of the right -of -way will increase the cost of utility engineering and facilities. Additional easements will also need to be acquired. The increased cost of utility relocation has increased the estimates for right -of -way support and right -of -way capital. Additionally, PS &E support estimates have been increased. from $1,700,000 to $1,950,000. This increase was requested by Caltrans for their design (structures) support activities. On November 1, 2010 the City Council approved Amendment No. 2 to a separate cooperative agreement between the City and S'CTA, which amended the funding contributions. This amendment allocated $2,750,000 Measure M 101 funds toward the City required R/W Capital (acquisitions), which have increased. 'Even though the cost of the City required tasks has increased, the City's contribution remains not -to- exceed $4,000,000. The proposed funding summary for Amendment No. 1 to the Caltrans/ City cooperative agreement, below, matches that of the financial plan outlined in the amended SCTA/City of Petaluma agreement. AMENDMENT NO. 1 PROJECT FUNDING SUMMARY ;� fi g • ' k ^ ,•v i , ' Y d AY }e. ,.. ^a A, M., '� k „ Fe n $ t. .2 1 Ai F '' °'�+'g, ''d.`.k t aY L`$ ` �d 9 g . &. c y ^e E 8 t om . I k M Y �` v �'X , Q•'t' \ k�9h�i � H a 4 W � A Q: Apr a Q a 11 x$x^ sQ ` i + C p ro q ++ t4 p�gz y p : � �+ "yo- =4i` JA c y ��P�yV„�p si.,4 elm 'ya q[ p q. N �9� v yv,`� 4 & y/ 0 \\? ,�S W 4 ,.. g�'m i SIN - a���$� LOCAL CITY Local $1,950,000 $1,260,000 $510,000 $1,770,000 $1,950,000 $3,720,000 (Other) LOCAL CITY Local $0 $2,750,000 $0 $2,750,000 $0 $2,750,000 (Measure M) Subtotals by $1,950;000 $4,010,000 $510,000 $4,520,000 $1,950,000 $6,470,000 Component „ Note; Total City commitment is not to exceed $4,000,000. The remaining amount of $280,000 is allocated to construction costs. FINANCIAL IMPACTS The City's total.financial commitment to this project remains $4,000,000. The City is the implementing agency for PS &E (design), right of way acquisition, and design services during construction of this 'project. Petaluma's remaining contribution of $280,000 ($4,000,000 less $3,720,000) will be spent on design.support services during construction. As identified in Amendment No.2 to the City /S'CTA cooperative agreement, $2,750,000 Measure M (101 funds) have been allocated for right -of -way capital. ATTACHMENTS 1. Resolution; including Exhibit A to the Resolution: Amendment No. 1 to the Cooperative Agreement between Calttans and,the City of Petaluma. 2. Original cooperative 'agreement between Caltrans and the City of Petaluma rd ATTACHMENT I RE O. 1 TO ON AUTHORIZING O THE CITY MANAGER TO. EXECUTE AMENDMENT RATIVE,AGRE'EMENT BETWEEN CALTRANS AND THE CITY OF' PETALUMA FOR THE EAST WASHINGTON STREET INTERCHANGE PROJECT RDA1002$0, WtHQI IS SEGMENT C -:1 OF THE 1VIARIN SONOMA NARROWS SEGMENT C (MSN -C) PROJECT WHEREAS, at its meeting of December 29, 2005, the Petaluma Community Development Commission authorized allocation of $4M from PCDC account undesignated fund balance to the East Washington Street.Interchange component (Project RDA 100280) of the MSN -C Project for right -of =way acquisition and construction. of ramp improvements to the East Washington Street Interchange' component of the MSN -C Project; ;and WHEREAS, on.January 26 2009, the Petaluma Community Development Commission adopted the findings, made'in accordance, with California Health and Safety Code Section 33445, for expenditure of these tax increment funds to pursue right -of -way acquisition, construction of the East Washington Street Interchange component, and full design of the MSN -C Project; and WHEREAS the City Council fconsented to the expenditure of said funds to undertake these Public Improvements; and' WHEREAS; the City of Petaluma and .Caltrans ,entered into a cooperative agreement, dated June 3, 2009, for;contribution of construction funding; sand WHEREAS Caltrans,'Sonoma County TransportationAuthority (SCTA) and the City of Petaluma have determined that it.is not feasible to relocate the City's sewer and water - utilities prior to construction of the interchange improvements; and WHEREAS, Cal'trans, SCTA and the City of.Petaluma' agreed that City sewer and water utilities will be relocated during construction of the Project and paid for out of Construction Capital funds ,as provided for in that certain Cooperative Agreement No. 04 -2318 between Caltrans and S,CTA, pursuant; to an exception received from the Federal Highway Administration for this reallocation of Project funding. 5 NOW THEREFORE, BE' TI' RESOLVED, that the Petaluma City Council authorizes the City.Manager to execute Amendment No,1 to the Cooperative Agreement between the City of Petaluma and Caltrans; attached to this resolution as Exhibit A and incorporated herein by reference. 1.241873. in 04 -SON- 101- 4.05 -5.20 EXHIBIT A TO RESOLUTION EA: 26404 District Agreement 04- 2263 -A1 AMENDM3ENT "NO. 1 TO COOPERATIVE AGREEMENT This.AMENDMENT NO. '1 (AMENDMENT). entered into and. effective on 2011, is:between the State of California, acting through its Department of Transportation, referred to as CALTRANS, and City of Petaluma, a body politic and municipal corporation, or chartered city of the 'State of California. referred to as CITY. RECITALS CALTRANS and -CITY collectively referred to for, purposes of this AMENDMENT as PARTNERS, entered'into Cooperative Agreement No 4 2253 ('AGREEMENT) on June 3 2009, defining th'e terms. and conditions for collaborating on the PS &E and Right of Way (R/W) phases of a highway improvement project (PROJECT) on State Route 101 in Sonoma County. PROJECT;consists of the -East Washington Interchange improvements including construction of a new northbound freeway on -ramp' widening of the existing southbound freeway on- ramp, required widening at the terminus of the northbound on- ramp and related utilitYrelocations in the City of Petaluma. 2. Subsequent to the execution of'the.AGREEM'ENT, PARTNERS and Sonoma County Transportation Authority (SCT , have decided. that because of;staging issues the CITY's water and sewer utilities. willbe relocated during construction and paid for out of Construction Capital funds, such relocation and funding being the subject of a.separate Cooperative Agreement (District.Agreement'No., 04 -2318) between CALTRANS and SCTA. Because the cons_truction PROJECT is funded entirely with federal funds, this funding arrangement needs; and has received!, an exception from FHWA. 3. PARTNERS now seek to,,,amend, AGREEMENT'to (a) reflect theTROJECT's revised work. scope resulting from, the , decision to relocate the CITY's utilities during Construction, as opposed''to during PS &E and' R/W, (b,) revise the: funding obligations and (c) add a Spending.Suininary designating dollar amounts .PARTNERS will spend within, the PS &E and R/W'phases of PROJECT. IT IS TIAERE'FORE MUTUALLY AGREED: SIJMIVI Al, ,attached to and made ENT is replaced in its entirety by SCOPE 4. The SCOPE' SUMMARY of AGREEIvI apart, of AMENDMENT, and any reference to SCOPE SUMMARY in AGREEMENT is deemed a reference. to SCOPE SUMMARY Al 5. The .FUNDING.SUMMARY of AGREEMENT is replaced in its entirety by FUNDING SUMMARY Al. attached' to and made a part of AMENDMENT, and any reference to PACT Version 9.1 3`31.08 1 Of 8 04.sON -1'01- 4.05 -5.20 EA: 26404 District Agreement 04-2263-Al FUNDING SUMMARY in AGREEMENT is deemed a reference to FUNDING SUMMARY AI'. 6:_ A SPENDING° SUMMARY Al ; attached to:and.rnade apart of.AIViEATDMENT, is hereby added, to AGREEMENT showing PARTNERS' designated dollar amounts for the PS &E,and RlW `Capital,•and. Support phases of PROJECT. 7. Article 50 of AGREEMENT is hereby replaced in its entirety to.read as follows: SD. CITY will identify and locate all utzlityfiaczlitlesmyfiihin PROJECT area as part of PS &E responsibilities; except as hated in the SCOPE SUM11ARY All utility facilities riot relocated or removed `in advance of construction will he .ideniifed on the plans, specrfica 0ns; and eslmzate far PROJE —CT.; 8: Article 101 of AGREEMENT is, hereby replaced in its entirety -to read as follows: 1 Dl. The following documents .are attached 10,­ and : lade an express 1 f g .. _. PE S UMMARY, FUNDING part ci , this' „a' reem'ent. SCO SUMMAR.Yand SPENDINGSUMMARY. 9. All other terms„ and :conditions' of AGREEMENT shall remain in fizll force and effect. 10. AMENDMENT is deemed, to be included and made �a parr of AGREEMENT. PACT Version 9.1 3.31:08 2 of 8 04 -SON- 1.01 -4.05 -5-'20 , EA: 26404 , District,Agreement 04- 2263 -A1 CONTACT INFORMATION The information provided_,belows' ndicates the pnmart contact data for.,each partner to this agreement. PARTNERS will - notify each other in writing of any °personnel or location changes. Thes''e equrre an amendment t o thxs:agreement.' changes do not r , The rimar. a reement contact person for The p Y .- ALTRANS is: Wajahat Nyaz Project Manager . 111 Grand Avenue: Oakland, California 946;12 Office Phone:, (51.0) 286 - 51.1.9 a a Mobile Phone (511x0) 715, -6273 ' Email: Waiahat Nyaz(&.dot. ca; gov The primary agreement contact person- for CITY is: Larry Zimmer, Engineering Manager 11 English Street Petaluma, California 949 '52 Office Phone ('707) 778 -4467 Fax Number: 00.7076- Email: l'znnmer @'c i:petaluma:ca:us The billing contact person,for is: Larry Zimmer, Engineering Manager Petaluma, California 94953 Office Phone (707) 778 4467 Fax'Number (7070 776 - 3`602; Email: lzim meri,a). ' petalurria:ca:us PACT version 9:1'3 3`6f,8 04- SON - 101- 4.05 -5.20 EA. District Agreement 04- 2263 -A1 SIGNATURES PARTNERS :declare that: I. Each partner is an, authorized legal entity under California state law. 2. Each partner has the authority to enter into AMENDMENT. 3. The people signing.AMENDMENT have the authority do so on behalf of their public agencies. STATE OF CALIFORNIA DEPARTMENT OF TRANSPORTATION CITY OF PETALUMA By: Helena (Lenka) Culik -Caro Deputy District Director - Design CERTIFIED AS TO FUNDS: By: Maureen Rehs. District Budget Manager PACT Version 9.1 3.31M City,Manager Attest: City Clerk Approved as to form: City Attorney Approved: Department Director Approved: Risk Manager Approved: Finance Director 4 of 8 E 04- SON - 101 -4.05 -5.20 EA: 26404 District Agreement 04- 2263 -A1 SCOPE SUMMARY Al PACT Version 9.1 131.08 5 of 8 th W h co o a. v d Z Q U F' U Q Z 3 Plans, S ecificatians, and Estimates &E) -185; 230, 235,240, 255, 260, 265 X X 185 ,Prepare Base Maps and Plan Sheets.for PS &E Develo ment X 230 Prepare Draft, Plans ;, Specifications, and Estimates X 235 Mitigate Environmental Imp acts and Glean Up' Hazardous W X X X 05 Environmental, Mitigation X X 05 Historical Structures Mitigation X 10 Archae*gical and Cultural Mitigation X 15 Biological Mitigation X 20 Environmental Mitigation Right of Way Work X 25: Paleontology:Mitigation X 99 Other Environmenteil,:Mitigation' Products X 10 Detailed Site investigation for Hazardous Waste X 15 Hazardous: Waste Man agement Plan X 20 Hazardous Waste Plans, Specifications, and Estimates X 25 Hazardous Waste Clean -Up' X 30 Certificatevof Sufficiency X 35 Long Term Mitigation`Monitoring X 40 .Updated Environmental Commitments Record X 45 NEPA Delegation X 240 .Draft Structures °Plans, S ecifiiations, and Estimates , . ,. s P X 250 Finat Structures 'Plans, Specifications, and Estimates :Package, X 255 Circulate Review, and Prepare. Final District Plans, Specifications, and;Estimates Packa e X X 05 Grculated and Reviewed Draft Dlstrlct'iPlans, S ecifcations, and Estimates Package X 10 Updated Plans, Specifications, and Estimates. Package X 15 'Environmental ;Re- Evaluation X 20, Final District Plans, ,Specifications, and Estimates Packa e X 25 Geotechnical Information Handout X 30 Materials Information Handout, X 35 Construction Staking 'Package:and Control X 40 Resident Engineer's Pending File X 45 NEPA.Delegation X PACT Version 9.1 131.08 5 of 8 04 -SON- 101- 4.05 -5.20 EA: 26404. District Agreement 04- 2263 -A1 Except for City of Petaluma's water and sewer utilities, which will be relocated during Construction. PACT Version 9.1 3.31.08 6 of 8 I. -2— IC) W ti Go o V 4) s7 z Q U L. U Q z 50 Secured Lease for Resident Engineer Office Space or Trailer X 260 Contfacf Bid Documents. Ready to List X 265 Awarded Ond Approved Construction Contract X 4 Right of -195, 260, 220, 225, 245, 300. X 195 Right of Way Property Management and Excess. Land X 200 Utility,Relocation * X 15 4ppf6ved, Utility Relocation Plan X 20 boity,Relocation Package X 25 Utility Relocation; Management X 30 Utility '.Close 'Out X 99 OtherEJtiiity Relocation Products X 220 Right�of Way Engineering X 225 Obtain „Right of Way Interests for Projedf Rightof.Way Certification X 245 Post Right of Way Certification ,Work X 300 Final' Right. Way Engineering X Except for City of Petaluma's water and sewer utilities, which will be relocated during Construction. PACT Version 9.1 3.31.08 6 of 8 I. -2— 04 -SON -101 -4.05 -520 EA: 26404 District Agreement 04- 2263 -A1 FUNDING SUMMARY Al PACT Version 9.1 3.31:08 7 of 8 I� c a d w o a o w d rL :c a G- 'ts to a V c o a ;a o F— (1) c a to d rs rL s � st t7 z U. ii c (nn (1 ci U. u_ LOCAL CITY Local $1,950,000 $1,260,000 $510,000 $1,770,000 $1,950,000 $3,720,000 Other LOCAL CITY Local (Measure M), $0 $2,750,000 $0 $2,750,000 $0 $2,750,000 Subtotals n $1 $4,010,000 $510,000 $4,520,000 $1,950,000 $6,470,000 Component t PACT Version 9.1 3.31:08 7 of 8 I� 04- SON - 101 - 4.05 -5.20 EA. 26404 .District Agreement 04- 2263 -A1 SPENDING. SUMMARY Al Design (PS &E) O' Z Q � � .., _mp O V �' � LIJ 1= 0, i Ri htrof'Wa Capital CITY _ $4,01.0,000 PLANS, SPECIFICATIONS, AND CITY $510,000 ESTIMATES_(PS &E).. -,185, 230, 235, 255 CITY $1,535;000 PLANS, SPECIFICATIONS, AND CALTRANS ESTIMATES" (PS &E} - 185, 230, 235, 255 $415,000 Right of UVav o 2. Z Q � � .., C Z E L v U L 0, i Ri htrof'Wa Capital CITY _ $4,01.0,000 Right of _ ,Way Support CITY $510,000 PACT Version 9.1 3.31.08 8o €8 I?� ATTACHMENT 2 04- 80N -401 -4.05 - 5.20 EA: 26.404 District Agreement 04 -2263 COOPERATIVE AGREEMENT G . This agreement; effective on \ / is between the; State of California, acting through its Department of Transportation,; referred to as CALTRANS, 'and: City of Petaluma, body politic and municipal corporation or chartered city ofthe State of California, referred to as CITY. RECITALS CALTRANS, and CITY, collectively referred to as PARTNERS, arc authorized to enter_ into a cooperative agreement for improvements` within the SHS right of wayper Streets and Highways Code sections 114 and/or 130. 2. WORK completed under this„ agreement contributes toward the East Washington'Interchange improvements, which include construction of anew northbound freeway: on -ramp, widening of the existing southbound freeway on- ramp, requiredwi'dening at the terminus of the northbound on -ramp and utility relocations, referred to as PROJECT. 3. PARTNERS will cooperate to complete, e PS &E and phases of PROJECT. 4. There are no prior PROJECT - related cooperative agreements. Prior to this agreement, CALTRANS developed the.Project Initiation Document and CALTRANS developed the Project Report. CALTRANS prepared the environmental documentation for PROJECT. The estimated date for COMPLETION OF WORK is January 31, 2011. PARTNERS now define in this�agreement the terms and'conditions under which they will accomplish WORK. ' DEFINITIONS CALTRANS STA NDARDS CALTRANS policies and procedures, including, but not limited to, the guidance provided the Guide to Capital Project Delivery Workplan Standards (previously known as WBS Guide) available at http: / /`dot.ca.g_oy CEQA —The Callfoma Environmental Quality Act (California Public Resources Code, sections 21000 et seq.) that requires State a jocal agencies to identify the significant environmental impacts of their actions and to avoid or mitigate those "significant impacts, if feasible. PACT Version 9.1 3.31.08 1 of 18 Is DistrictAgreement 04 -2263 COMPLETION OF WORK - All PARTNERS have met all scope,, cost, and schedule cornmitments included in this agreement and have-signed a COOPERATIVE AGREEMENT CLOSURE STATEMENT. COOPERATIVE AGRE E CLOSURE. STATEMENT — A document:signed by PARTNERS that 1VIENT' :'., verifies the completion of all scope, cost,,.and schedule commitments, included.in this agreement. FHWA — Federal Highway Administration. FHWA STANDARDS — FHWA regulations, policies and procedures, including but not limited to, the guidance provided at http://www FUNDING PARTNER A partner' who commits a defined dollar amount to WORK. FUNDING SUMMARY - The table in which PARTNERS` designate: funding sources, types of funds, and the project components in which the fun . ds,.are'to be spent. Funds ,listed' on the FUNDING SUMMARY are "not -to- exceed" amounts for each FUNDING PARTNER: HM -1 — Hazardous material (including; but not limited to, .hazardous waste) that may require removal and disposal pursuant to federal or state law whether' t is disturbed by PROJECT or not. .HM-2 — Hazardous material (including, but not limited to, hazardous waste) that may require removal and disposal pursuant to federal or state law only,if disturbed by PROJECT' HM MANAGEMENT ACTIVITIES' — Management activities related to= :either HM -I or HM -2 including, without limitation, any necessary manifest requirements and, disposal facility designations. IMPLEMENTING AGENCY — The partner responsible for managing the scope, cost, and schedule of a project component to ensure the completion ofthat component. activities result in WORK bem develo ed m h the a TING AGENCY'S quality assurance that IMPLEMENTING, I A Independent ualit u Assuran_ce E ME pplicable standards and within an g p ac cordance with established Quality Management, Plan IQA does not include any work necessary to actually develop or deliver WORK or any validation by verifying or rechecking work performed by. another partner. NEPA — The National Environmental,Policy Act .of 1969 that establishes amational policy for the environment and a process to disclose the adverse�impacts of projects with.a federal;nexus. PARTNERS —The term that collectively references: all signatory agencies to this agreement. This term only describes,the relationship between these agencies to work together to achieve a mutually beneficial goal. It is not used in the traditional legal sense in which one partner's individual actions legally bind the other partners. PROJECT MANA'G'EMENT PLAN —A group of.docurnents used to guide a prej,ect's.execution and' control T . throughout the project's lifecycle. PACT Version 9.1 3.31.08 2 of 18 I &2 District Agreement 04 -2263` PS &E ( Plans , p ons, a6d.Estimates) — The project component that includes the activities required to . S ecificati deliver the plans, specifications -and estim. ates 'for PROJECT. I2/W (Right of Way) — The project component that includes the activities, required to deliver the right of way for PROJECT. SAFETEA -LU — The Safe, Accountable Flexible, Efficient Transportation Equity Act: A Legacy for Users, signed into federal law on August 1;0; SCOPE SUMMARY — The;table'in which,PARTNERS designate their commitment to specific scope activities within each project component as outlined by'-the Gidde to Capital Prqject Delivery Workplan Standards (previously known as VMS Guide), available at' : / /dot.ca.g_ov SAS — State Highway System. SPONSOR(S) — The partner that accepts'the obligation to secure`financial resources to fully fund WORK. This includes any additional funds beyond those committed in this agreement necessary to complete'the full scope of WORK defined in this agreement or settle claims. WORK — All scope and cost commitments included; in this agreement. RESPONSIBILITIES 9. CITY is CO- SPONSOR .for all WORK. 10. CALTRANS is CO- SPONSOR „for all WORK. 11. CITY is the only FUNDING PARTNER for this agreement. CITY " ,funding commitment is defined in the FUNDING SUMMARY. 12. CALTRANS is the CEQA lead agency for PROJECT.. 13. CALTRANS is the NEPA. lead agency for.PROJECT. 14. CITY is IlVIPLEMENTING,AGENCY for PS &E and' R4. SCOPE Scope: General 15. All WQRK will be performed in accordance with federal and .California'laws, regulations, and standards. All WO RK will be performed in, accordance with FHWA STANDARDS -and CALTRANS STANDARD'S: PACT Version 9.1 3.31.08 3 of 18 I District Agreement 04 -2263 16. IMPLEMENTING AGENCY for a project component will provide a Quality Management Plan for that component, as part of the PROJECT MANAGEMENT PLAN. , 1.7. CALTRANS will provide IQA for the pgrtioris of WORK within. existing and proposed SHS right of way. CAL TRANS retains the right to reject.noncompliant WORK, protect public safety, preserve property rights, and ensurelhatall WORK is in the best interest of the SHS. 18. CITY may provide IQA for the portions of WORK ; outside existing „and proposed SHS right of way. 19. PARTNERS, may, at.,their own expense,, have a representative observe any scope, cost, or schedule commitments performed by another partner. Observation does not constitute authority over those commitments. 20. Each partner will ensure thatall'.oftheir personnel participating in WORK are appropriately qualified to perform the tasks assigned to them: 21. PARTNERS will invite each other to participate in. the selection and retention of any consultants who participate in WORK. 22. PARTNERS will conform to sections 1720 — 1815 of the California Labor Code and all applicable regulations and coveragei determinations issued by the Director of Industrial Relations.if PROJECT work is done under contract (not:compl'eted by a partner's own employees) and is governed by the Labor Code's definition of a "Public” work" (section 1720(a)(1)). PARTNERS will include wage requirements in all contracts for "public work" and will require their contractors and consultants to include prevailing wage requirements in all agreement- funded subcontracts for "public work ". 23. IMPLEMENTING AGENCY for each project component included in this agreement will be available to help resolve WORK - related: problems generated by that component for the entire duration of PROJECT. 24. CALTRANS will issue, upon proper application, and at no cost to CITY, an encroachment permit required for WORK within SHS right of way. .Any third party age.nt :(i. n lulling, but not limited to, contractors, consultants, .and utility owners) must obtain .''an encroachment permit issued in their name, prior performing, any WORK within, the SHS R/W. All third. party agents will be assessed an encroachment permit fee. 25. If unanticipated ctiltural, archaeological, paleontological, or other protected resources are discovered during WORK, all work in that area will stop until a qualified can evaluate the nature and significance of the discovery and a plan is approved for its removal or protection. -26. All administrative draft arid,admnistrative final reports, studies, materials, and documentation relied upon, produced, created, or utilized for PROJECT will be held an confidence pursuant to Government Code section 6254.5(e). PACT Version 9.1 3.31.08 4 of 18 District Agreement 04 -2263 PARTNERS will not distribute, release, or share said documents with anyone other .than employees, agents, and consultants who require access to complete WORK without the written consent of the partner authorized to release•them, unless required or authorized to do so by law. 27. If any partner receives a public, records request, pertaining to WORK under this agreement, that partner will notify PARTNERS within five (5) working days of receipt and make PARTNERS aware of any transferred public documents. 28. If H 4 -1 or HM -2 is found during WORK., IMPLEMENTING AGENCY for the project component during which it'is found will immediately notify.PARTNERS. 29. CALTRANS, independent of PROJECT, is responsible for any HM -1 found within existing SHS right of way. CALTRANS will undertake.HM -1 MANAGEMENT ACTIVITIES with minimum impact to PROJECT schedule. 30. If HM -1 is.found outside existing SHS right of way, .responsibility for such HM -1 rests with the owner(s) of the parcel(s)' on which the HM -1 is found. CITY, in concert with the local agency having land use jurisdiction over the parcel(s), will ensure that HM -1 MANAGEMENT ACTIVITIES are undertaken with minimum impact to PROJECT schedule. 31. If HM -2 is found within PROJECT limits, the public agency responsible for the advertisement, award, and. administration (AAA) of the PROJECT construction contract will be responsible for HM -2 MANAGEMENT ACTIVITIES. 32. CALTRANS' acquisition or acceptance of title to any property on which any HM -1 or HM -2 is found will proceed in accordance with CALTRANS' policy on such acquisition. 33. PARTNERS will comply with all of the commitments and conditions set forth in the environmental documentation, environmental permits, approvals, and applicable agreements as those commitments and conditions apply to each partner's responsibilities in this agreement. 34. IMPLEMENTING AGENCY for each project component will furnish PARTNERS with written monthly progress reports during the implementation of WORK. in that component. 35. Upon COMPLETION.OF WORK, ownership and title to all materials and equipment constructed or installed as part of WORK within SHS right of way become the property of CALTRANS. 36. IMPLEMENTING AGENCY.for a project component may accept, reject, compromise, settle, or litigate claims of any non- agreement parties hired to do WORK in that component. 37. PARTNERS will confer on, any claim that may affect WORK or PARTNERS' liability or responsibility underthis agreement:;in order to retain resolution possibilities for_potential future claims. No partner shall prejudice the rights of'anotherpartner until after PARTNERS confer on claim. 38. PARTNERS will maintain and make available to each other all WORK- related documents, including financial data, during the term of this agreement and retain those records for four (4) years from the date PACT Version 9.1 3.31.08 5 of 18 9 District Agreement 04 -2263 of termination or COMPLETION OF WORK, or three (3) years .from the date of final federal voucher, whichever I is later. 39. PARTNERS have the right to audit each other in accordance with generally accepted governmental audit standards. CALTRANS, the State auditor; FHWA, and CITY will have access to all WORK - related records of each partner for audit, examination excerpt, or transaction. The examination of airy records will take place in the offi ces'.and locations where said_records are generated and/or stored and will be•,Aceomplished during reasonal le hours of operation. The audited partner, .will'reuiewthepreliminary audit, firid'irigs, and recommendations, and provide written comments within 60 calendar days of receipt. Any audit dispute not resolved by PARTNERS is subject to dispute resolution. Any costs arising out of the dispute resolution process will" be paid within 30 calendar days of the final audit or dispute resolution findings. 40. PARTNERS consent to service as permitted by law. 41. PARTNERS will not incur costs beyond the funding commitments in this agreement. If IMPLEMENTING AGENCY anticipates'that funding for WORK will be insufficient to complete WORK, SPONSOR(S) will seek out additional funds'and PARTNERS will amend this agreement. p y PLENIENTING AGENCY will place all facilities impacted by 42. If WORK stops for an reason IM WORK in a safe and operable condition acceptable -to CALTRANS. 43. If WORK stops for any reason, PARTNERS are still .obligated to implement all applicable commitments and conditions included in the,PROJECT environmental documentation, permits, agreements, or approvals that are in effect the time that WORK stops, as they apply to each partner's responsibilities in this agreement in order to keep PROJECT in environmental compliance until WORK resumes. 44. As theNEP.,A lead agency, CALTRANS will coordinate and obtain,the following.federal resource agency permits; agreements,.,and/or U.S. Army Corps of Engineers Permit (404). 45. CALTRANS will coordinate, and obtain the following non - federal resource; agency permits, agreements, and /or approvals;, Department of Fish and Game 1600 Agreement(s), Waste IDischarge .(NPI)ES) Permit,.Regional Water Qualify Control Board 401 Permit, and�.anyother iSon- federal resource agency permits, agreements approval which are required for PROJECT. 46. CITY will, prepare any required federal resource agency permits, agreements and/or approvals for PROJECT. CLTY willsubmt all said applications to CALTRANS`for review, continent and approval. CALTRANS will submit the final:applications to the appropriate federal :resource agencies. PACT Version 9.1 3;31.08 6 of 18 M District Agreement 04 -2263` 47. CITY will prepare any required non - federal resource agency pen - nits, agreements and/or approvals for PROJECT. CITY will submit, all said applications to CALTRANS for review, continent and approval. CALTRANS will submit "the`fiiial.applications to the appropriate non - federal resource agencies. 48. Each partner accepts responsibility toa complete the activities that they selected on the SCOPE SUMMARY.. Activities marked with "N /A" on the SCOPE SUMMARY are not included in the scope of this agreement. Scope: Plans, Specifications, and Estimates (PS &E) 49. CITY will ensure that the engineering .fine preparing the plans, specifications, and" estimates will not be employed by or under contract to the PROJECT construction contractor. CITY will not. employ the..engineering firm preparing the plans, specifications, and estimates for construction rnanagement':of„PROJECT. However, CITY may retain°the engineering firm during CONSTRUCTION to check shop drawings, do soil foundation tests, test construction materials, and perform construction surveys. 50. CITY will identify and locate all utility facilities within PROJECT area as part of PS &E responsibilities. .All utility facilities. not relocated or,rerroved in advance ofconstruction will be identified on the plans, specifications, and restimate for PROJECT. 51. CITY will make all.necessary arrangements with utility owners for "the timely accommodation, protection, relocation; or removal .of'any existing utility facilities; that conflict with construction of PROJECT or that violate CALTRANS' .encroachment policy. 52. The responsibility to advertise, opeabids, award, and approve the, construction contract (AAA) will be handled outside the commitments of ihis agreement. However, CITY and CALTRANS acknowledge, and have agreed, that when AAA is necessary, CALTRANS wild perform those duties which include activity 3.265. 53. CITY:acknow:ledges that activity'3260 will be performed by CALTRANS'. In order for CALTRANS to perform AAA: in the,f the PS &E package must be reviewed and approved by CALTRANS District. and HO Office', Engmeers,pri'or to advertisement, which includes all the duties listed in the SCOPE SUMMARY under activity3.260. 54. CITY will ensure thatthe consultant who prepared the PS &E package will remain available to address all comments generated during the performance of activity 3:260 Scope:. Right idf Way (>R/W) 55. CITY w..:ill :provide a- land licensed in the State of California to be responsible for surveying and right of way engineering. All survey and right of way engineering documents shall bear the professional PACT Version 9.1 3.31.08 7 of 18 District Agreement 04 -2263 seal,, certificate.nuniber, registration; classification, expiration date of certificate and signature of the responsible surveyor. 56. CITY will provide CALTRANS- approved verification of its arrangements for the protection, relocation, or removal of all conflicting, facilities and that such. work will b& completed prior to construction contract: award or as otherwise stated in'the PROJECT specifications, and estimates. This verification must include references to all required SHS encroachment permits. 57. CITY will utilize a qualified- CALTRANS- approved public agency or consultant in all right of way activities. Right of way consultant contracts will be administered by :a qualified right of way person. 58. CITY will provide a.Rightof"WayCertification to CALTRANS prior to PROJECT advertisement. 59. All right of way conveyances must be completed prior to COMPLETION OF .WORK. CALTRANS' acceptance of right of way fideis subject to review of an Updated Preliminary Title Report provided by CITY verifying that the tltle'is free of all encumbrances and' liens: ,Upon acceptance, CITY will provide CALTRANS with a Policy of Title Insurance in CALTRANS' name 60. The California Transportation Cor m' 'Ission (CTC) will hear all Resolutions of Necessity (RONs), if property condemnation is necessary. COST Cost: General 61. SPONSOR(S) will secure °fu'nds forall WORK including,any additional funds beyond the FUNDING PARTNERS' existing commitments In4his agreement, Any change to the funding commitments outlined in this agreement requires an amendment to this agreement. 62. The cost of any awards, judgments, or settlements generated `by WORK is a WORK cost. 63. CALTRANS, independent.ofPROJECT will pay all costs MANAGEMENT ACTIVITIES related to HM= I found within existing 'SHS right of way. 64. Independent ofPROJECT : all costs for H1VI MANAGEMENT ACTIVITIES related to HM -1 found outside,ahe existing SHS. right of way will be the responsibility of the owner(s) of'the : parcel(s) where the HM -1 `is .located. 65. HM MANAGEMENT ACTIVITIES costs related to HM -2 are a PROJECT CONSTRUCTION cost. 66. The cost.of coordinating,.:obtaining, complying with, implementing, and ifnecessary renewing and amending'resource agency permits, agreements, and/or approvals 'is. a WORK cost. 67. The. cost to comply with and implement the commitments set forth in the environmental documentation is .a WOK cost. PACT Version 9,1'3.31.08 8 of 1.8 District Agreement 04 -2263 68, The cost to ensure that PROJECT remains in.environmental compliance is a WORK cost. 69. The cost of any legal challenges to the CEQA or NEPA environmental process or documentation is a PROJECT cost. 70. Independent of WORK costs, CALTRANS will fund the cost of its own .IQA for WORK done within existing or proposed .future SHS right of way. 71. Independent of WORK costs; CITY wi ll fund the cost of its own 4QA for WORK done outside existing or proposed future SHS right of way. 72. Fines, interest,, or penalties: levied against any partner will be paid, independent of WORK costs, by the partner whose actions or lack of action caused the levy.'That partner "will` indemnify and defend all other partners. 73. The cost to place PROJECT`ri`ght of way in a safe and operable,condition and meet all environmental commitments is a WORK cost.. 74. Because IMPLEMENTING AGENCY is responsible for managing „ the . scope, cost, and schedule of a project component, if there are insufficient funds.available in this agreement to place the.right of way in a safe and operable condition the appropriate IMPLEMENTING AGENCY accepts responsibility to fund these activities until such time as PARTNERS .amend this, agreement. That IMPLEMENTING AGENCY may request reimbursement for these costs during the amendment process. 75. If there are insufficient funds: in this agreement to implement applicable commitments and: conditions included in the PROJECT environmental. documentation, permits, agreements, and/or approvals that are in effect at a time that WORK.stops, the partner implementing:the commitments or conditions accepts responsibility to fund these activides•until such time are PARTNERS amend this agreement. That partner may request reimbursement for these costs during the amendment process. 76. PARTNERS will. pay invoices within 30 calendar days of receipt of invoice. 77. FUNDING PARTNERS' accept responsibility to provide the funds identified on the FUNDING SUMMARY. 78. SPONSOR(S). accepts responsibility to ensure full funding for the identified scope of work. Cost: Plans,.Specificaiions -aud Estimates (PS &E) os>t 79. The cost to p i . any utility-facilities whether inside i�el y ,denyf y andaocafe, p rotect, relocate or remove , or SHS n ht. of wa will - be determined m accordance with federal and California, laws and PACT version 9.1 3.31.08 9 of 18 2-__�> District Agreement 04 -2263 regulations and CALTRANS' policies; procedures, standards, practices, and applicable agreements including, but - bot limited to; Freeway Master Contracts. 80. The following partners will submit invoices forPS &'E:. ® CALTRANS will .invoice CITY 81. PARTNERS will exchange Rinds for actual costs. CALTRANS will. invoice CITY for _an initial deposit. of $50 upon execution of this agreement. This deposit represents two (2) months' estimated support costs. Thereafter CALTRANS will'submit to CITY monthly invoices for °.costs based on the prior month's actual expenditures. After PARTNERS agree that all'Scope activities are complete, CALTRANS Will submit a final accounting for all WORK costs: $ased`on the f nal accounting, PARTNERS will refund or invoice as necessary in order to satisfy the obligation of this agreement. :„ SCHEDULE 82. PARTNERS will manage the for WORK through the plan included in the PROJECT MANAGEMENT PLAN. GIENERAL. CONDITIONS 83. This agreement will be understood in accordance-wi.th acid goverried'by the Constitution and laws of the State of California This agreement "will be enforceable in the State of California. Any legal action arising from this agreement. will'be , filed' and maintained in the Superior Court of the county in which the CALTRANS district office signatory to this agreement resides. 84. All obligations of CALTRANS under: the terms of this agreement are subject to the appropriation of resources by the Legislature, the.State Budget Act authority, .and. the allocation of funds by the California Transportation Commission. 85. Any PARTNER who performs IQA does so for its own benefit, further,. that PARTNER cannot be assigned liability due to its IQA activities. 86. Neither CITY nor ant o dAcer or employee thereof is responsible for any °injury., damage or .liability occurring byreasorrof anything done or omitted to be done._by CALTRANS under or in ,connection with any authority,.o.r Jurisdiction conferred upon CALTRANS' under this agreement. It is understood and,agreed that-:CALTRANS will. fully defend,, indemnify, and save harmless CITY and all of its officers and employees from all claims, suits, or actions of everyname,.kind, and description brought forth under, but not. inited to, tortious, contractual, inverse condemnation, or other theories or PACT Version 9.1 3.31,.08 10 Of 18 2' District Agreement 04 -2263 assertions of :liability occurring -by reason of anything done or omitted to be done by CALTRANS under this agreement. 87. Neither CALTRANS nor any officer or employee thereof is responsible for any injury, damage, or liability occurring by reason. ..of anything done or omitted to be done by CITY under or in connection with any work, authority, or jurisdiction conferred upon CITY under this agreement. It is understood and agreed. that CITY will fully defend, indemnify, and save harmless CALTRANS and all of its officers and employees from all claims, suits; or actions. of every name, kind, and description brought forth under but -not limited to,'tortious, contractual, "inyerse condemnation, or other theories or assertions of liability occurring'by reason -of anything done or `omitted to be done by CITY under this agreement. 88. This agreement is not intended to create arthird party beneficiary_ or define duties, obligations, or rights in parties not signatory to°this,agreement: This agreement is not intended to affect the legal liability of PARTNERS by imposing any standard 'of care for completing WORK different from the standards imposed by law. 89.. PARTNERS will not assign or attempt to assign agreement obligations to parties not signatory to this agreement. 90. Any ambiguity contained -in this :agreement will not be interpreted against PARTNERS.. PARTNERS waive the provisions of Califorma.Civil Code section 1:654. 91. A waiver of apartner's performance under this agreeinent`will not constitute.a continuous waiver of any other provision. An amendment made to;any °art'icle or section of this does not constitute an amendment to or negate all other articles or sections of'this agreement. 92. A delay or omission to exercise'a.right or - power due to a default does not negate the use of that right or power in the future when deemed` "necessary. 93. If any partner defaults m tlieir obligations, the non - defaulting partner(s) will request in writing that the default be remedied within 30 calendar days. If the defaulting partner fails to do so, the non - defaulting partner (9) may initiate dispute resolution. 94. PARTNERS will frst,:attempVto xesolve agreement disputes, at the PROJECT team-level. If they cannot resolve the dispute "themselves, the CALTRANS district,director and the executive officer of CITY will attempt to negotiate aresol'ution'.. 'If no resolution is reached, PARTNERS' legat counsel. wil1 initiate mediation.. PARTNERS :agree to participate in mediation in good faith and will'share equally in its costs. Neither. the dispute nor the mediation process relieves PARTNERS from full and timely performance of WORK "'in accordance with =the terms of this agreement. However, if any partner.stops WORK, the other partner(s) may seek equitable relief to ensure that WORK continues. PACT Version 9.1 3.31.08 11 of 18 2 _ ' District.Agreement 04 -2263 Except for equitable relief, no .partner may file a civil complaint until after mediation, or 45 calendar days after filing the written':med ation request, whichever occurs first. Any civil complaints will be,filed in the Superior Court of the county.in which the CALTRANS district office signatory to this agreement,resides. The prevailing partner will be entitled to an award of all costs, fees, and expenses, including reasonable attorney fees as axesul "t of.;litigating a dispute under this agreement or to enforce the provisions of this article including equitable relief. 95. PARTNERS maintain therabilityto pursue alternative or additional dispute remedies ifa previously selected remedy does not" achieve "re'solufton. 96. If anyprovisiom.in this agreement,are .deemed to be, or are in fact, illegal, inoperative, or unenforceable, those-provisions do render any or all other: agreement provisions invalid, inoperative, or unenforceable, and those provisions will be automatically severed fi this agreement. 97. This agreement is intended" to be PARTNERS' final expression-and supersedes all prior oral understanding or writings pertainingto WORK. 98. If during performance of WORK_additional activities or environmental documentation is necessary to keep PROJECT in environmental cornpliance, PARTNERS' w, ill :amend this agreement to include completion of those additional tasks. 99. PARTNERS will execute a formal written amendment._if there are any changes to the commitments made in this agreement. 100. This agreement will terminate upon COMPLETION OF WORK or upon 30 calendar days' written notification to terminate and acceptance between PARTNERS, whichever occurs first. However, all indemnification , °document.retention, audit, claims, environmental commitment, legal challenge, and ownership articles will remain in effect until terminated' or modified in writing by mutual agreement. 101. The following documents are attached to, and made an express part of this agreement: SCOPE SUMMARY FUNDING SUMMARY. 102. Signatories :may execute agreement through individual signature pages provided that each signature is an original. This agreement is not fully executed until all original signatures are attached. PACT Version 9.1 3.31.08 12 of 18 2 L District Agreement 04 -2263 CONTACT INFORMATION The information provided'below indicates the°primary contact,data. ::for"ea6h.partner to this agreement. PARTNERS will notify each other.-in writing any personnel or location changes. These changes do not require an amendment to this agreement. The primary agreement contact person for CALTRANS is: Jit Pandher, Regional Project Manager 111 Grand. Avenue Oakland, California 94,623 Office Phone: (510.) 286 -6425 Email: jit s _pandher @dot.ca:gov The primary agreement contact°:person for CITY is: Vincent Marengo, Director of Public Works 11 English Street Petaluma California 94952. Office Phone: (707) 778= 4467 . Fax Number: (707) 7,76 =3602 Email: vmarengo @ci.petaluma.ca.us The billing contact person for CITY is: Vincent Marengo, Director of Public Works Petaluma, California 94953 Office Phone: (707) 778 -4467 Fax Number: (707) 776 -3602 Email: vmarengo @ci.peialuma.ca.us PACT Version 9.1 3.31.08 13 of 18 2 11 District Agreement 04 -2263 SIGNATURES PARTNERS declare that: 1. Each partner is an authorized legal. entity under California state. law,. 2. 'Each partner has the authority to enter into I this agreement. 3. The people signing this agreement `have the authority to do so on behalf of their public agencies. STATE OF CALIFORNIA DEPARTMENT OF TRANSPORTATION By: Helena (Lenka). Culik -Caro Deputy District Director CERTIFIED AS TO FUNDS: CITY OF PETALUMA John C Brown City Manager Attest: Claire Cooper City Clerk By: . Cynthia Stratton District'Budget Manager APPROVED AS TO FORM AND PROCEDURE By: Eric Danly City Attorney .APPROVED By: Department Director APPROVED Rls' k Manager APPROVED s Direct Finance 14 of 18. PACT Version 9..1.3:31.08 �� 04- SON -101 -4.05 - EA: 26404 District Agreement 04 -2263 SCOPE SUMMARY V' in W ti co C. o c: U N � fn z Q Q U Q Z 3 Plans; Specifications; and Estimates (P..S&E) - 185, 230,.,235,.240„250,,255; 260,'265.' X X 185 Prepare Base 'Maps'and Plan Sheets for PS &E Development. X 230 Prepare Draft Plans, Specifications °Estimates X 235 Mitigate'Environmental Impacts;and'Clean' Up Hazardous Waste X X X 05 Environmental Mitigation X X 05 Historical Structures Mitigation. X 10 Archaeolodical and Cultural Mitigation X 15 Biological Mitigation X 20 Environmental Mitigation Right of Way Work X 25 Paleontology Mitigation X 99 Other. Environmental Mitigation'Products X 10 Detailed Site Investigation for Hazardous Waste X 15 Hazardous, Waste Management Plan X 20• Hazardous Waste Plans, Specifications, and Estimates X 25 Hazardous Waste Clean -Up X 30 Certificate of Sufficiency X 35 Long Term Mitigation' Monitoring X 40 Updated Environmental Commitments.Record' X 45 NEP.A Delegation X 240 ,br4ft;Strbct6res.,Plans; Specifications, and Estimates X 250 Final- Structures Plans Specifications, and Estimates Package X 255 Circulate Review, and Prepare F,inal',D.istrict Plans, S ecifications, ,and. Estimates Package X X 05 Circulated and'Re. viewed. Draft District, Plans, Specifications., and`Estimates Package. X 10 1 Updated Plans; Specifcations, and Estimates - Package X 15 Environmental'Re- Evaluation X 20 Final`DistricfPlans, Specifications, and:Estimates Packa e: X .25 Geotechnical Information Handout X' 30 Information Handout X 35, . ,Construction 'Staking Package and Control X 40 „ Resident Engineer's Pending File X 45 NEPA Delegation X 50 Secured Lease for Resident Engineer Office Space or Trailer X 260 Contract Bid Documents Ready to List X 265 Awarded and Approved Construction Contract X PACT Version 9.1 3.31.08 15 of 18 District Agreement 04 -2263 4 Ri hYOf Way R/W - 195, 200, 220, 225; ,.245 ,9 y �, ) X 195 Right of Way Property Management and'E)ccess Land X 200 Utility Relocation X 15 Approved: Utility Relocation Plan X 20 Utility, Relocation Package X 25 Utility, Relocation Management X 30 Utjlity Close Out X 99. Other Uti(ity,3 elocation4Rroducts X 220 Right;of Way Engineering X 225 Obtain Right.of'Way Interests,for Project Rightof'Way Certification: X 245 Post' Right of Wa.y Work X 300 Final Right of Way Engineering X PACT Version 9.1 3.31.08 16 of 18 O 04.- SON -101 -4.05 - 5.20 EA'. 26404 District Agreement 04 -2263 FUNDING SUMMARY C) =a Q) ".t c r O ° c a �- 7 3 C v C 7. <a. o�S d ca V 3 W 0 a c, = to o to .0-0 LL �d _ n 3 3 N(n C. � V' 0 3 LL LOCAL CITY Local $1.;;700,000.00', $1,000 000.00 $150,000.00. $1.,850`,000.00 $1,000,000.00 $2;850,000.00 Subtotals by Component $1, $1,000,000:00 $150,000.00 $1,850,000.00 $1,000,000.00 $2,850,000:00 PACT Version 9.1 3.31.08 17 of 18 ll" District Agreement 04 -2263 SPENDING SUMMARY PTS-19w T%E) Right of Wav L 0 V " �E' U) m)V E Ax N� 15i �: E'. Right of Way Capital CITY $1,000.,000 Right of Way (14W) - Support CITY PLANS, SPECIF . I . CAT - ION , S- ANUE ESTIMATES' . AND - 1: . -.- �- -1 - 185;.230.,2-35, - CITY , 345-,000 PLANS, SPECIFICATIONS, AND EST (PS&E) ­240, 2 1 50 CALTRANS $355,000 Right of Wav PACT Version 9.1-3.31.08 18 of 18 L 0 V " �E' U) m)V E Ax Right of Way Capital CITY $1,000.,000 Right of Way (14W) - Support CITY $150 PACT Version 9.1-3.31.08 18 of 18 TWA WITHIN MTRUMEAtTISA TRlatS��gPli bF fiif= . � ot� �ll� iiV'l�lil� t3G • r ReSOlut on No. 2009 -07`5 N.0 S JUG 'S' COQ` L s, }.' ,, ;�, _.w , of-the City of Petaluma, Callfo-na Arrs�: " Ar1E�`F AUTHORIZING THE MANAGER TO EXECUTI�M JOIN A COOPERATIVE AGREEMENT BETWEEN. THE CITY AND CALTRA S IN AN AMOIIN'T,NOT TO EXCEED`S2.85M FOR.DEL;IVERY OF PLANS, SPECIFICATIONS AND ESTIMATES (PS &E) AND RIGHT .OF-WAY ACQUISITIONS, r AND TO EXECUTE A C:OOPERATI'VE AGREEMENT BETWEENTHE CITY AND SCTA TO PROVIDE CONSTRUCTION FUNDING IN AN AMOUNT NOT -TO- EXCEED S:I 1.5M "FOR TR.E EAST WASHINGTON INTERCHANGE PROJECT (PROJECT RDA100280) COMPON'ENT' TILE MA.RIN SONOMA NARROWS SEGIME °NT C: (MSN' -C) PROJECT WHEREAS, the City of Petaluma wishes to proceed with -the design `(plans, specifications, and estimate, or P &E), right- of-way acquisitions; and contribute to the construction of the East Washington Interchange component of the Marin Sonoma Narrows (MSN) Segment C Project; and WHEREAS at its meeting of December'29, 2005 the Petaluma Community Development Comm] ssionauthorized allocation of $41x1 from P.CD.0 account undesi.gnated fund balance to the East. Washington Interchange: component (Project RDA '100280) of the MSN -C Project for right -of -way acquisition and construction of the:ramp improvements to the East Washington interchange componenf'ofthe MSN -C Project; and, WHEREAS, on January `26, 2009, the Petaluma Community Development Commission adopted the findings, made in,accordance with California Health and Safety Code Section 33445 for expenditure of these tax increment funds to pursue right -of -way acquisition, construction of the East Washington Interchange component and full design.of the MSN -C Project; and, WHEREAS, the City Council consented to the expenditure of said funds twundertake these Public Improvements; and, WHEREAS, in order to proceed, a.cooperative funding agreement for PS&E and right- of-way acquisitions must be 'executed between the City of Petaluma.and the California Department of Transportation;' and, Resolution No. 2009-075 N.C.S. Page 1 WHEREAS, in order to pTocegd, a cooperative funding agreement for contribution of constfuction "funding must be executed between the City of Petaluma and. the Sonoma,Co.unty Transportation Authority. NOW THEREVORtE, BE IT RESOLVED, that the Petaluma City Council authorizes the City Manager to execute: the Cooperative Agreement between the, City of Petaluma and the California Department of Transportation, attached to this resolution as. Exhibit A and incorporated herein by reference, and to execute the "Cooperati:ve Agreement between the City of Petaluma and Sonoma "County Transportation, Authority,, attached to this resolution as Exhibit B and incorporated herein by reference, including any final changes to:such agreements approved by the City Attorney. Under;* power and authority confcircd,upon, this Council bythe Charter of said; City. REFERENCE: AYES: NOES: ABSENT: ABSTAIN ATTEST I lid eby foregoing Resolution was.introduced and adopted by the Council of the Ciiy' ' ,of Petatuma;at'a Regular`nieeting on the I day oQune 2009, by the "follow.ing vote;. Vice ; Playrl3arrett, Glass; Harris, Healy, Rabbitt, Renee, Mayor Torliatt None Ity to None None b" City Clerk �Mayor " kcsolution.No. 2009 -075 N.C.S. Page 2 �� STATE OF CALIFORNIA- BUSTNESS TRANSPORTATION AND HOUS[NG:AGENCY ARNOLD SCHW ARZENEGGER. Govemor DEPARTMENT OF TRANSPORTATION 111 GRAND AVENUE = 1 ° P: O.'BOX 23660 OAKLAND, CA 94623, -•0660 PHONE (510) 622 -0754 Flexyourpower! FAX (510) 622 -0826 Be energy efficient! TTY. (800) 735 -2929 June 10, 2009 Ms. Sherry Pimsler Administrative Assistant Public Works Department City of Petaluma P. O. Box 6 -1 Petaluma, CA. 94953 04-'Son-10,1-PM 4.05/5:20 East Washington I/C Improvements 04- 264041 District Agreement No. 4 -2263 Dear Ms. Pimsler: Enclosed for your file is a fully executed copy of Cooperative Agreement 4 -2263 between the State and City of Petaluma for the East Washington Interchange Improvements project.. This Agreement was executed on June 3, 2009. The estimated date for completion of work under this Agreement is January 31, 2011. S, erely, PAUL P. MAI Design Office Chief :Design South, Santa Clara "B" Enclosure ''Caltrans improves mobility across California"