CITY OF PETALUMA, CALIFORNIA
F AGENDA �'
BILL -
Agenda Title:
Meeting Dat e : April 19, 2004
Resolution Accepting the Completion of the Traffic Signal Loop
, Installation Project No. 03-8063-3 (formerly 03- 3306 -3).
Mee Time: F;l 3:00 PM
❑ 7:00 PM
Category (check one): Consent Calendar ❑ Public Hearing ❑ New Business
F Unfinished Business ❑ Presentation
Department:
Director
Contact Person:
Phone Number:
Public Facilities & Services
Rick Wadzien
Steve Castaldo
779-4303
Cost of Proposal: $36,077.65
Account Number:
8063 (formerly 3306)
Engineers Estimated Budget: $ 70,000.00
Name of Fund:
General Fund
Attachments to Agenda Packet Item:
1) Resolution
Summary Statement:
On January 5, 2G04 Mike Brown Electric completed work on the Traffic Loop Installation Project, for a
final construction. cost of $34,221,11 The total cost of the project was $36,077.65, including
administration, design and. construction management. Sufficient funds are available to accept and close out
the project.
Recommended City Council Action /Suggested Motion:
Adopt the resolution accepting completion of the construction contract, authorizing the City Clerk to sign
and file a Notice of Completion with Sonoma County Recorder, and the Finance .Department to release
10% retention, to the Contractor 35 days after the recordation of the Notice of Completion.
Reviewed by finance Director:
Reviewed bv Citv Attornev:
Approwd by City Manager:
-D te•
a
Date:
Today's Date
Revi and Date Revised:
File Code:
#
3-8-04
S:\Staff\Castaldo\3306 Traffic Loops\Agenda
COMP16tion Bills
•
i�
CITY OF PETALUMA, CALIFORNIA
APRIL 19, 2.004
AGENDA REPORT
FOR
RESOLUTION - ACCEPTING THE COMPLETION OF'THE TRAFFIC LOOP INSTALLATION
PROJECT No. 03- 8063 -3 (formerly 03- 3306 -3)
1. EXECUTIVE. SUMMARY
On January 5, 2004, Mike Brown Electric completed work on the Traffic Loop
Installation Project; for a final construction cost of $34,221.12. The total cost of the
project was $36,077:65, including administration, design and construction management.
Sufficient funds are available to accept and close out the project.
2. BACKGROUND
The purpose of this project was to replace malfunctioning traffic loops, where necessary,
as well as install new loops replace existing camera systems. The City determined that
the sun's angle.and atmospheric conditions caused the cameras to malfunction and the
system to subsequently go into default mode, causing traffic delays. New traffic loops
have corrected this situation.
Originally the contract was initiated at $57,224:35. However, a portion of the work was
deleted due to lack of `available funds. The amount of the deletion contract change order
was $23,003.23. Contract change orders are on file with the City Clerk.
3. ALTERNATIVES:
a. Accept completion of the project.
4. FINANCIAL IMPACTS
'The, total cost:of this project was $36,077.65, including general fund overhead,
administration, design, construction and contingency. Sufficient funds are available to
accept and close out the project.
Estimated Costs Amount Budgeted
General Fund Overhead $0.00
Administration $1,856.51
Design $0.00
Construction Management $0.00
Construction $34,221.14
Contingency $0.00
Total $36,077.65
Funding Source: General Fund
IM
5. CONCLUSION
The final proj ea cost is under the original project estimate due to :a contract change order
reduction.
6. OUTCOMES OR PERFORMANCE MEASUREMENTS TRAT WILL IDENTIFY SUCCESS OR
. COMPL - ETION:
Completion of the project.
7. RECOMMENDATION
Adopt the resolution accepting completion of the ;construction contract, authorizing the
City Clerk to sign and file a Notice of Completion with Sonoma County Recorder. and
the Finance Department to release 10 %o retention to the Contractor 35 days after' the
recordation of the Notice of Completion.
s \p"f &s \stafAcastaldo\3306 -3
•
L
4
�a
Resolution No. N.C.S.
of the City of Petaluma, California
ACCEPTING THE COMPLETION OF THE TRAFFIC SIGNAL
INSTALLATION PROJECT NO. 03- 8063 -3 (formerly 03- 3306 -3)
WHEREAS, on June lb, 2003, the City Council awarded to Mike Brown
Electric, the construction contract for the Traffic Signal Loop Installation project.
WHEREAS, Mike Brown Electric, Inc. has completed all the work to the
satisfaction of the Director, Public Facilities & Services.
NOW THEREFOR BE IT RESOLVED by the City Council of the City of
Petaluma, California, that the project is hereby accepted,
BE IT FURTHER RESOLVED that the City Council of the City of Petaluma
authorizes the City Clerk to sign the Notice of Completion and file same with Sonoma
County Recorder, and that the Finance Department is hereby authorized to release the ten
i
percent (10 %) retention to Mike Brown Electric within thirty -five (35) days after the
recordation of the Notice of Completion.
Under the power, and authority conferred upon this Council by the Charter of said City
REFERENCE: I hereby certify the foregoing Resolution was introduced and adopted by the Approved as to
Council of the City of Petaluma at a (Regular) (Adjourned) (Special) meeting form
on the .......................... day of ........................ .............................. 20......, by the
following vote: ........ ...............................
City Attorney
AYES:
d r ES:
ABSENT:
ATTEST:
.............................................. ............................... ....................................................... ...............................
City Clerk Mayor
Council File .... ...............................
Res. No . ......... ......................... N.C.S.