"CITY OF PETALUMA, CALIFORNIA
June 7, 2004-
AGENDA BILL
Agenda Title
y
Meeting Date June 7, 2004
Resolution Accepting the Completion of the -Petaluma Transit'
Maintenance and Operations Building Remodel Project No. 9032.
Meeting, Time ®3:00 PM
•
❑ 7:00 PM
Category ,(check one) Z Consent Calendar ❑ :Public Hearing ❑ New Business
❑ Unfinished Business .. ❑ Presentation
Department
Dir.eetor
Contact:Person
Phone Number
Public Facilities & Services
Ric J k 1a "' n
Steve Castaldo
778 -4303
Cost of Proposal $31 ,144.
Account Number
9032,
- Engineers Estimated Budget $ -2 - 03 -04 TDA Claim
Name of Fund:
$134,000 — 04 =05 TDA Claim
Public Transportation (TDA)
Attachments to Agenda Packet- Item
1) Resolution
Summary Statement
On May 14, 2004, Sonoma County. Builders .completed work to remodel the transit building located at 555
North McDowell Blvd., for a final construction cost of $292,020.77. The total cost of the project was
$319,144.30. Sufficient funds are available to accept and close out the project.
Recommended City Council Action /Suggested M tion
Adopt the resolution accepting completion of the construction contract, authorizing the City Clerk to sign
and file a Notice of Completion with Sonoma County Recorder,. and the Finance Department to release the
10 %retention to the Contractor 3 5 days after °the recordation of the Notice of Completion.
Revip-wed'by Finance Director:
Reviewe b = r
Approved by City Manager
Date:
r Date:
Toda 's Date:
Revision # and Date,Revised:
File Code:
#
5 -14 -04
S \Siaff\Castaldo \9.032 Transit Bldg\Agenda .
Bills
•
CITY OF PETALUMA, CALIFORNIA
JUNE 7, 2004
AGENDA REPORT
FOR
RESOLUTION ACCEPTINGTHE COMPLETION OF THE PETALMA,TRANSIT MAINTENANCE AND
OPERATION$ BUILDING REMODEL PROJECT NO:. 9032
1. EXECUTIVE SUMMARY
On May 14, 2004, Sonoma. ,County Builders, completed work to remodel the transit
building located at 555 North .McDowell Blvd., for a final construction cost of
$292,020.77. The total cost' of the project was $319;144.30. Sufficient funds are
available to accept and close', ouUthe project.
2. BACKGROUND
On November 17, 2003 this project was awarded to Sonoma .County Builders. The City
of Petaluma currently owns the facility located at 555 No. McDowell Blvd., previously
occupied by the Marin/Sonoma.Mosquito and Vector Control "District, and purchased
with STP /CMAC (Federal, Transportation) funds. Within the facility exists a 6,280
square foot metal frame vehicle maintenance building, which. is now occupied by the
City's fixed transit and paratransit operational staff,
Transit operations <were formerly housed in. a temporary building located within the
Kenilworth Schoot.grounds, rented on a month -to -month :basis. The original lease with
the school district for this location expired. The remodel at .555 N. McDowell Blvd. is
completed, and the entire operation has relocated to the.new site..
Not only has the remodel provided improved office, space'for our fixed route and
paratransit providers, 'it, facilitates increased coordination between the two systems,
optimizing service to riders. In,addition, both transit systems are now located on the
same site as the City staff'person providing oversight for transit operations, making it
easier to monitor and administer transit contracts'and related activities.
3. ALTERNATIVES:
a. Accept completion of the project.
4. FINANCIAL IMPACTS
The total cost of the, project was $319,144.30, including general fund overhead,
administration, design, construction and contingency. Sufficient funds are available to
accept and close out the project.
d
Estimated Costs
General Fund Overhead
Administration
Design,
Construction Management
Construction
Contingency
Total
)Funding Source:
Actual Amounts
$15,244.95
$3,666.78
$8,211.80
$0.00
$292,020.77
$0.00
$319,144.30
Public' Transportation (TDA)
•
5: CONCLUSION
The bid project cost was within the amount available for this project.
6: OUTCOMES OR PERFORMANCE 'MEASUREMENTs THAT WILL IDENTIFY SUCCESS OR
COMPLETION:
Completion of°the project.
7. RECOMMENDATION:
•
p accepting completion
A o ;f the resolution acre tin of'the construction contract authorizing- the
City Clerk to sign and file a Notice, of'Coinpletion with Sonoma County Recorder,, and
the Finance Department to release the 10% yetention to the Contractor 35 days after the
recordation of 'the Notice of Completion.
A
Resolution No. N.C.S.
of ° the :City of Petalurma, California
ACCEPTING THE COMPLETION OF THE - PETALUMA TRANSIT
MAINTENANCE AND OPERATIONS BUILDING REMODEL
PROJECT NO. `9032
WHEREAS, on November 17, 2003:, the City Council awarded to Sonoma
County Builders. The construction. contract for remodeling of an existing building
located at 555 N: McDowell. Blvd; and
WHEREAS, on May -14, 2004, Sonoma County Builders, completed all the work
to the satisfaction of the Director, Public Facilities. & S`ervices.
NOW, THEREFOR B
, E IT 'RESOLVED that the City Council of the City of
Petaluma authorizes the City Clerk to sign the Notice of Completion and file same with
Sonoma County Recorder, and that the Finance Department is hereby authorized to
release the ten percent (10 %):retention to Sonoma County Builders within thirty-five (35)
days after the recordation of the Notice of Completion.
Under-the power and::authorityconferred upon this Council; by, the Charter of said City.,
REFERENCE: I -hereby, certify the: foregoing Resolution was introduced and' `adopted by the Approved as to
Council ' of the City of Petaluma at a (Regular) (Adjourned) (Special) meeting form
on 'the . ........ day of .............. ........ ........., 20......, by the
following vote;, ........ ...............................
City Attorney
AYES:
W ES:
ABSENT:
ATTEST: .................................. : ......................... .:........................................... ................................................................. ...............................
City Clerk Mayor
Council File ..... .....................:......:..
Res. No., .................................. N.CS. '