DATE`. June 18, 2012 .
TO: Honorable Mayor:and Members of the City Couneil through City Manager
FROM Dan St..John, F.ASCE —.Director, Public Works & UtiIO�
Joseph Rye—Transportation Manager
SUBJECT'.- Resolution Approving the Project Budget and Authorizing,Award of Contract for
. the Petaluma.TransitFacility Rehabilitation Phase I Project to R.E. West Builders,
Inc.
•
RECOMMENDATION
ENDATION
It-is requested that City Council adopt the resolution approving the projec •budget and
authorizing award of contract for the Petaluma Transit'Facility Rehabilitation Phase I Project to
R.E. West Builders, Inc..
•
,BACKGROUND
Phase I of the referenced project began with development of a master plan for the future use of
the transit facility at 555'N::McDowell and proceeded into design ofanupgrade of the existing
maintenance building'to enable indoor repair and maintenance of transit buses, and installation of
a drive through,bus wash. With S i million in additional,State of Good:Repair(SGR) funding, the
project was expanded to includeelements,originallyslated for Phase II: Phase I will complete all
improvements desired!on the Maintenance Building and a separate Phase II project, scheduled
next year, will improve thegroundsand parking lot areas. The current:Phase I Transit Facility
Rehabilitation project will.now:
q Reduce the existing maintenance building's footprint„and replace the southerly half of •
thedbuilding with anew.two bay, high roofed, pre-engineered building,
• Improvelighting, heating, and ventilation in the maintenance area,
• Replace the roof on the existing northerly half of the maintenance building'to remain,
•
• Relocate'the parts room, mechanic's office, traffic signal and street light:shop within the
maintenance build ing,
o Improve the-most\deteriorated patches offheezisting parking lot, and
• Improve transit:operator offices and dispatch space. •
Agenda Review: 'n/
City Attorney 1 1////���'�J(: Finance Director City Manager
•
The work includes demolition of the southerl halt of the;exis`tin maintenance:buildin , and
Y' g.` g
add-on:structures.on the westerly side which currently`house the parts:room and mechanic's.
office., Interior modifications to the remainmg,(northerly,),end include a new parts room, offices
for'the mechanic and operationsistaff, a new workshop and storage-area for the traffic technician.
A new, pre-engineered metal building erected to replace portions of the southerly end of the
building, will wide bays that will be taller than the existing structure, to enable
indoor maintenance of longer and taller modern transit buses.
DISCUSSION
Through a design consiiltant;.,Public Works & Utilities staffprepared'the hid documents and the
Notice Inviting Bids Was:issued on May 9, 2012. 3 bids were received on June 6, 2012, as
follows:
Name of Bidder Base Bid Amount
R.E. West Builders, Inc., Santa Rosa $1,390,594.00
A.E.Nelson Construction, Rohhert:Park $1,489,700.00
Dahl, Taylor and Associates, Inc., Santa Ana $1,595,000.00
Engineer's estimate $1,100;000:00
R.E. West Builders, Inc:is the apparent low bidder. Staff has verified that R.E. West possesses a
valid California Contractor's License, Class B, number B 883183 that qualifies R.E. West to
perform the Project. R.E. West has performed similar work"for"various public agencies
including the City of Berkeley.and Lake County, and has done projects,in Petaluma at Petaluma
Valley Hospital and Basin Street'.Properties. Staff recommends authorizing the City Manager to
enter into a contract with the low bidder, R.E. West Builders, Inc., for the base bid for a total
contract award of$1,390,594.
The proposed action meets Council Goal: "Plan for and implement.priority capital projects as
funding permits".
FINANCIAL:IMPACTS'
The project is 100%,,grant-fiinded and-therefore will-have-no fiscal impact to Petaluma Transit's
operating budget or the geheral fund. Minor energy and maintenance cost savings are
anticipated as a-result of new construction with more energy efficient equipment.
2
•
the following is.a'breakdown of the project budget`
FTA SGR' = TDA ` Total Approved Revised Project
• . Grants Match. • Fundint CIP:Bud.et Bud et
Design •90;400 - '22;600' 113,000 163,000 113,000
Planning& 3000 •• 7;800' 39;000 42,000 39,000
Environmental
Construction 1,139;200.' 284,800' 1,424,000 1,300,000 1,424,000
Contract
Construction .30;400* 7'600 38,000 52,000 38,000
Management & -
Inspection •
Contingency 801000' 120,000_ 100,000 139,000 100,000
OP 281800; 7;200 36,000 54,000 36,000•
Overhead/Salaries • • _
TOTAL = • '1;1140000" ,2350,000. 1,750;000 1,750,000 1,750,000
The estimated total project cost of Phase I,including planning, design, construction,
. administration, inspection, testing and contingency:is++:$1,689,000. The project will be
80% funded:by Federal Transit Administration (FTA) State of Good Repair (SGR) funds, with
the requisite 20% local match coming:from Petaluma Transit's Transportation Development Act
(TDA) reserves. All unused FTA:SGR and the committed TDA local matching funds from
Phase 1 will be used to design'and construct the Phase 2•project. This project is included in the
2012-2013 Budgetand•CIP which was approved by City•Council on June 4, 2012.
ATTACHMENTS
1. Resolution
•
•
3
Attachment 1
RESOLUTION APPROVING THE;PROJECT BUDGET AND
AUTHORIZING THE AWARD OF CONTRACT THE PETALUMA
TRANSIT'FACILITY REHABILITATION PROJECT R:E. WEST
, BUILDERS, INC.
WHEREAS, City staff' has prepared construction bid documents and advertised for
construction of this Project; and
•
WHEREAS, in accordance with the City of Petaluma Charter and Municipal Code,
California Public Contract Code:Section 20162 and other applicable law, City staff solicited bids
for the Project; and
WHEREAS, the Project was bid on May 9, 2012, and bids were received and opened
in accordance with applicable law; and •
WHEREAS, the lowest bid for the Project was from RE. West Builders, Inc., ("R.E.
West") for $1,3'90,594_for the base bid;and
• WHEREAS, staff has determined that R.E. West's bid satisfies the bidding requirements
for the Project; and
WHEREAS, stdif has verified that R.E. West possesses a valid California Contractor's
License, Class B, number B 883183 thatqualifies R.E. West to perform the Project; and
•
WHEREAS, the Project is exempt pursuant:to California Environmental Quality Act
("CEQA") pursuant to Title 14, the California Code of Regulations ("CEQA Guidelines"),
Section 15301, as the minor alteration of existing public_ facilities with negligible or no
expansion in use.
NOW, THEREEORE,.BE IT RESOLVED that the City Council of the City hereby:
1. Approves the Project Budget in the amount. of $1,559,000 including a construction
contingency of$100,000.
2. In accordance with the City of Petaluma Charter and Municipal:Code, California Public
Contract '.Code Section. 20162 and other applicable law, waives any and all non-
• conformance in the bid of RE. West Builders, Inc: for the Petaluma Transit Facility
Rehabilitation Phase I':project, finds the bid of$1,390,594 to be the lowest, responsive
bid and further-find's that.R.E. West Builders, Inc.,is`,the;lowest responsible bidder.
3. Awards the contract for,the Petaluma Transit Facility Rehabilitation Phase I project to
R.E. West Builders, Inc., in the amount of $1,390,594, the 'amount of the lowest
responsive bid, conditioned on RE: West timely executing the project contract and
submitting all required documents, including but not limited to, executed bonds,
certificates of insurance, and endorsements, in accordance with the project bid
documents.
4: Directs staff toy issue a-notice of award to R.E. West Builders, Inc.
4
•
5. Authorizes and directs the City,Manager to execute the project contract on behalf of the
City.of Petaluma upon timely submission by RE West o`fthe signed project contract and
all other required documents, includingsbut not limited to, executed bonds, certificates of
insurance,.and endorsements, in accordance with the project bid documents.
•
•
5