RESOLUTION ACCEPTING COMPLETION OF THE TEMPORARY FIRE STATION PROJECT
(C11502435) AT 307 PETALUMA BOULEVARD SOUTH AND THE FIRE STATION NO. 2 ONSITE
ASPHALT PAVING PROJECT (C11501911) TO ARNTZ BUILDERS INC. AND AUTHORIZING
RELEASE OF RETENTION
WHEREAS, on July 7 2025, the City Council adopted Resolution No. 2025-090 N.C.S. awarding a construction
contract to Arntz Builders Inc. in the amount of $2,558,425 for the Temporary Fire Station Project (C11502435) and
the Fire Station No. 2 Onsite Asphalt Paving Project (C11501911); and
WHEREAS, the contract work has been completed in accordance with the plans and specifications, to the
satisfaction of the Public Works Department and The Petaluma Fire Department; and
WHEREAS, Contract Change Order No. 01 was issued to reconcile scope modifications and final measured
quantities, resulting in a net decrease of $3,112; and
WHEREAS, the final Contract Amount for the project is $2,555,313.00; and
WHEREAS, the combined projects were completed without use of construction contingency funds and were
delivered within the approved project budget.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Petaluma as follows:
1. Finds that the Recitals set forth above are true and correct and are incorporated herein by reference.
2. Accepts the Temporary Fire Station Project (C11502435) and Fire Station No. 2 Onsite Asphalt Paving Project
(C11501911) as complete.
3. Authorizes the City Clerk to file a Notice of Completion with the Sonoma County Recorder’s Office.
4. Authorizes the City Manager, or designee, to release retention in accordance with Public Contract Code Section
7107 following expiration of the statutory lien period and confirmation that all contract requirements have been
satisfied.
5. Finds that this action has already been evaluated for compliance with the California Environmental Quality Act
(CEQA) when the project was awarded and was found to be exempt from CEQA pursuant to Class 1, Class, 3,
Class 4, and Class 32. Acceptance and release of retention fall within this previous determination and is
regardless an administrative action that does not have a significant impact on the environment.
//
//
//
//
Docusign Envelope ID: 9400E630-5134-434A-A104-56587BF7A596
Resolution No. 2026-026 N.C.S. Page 2 of 2
Under the power and authority conferred upon this Council by the Charter of said City.
REFERENCE: I hereby certify the foregoing Resolution was introduced and adopted by the
Council of the City of Petaluma at a Regular meeting on the 16th day of March
2026, by the following vote:
Approved as to
form:
__________________________
City Attorney
AYES: McDonnell, Barnacle, Cader Thompson, DeCarli, Nau, Quint, Shribbs
NOES: None
ABSENT: None
ABSTAIN: None
ATTEST: ______________________________________________
City Clerk
______________________________________________
Mayor
Docusign Envelope ID: 9400E630-5134-434A-A104-56587BF7A596