HomeMy WebLinkAboutAgenda Bill 09.A-Memo 01/06/2003JAN 8 2003
CITY OF PETALUMA, CALIFORNIA
MEMORANDUM
Water Resources and Conservation Department, Il English St., Petaluma, CA 94952
(707) 778 -4304 Fax (707) 776 -3635 E -mail: dwrc @cipetaluma.ca us
DATE: . December 16, 2002
TO: Michael Ban
FROM: Tom Hargis��
SUBJECT: Status Report — Corps of Engineers Payran Reach Flood Control Project
The following is a brief status report on the Corps project for the City Council meeting of
January 6, 2003.
1. Current Construction
A. The current construction project involves removal of . earth and sediment from
under the Payran and Lakeville Street vehicular bridges, which has been
completed.
B. Installation of 30 inch storm drain pipe in Madison Street from Vallejo to Payran
Street: as of Monday, December 16, 2002, one storm drain inlet at the Payran and
Madison intersection has yet to be installed, as well as the permanent trench
paving.
C. Installation of flap gate on the existing storm drain discharging into the Petaluma
River at the Lakeville Street Bridge. The Corps is evaluating a value- engineering
proposal from the contractor prior to proceeding with installation.
D. Installation of a generator in the Jess Avenue storm drain pump station: the
Corps' contractor is awaiting arrival of the generator from the supplier.
The estimated cost for this phase of work (Items A — D above) is $1,300,000.00.
2. Slide repair /trapezoidal channel after the construction of the trapezoidal channel there
was an embankment slip out adjacent to Madison Village Townhomes. The Corps has
prepared contract documents for repair of the slide, but is holding the bid process until
late winter /early spring so that the slide repair can be done during the summer months.
Estimated cost: $500,000.00.
3. Mainline railroad track relocation the next major phase of work will be to build the
approaches to the new mainline railroad bridge over the Petaluma River adjacent to
December 16, 2002
Page 2
Lakeville Street. As part of that work, there will be excavation of river material under the
old and the new railroad bridges, completion of the flood wall where the existing railroad
bridge is and demolition of the existing mainline railroad bridge. 'The project has been
delayed in order to accommodate Sonoma -Marin Area Rail Transit's (SMART's) request
for a higher design'speed, i.e., 45mph rather than 30mph as future passenger trains enter
and depart Petaluma over the new mainline railroad bridge. As of Monday, December
16, 2002, the Corps is negotiating with a civil engineering firm for modification of the
existing plans to accommodate SMART's request. It is anticipated that the project'will
go to bid in the spring and be-completed by the end of calendar year 20.03. The estimated
cost is $3;600,000.00.
4. The last phase of work the industrial railroad track is an alternative to replacing the
existing downstream spur line railroad bridge. If approvals can be received from all the
various railroad authorities, aline coming off the main line on the southerly side of the
Petaluma River would be installed. Additional work would be demolition. of the existing
railroad bridge, additional channel excavation, and installation of riprapping at the
downstream end of the U- shaped sheet pile wall, "as well as any incidental cleanup on the
remainder of the project. The estimated cost is $3.2 million.
5.' Funding , an additional $10.7 million is needed for the Corps' budget to complete
construction of the project, as well as reimbursement to the-City of Petaluma. The City
has received two $1.5 mmillion reimbursement checks from the Corps of Engineers and is
anticipating an additional $3 million check at any time. This would bring the City's
reimbursement to $6 million of an estimated $6.8 million. The additional reimbursement
to the City will take place after completion of the project and the final .costs are known.*
Through the City's lobbying efforts in Washington, D.C., the current proposed
Presidential budget includes $4 million for the Corps project. The House Appropriations
Bill contains $8.5 million for the 'Corps project and the Senate Appropriations Bill
includes $10.7 million (enough to complete the project). Our latest conversations with
Washington, D.C. indicate a uncertainty as to resolution of the federal budget
stalemate. The federal government is working under a continuing ; resolution which
would allow continued construction activity, i.e., the slide repair and mainline railroad
bridge project to continue. The irdustrial alternative to replacement of the drill line
bridge will be dependent upon Congressional funding. The City of Petaluma has been
front ending the design costs for the industrial lead in order to avoid waiting until federal
funds are again secured in. order to continue to evaluate this significant cost- saving
alternative.
6. Right -of=Way Issues the City, through :its Right =of -Way Agent, Geoff.•Hornsby, has
procured four of the nine right -of -ways necessary, for the mainline railroad bridges, is ..
close to securing three others, and is resolving property owner issues on two remaining
properties. Preliminary discussions are taking place with two affected property owners
for the industrial lead alternative and the appraisal process is beginning on the one
downstream property easement needed for the demolition and riprap stabilization at the
spur line bridge downstream of the U- shaped channel portion of the project. 0
December 16, 2002
Page 3 -
7. Remaining issues
A) There is surplus property that 'could be disposed of once the Corps project is
completed. These are. miscellaneous, odd - shaped properties left over from channel
widening, home relocation, access road construction and pump station site
development. These will be brought to the City Council in the future for direction
to staff for possible abandonment to eliminate future City maintenance expenses.
B. The Corps has developed a Draft Operation and Maintenance Manual which is
being reviewed by the Sonoma County Water Agency (SCWA) and the City. A
future agreement will transfer a portion of the project's maintenance responsibility
to SCWA.
TH:dfb
xc: Paul Marangella
S: /C1P/Drainage/9989 -1999 CNRR Mainline Bridge Replacement/12 -16 -02 Status Mmo to MB
•