HomeMy WebLinkAboutResolution 2009-034 N.C.S. 03/16/2009Resolution No. 2009-034 N.C.S.
of the City of Petaluma, California
APPROVING A REVISED PROJECT BUDGET
FOR THE WASHINGTON STREET 16-INCH WATER MAIN AND SEWER CURED-
IN-PLACE PIPELINE PROJECT (C501008) AND AUTHORIZING THE CITY
MANAGER TO EXECUTE AMENDMENT N0.2 TO THE PROFESSIONAL DESIGN
SERVICES AGREEMENT WITH WINZLER & KELLY FOR ADDITIONAL
CONSTRUCTION MANAGEMENT SERVICES TO ACCOUNT FOR
UNANTICIPATED UTILITY CONFLICTS
WHEREAS., on June 2, 2008, City Council awarded the construction contract for the
Washington Street 16-inch Water Main and Sewer Cured-In-Place Pipeline Project to Team
Ghilotti, Inc., and authorized execution of a professional design services agreement with Winzler
& Kelly for inspection and construction management services; and,
WHEREAS, construction commenced on June 23rd, 2008; and,
WHEREAS, during construction a significant number of unmarked, unknown and
incorrectly marked underground utilities were encountered which hampered construction
progress; and,
WHEREAS, the City temporarily suspended the project on August 29, 2008, through the
holiday season, in order to avoid a conflict with construction of the "D" Street Bridge
Rehabilitation Project; and,
WHEREAS, the presence of unknown utilities has added 23 working days to the project
schedule for which the contractor must be compensated; and,
WHEREAS, the suspension of work has added 20 working days to the project schedule
for mobilization and demobilization for which the contractor must be compensated; and,
NOW, THEREFORE, BE IT RESOLVED that the Petaluma City Council hereby:
Resolution No. 2009-034 N.C.S. Nage
1. Increases the project budget by $267,315.49, which increases the total project budget
amount from $1,460,000 to $1,727,315.49.
2. Authorizes the City Manager to execute Amendment No. 2 to the professional design
services agreement with Winzler & Kelly in the amount of $153,585 for additional
inspection and construction management services.
Under the power and authority conferred upon this Council by the Charter of said City.
REFERENCE: I hereby certify the foregoing Resolution was introduced and adopted by the
Council of the City of Petaluma at a Regular meeting on the 16`h day of March,
2009, by the following vote:
AYES: Vice Mayor Barrett, Glass, [-iarris, Healy, Rabbitt, Renee, Mayor Torli
NOES: None